Registered No litigation declared Residential / Group Housing project

VED HEIGHTS

By PRAFUL NARENDRA DESHMUKH

RG-MH-07771 · RERA P50500014030 · Last updated on MahaRERA portal: 10 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 48 months
  • 2 extensions taken
  • Rs 6.60 crore secured on the land, in favour of Indian Overseas Bank
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
7 of 11Construction stages donefurthest along: Installation of Lifts, 99%
6 of 26Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 203 documents Report an error

VED HEIGHTS is a Residential / Group Housing project by PRAFUL NARENDRA DESHMUKH in Nagpur, Maharashtra, registered with MahaRERA as P50500014030 on 7 Nov 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 20 of the 26 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameVED HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • Cement Road
    • Shivaji Nagar
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440010
  • Pincode440010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500014030
  • ReraGenie IDRG-MH-07771

Builder

  • NamePRAFUL NARENDRA DESHMUKH
  • Entity typeIndividual

Key dates

this monthRegisteredNov 2017First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Nov 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed203 files

Current status

77%20 of 26 units booked
99.0%Work done, per cost certificate

Figures as on 10 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VED HEIGHTSNA121026026

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 99%.

VED HEIGHTS: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%

Progress on shared amenities15

As on 10 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes99%
Electrical meter room, sub-station, receiving stationYes99%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed57

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots57
Closed/Covered1
Open Space56

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,337 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofIndian Overseas Bank
Secured amountRs 6.60 crore
CERSAI search filedYes
Declared on10 Jul 2025

Approvals and building plan

Sanctioning authorityNagpur Municipal Corporation
Permissible FSI1791.0
Proposed, not sanctioned1,791 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAMDASPETH NAGPUR 440025
Estimated costRs 15.12 cr
Cost incurredRs 14.97 cr
Work done99.0%
BuildingWingEstimatedIncurred
VED HEIGHTSNARs 9.07 crRs 8.98 cr
-NARs 6.05 crRs 5.99 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPranav Ajay Lakhotiya
EngineerRAKESH SURESH MARASKOLHE
Chartered AccountantSuresh A Kewalramani
Chartered AccountantSwarupa s Wazalwar
Chartered AccountantShikha Kodwani
Chartered AccountantAtul Bhaiyya
PartnerRole in project
PRAFUL NARENDRA DESHMUKH-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500017053Dec 2022 → Dec 2024

Reason as filed by the promoter1) After the impact of the pandemic, the increasing prices of the construction materials such as cement, steel, copper, electrical, plumping and paints resulted in the shortage of the progress of new multi-storied apartment projects. We suffering from delays in terms of the number of days it takes for the arrival of the Construction Material on the project site after placing the order for the same. 2) Also, our Construction activities slowed down has slowed down due to an acute shortage of workers such as masons, earth workers, carpenters, plumbers and others. Except for a few, most of the mig

EA20072621807Dec 2022 → Dec 2026

Reason as filed by the promoterOur project was earlier granted an extension of 2 years, from 30/12/2022 to 31/12/2024, due to the adverse impact of the pandemic and financial constraints. We had simultaneously applied revised construction permissions for additional construction area, including 3 extra floors on 03-02-2023 to utilize the remaining FSI. The revised sanction plan for these extra floors was finally approved by Nagpur Municipal Corporation on 08/07/2024. Thisdelay in approval for revised plan consumed valuable 17 months out of 24 months, ie 75% of the extended time to complete the project. The Part Occupancy Cer

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Oct 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Oct 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Oct 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Oct 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed203

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 203 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_FY 26-27 Q1 signed.pdf10 Sep 2026
Withdrawal Update Form 2File: Form 2_FY 26-27 Q1 signed.pdf10 Sep 2026
Withdrawal Update Form 3File: Form 3_FY 26-27 Q1 signed.pdf10 Sep 2026
Form 2A (FY 2025-2026)File: VH FORM 2A 2025-26_SIGNED.pdf10 Sep 2026
Withdrawal Update Form 1File: Form 1 Q4 FY 25-26 _signed.pdf9 Sep 2026
Withdrawal Update Form 1File: Form 1 Q4 FY 25-26 _signed.pdf9 Sep 2026
Withdrawal Update Form 2File: Form 2 Q4 FY 25-26 _signed.pdf9 Sep 2026
Withdrawal Update Form 2File: Form 2 Q4 FY 25-26 _signed.pdf9 Sep 2026
Withdrawal Update Form 3File: Form 3 Q4 FY 25-26 _signed.pdf9 Sep 2026
Withdrawal Update Form 3File: Form 3 Q4 FY 25-26 _signed.pdf9 Sep 2026
Withdrawal Update Form 1File: Form 1 Q1 FY 25-26 _SIGNED.pdf8 Sep 2026
Withdrawal Update Form 1File: Form 1 Q2 FY 25_26 _signed.pdf8 Sep 2026
Withdrawal Update Form 1File: Form 1 Q3 FY 25-26 _Signed.pdf8 Sep 2026
Withdrawal Update Form 2File: Form 2 Q1 FY 25-26_Signed.pdf8 Sep 2026
Withdrawal Update Form 2File: Form 2 Q2 FY 25_26 _signed.pdf8 Sep 2026
Withdrawal Update Form 2File: Form 2 Q3 FY 25-26 _Signed.pdf8 Sep 2026
Withdrawal Update Form 3File: Form 3 Q1 FY 25-26_Signed.pdf8 Sep 2026
Withdrawal Update Form 3File: Form 3 Q2 FY 25_26_signed.pdf8 Sep 2026
Withdrawal Update Form 3File: Form 3 Q3 FY 25-26 _Signed.pdf8 Sep 2026
Form 1File: Form 1_Q4_24-25.pdf3 Sep 2026
Form 2File: Form 2_Q4_24-25.pdf3 Sep 2026
Form 3File: Form 3 FY 2024-25 Q4.pdf3 Sep 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold Q4 FY 2024-25 V2.pdf3 Sep 2026
Form 1File: Form 1_Q1_24-25.pdf13 Jul 2026
Form 2File: Form 2_Q1_24-25.pdf13 Jul 2026
Form 3File: Form 3_Q1_24-25.pdf13 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold_Q1_24-25.pdf13 Jul 2026
Form 1File: Form 1_Q2_24-25.pdf13 Jul 2026
Form 2File: Form 2_Q2_24-25.pdf13 Jul 2026
Form 3File: Form 3 Q2 24-25.pdf13 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold_Q2_24-25.pdf13 Jul 2026
Form 1File: Form 1_Q3_24-25.pdf13 Jul 2026
Form 2File: Form 2_Q3_24-25.pdf13 Jul 2026
Form 3File: Form 3 Q3 24-25.pdf13 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold_Q3_24-25.pdf13 Jul 2026
Form 1File: Form 1_Q2_23-24.pdf11 Jun 2026
Form 2File: Form 2_Q2_23-24.pdf11 Jun 2026
Form 3File: Form 3_Q2_2023-24.pdf11 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold_Q2_23-24.pdf11 Jun 2026
Form 1File: Form 1_Q3_23-24.pdf11 Jun 2026
Form 2File: Form 2_Q3_23-24.pdf11 Jun 2026
Form 3File: Form 3_Q3_2023-24.pdf11 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold_Q3_23-24.pdf11 Jun 2026
Form 1File: Form 1_Q4_23-24.pdf11 Jun 2026
Form 2File: Form 2_Q4_23-24.pdf11 Jun 2026
Form 3File: Form 3_Q4_2023-24.pdf11 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold_Q4_23-24.pdf11 Jun 2026
Form 5 (FY 2023-2024)File: Form 5_2023-24.pdf20 Dec 2025
Form 5 (FY 2017-2018)File: FORM 5 17-18.pdf20 Dec 2025
Form 5 (FY 2018-2019)File: FORM 5 18-19.pdf20 Dec 2025
Form 2A (FY 2017-2018)File: Form 2A_2017-18.pdf18 Dec 2025
Form 2A (FY 2018-2019)File: Form 2A_2018-19.pdf18 Dec 2025
Form 2A (FY 2019-2020)File: Form 2A_2019-20.pdf18 Dec 2025
Form 2A (FY 2020-2021)File: Form 2A_2020-21.pdf18 Dec 2025
Form 2A (FY 2021-2022)File: Form 2A_2021-22.pdf18 Dec 2025
Form 2A (FY 2022-2023)File: Form 2A_2022-23.pdf18 Dec 2025
Form 2A (FY 2023-2024)File: Form 2A_2023-24.pdf18 Dec 2025
Form 2A (FY 2024-2025)File: Form 2A_2024-25.pdf18 Dec 2025
Form 5 (FY 2019-2020)File: FORM 5 19-20.pdf16 Dec 2025
Form 5 (FY 2020-2021)File: Form 5 20-21.pdf16 Dec 2025
Form 5 (FY 2021-2022)File: Form 5 21-22.pdf16 Dec 2025
Form 5 (FY 2022-2023)File: Form 5 22-23.pdf16 Dec 2025
Form 1File: Form 1_Q4_17-18.pdf29 Sep 2025
Form 2File: Form 2_Q4-17-18.pdf29 Sep 2025
Form 3File: Form 3_Q4_2017-18.pdf29 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold & Unsold_Q4_17-18.pdf29 Sep 2025
Form 1File: Form 1_Q4_17-18.pdf29 Sep 2025
Form 2File: Form 2_Q4-17-18.pdf29 Sep 2025
Form 3File: Form 3_Q4_2017-18.pdf29 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold & Unsold_Q4_17-18.pdf29 Sep 2025
Form 1File: Form 1_Q2_18-19.pdf29 Sep 2025
Form 2File: Form 2_Q2_18-19.pdf29 Sep 2025
Form 3File: Form 3_Q2_2018-19.pdf29 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold & Unsold_Q2_18-19.pdf29 Sep 2025
Form 1File: Form 1_Q3_18-19.pdf29 Sep 2025
Form 2File: Form 2_Q3_18-19.pdf29 Sep 2025
Form 3File: Form 3_Q3_2018-19.pdf29 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold & Unsold_Q3_18-19.pdf29 Sep 2025
Form 1File: Form 1_Q4_18-19.pdf29 Sep 2025
Form 2File: Form 2_Q4_18-19.pdf29 Sep 2025

How this compares with Nagpur

77%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 48 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VED HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shivaji Nagar2,800+ in Nagpur

2 kmVED HEIGHTSCompleted 26Lapsed / revoked 16Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 78 registered projects within 2 km.

Builder: PRAFUL NARENDRA DESHMUKH

PRAFUL NARENDRA DESHMUKH has 1 registration on MahaRERA, including VED HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if VED HEIGHTS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VED HEIGHTS?

The registered promoter entity is PRAFUL NARENDRA DESHMUKH, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VED HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VED HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VED HEIGHTS?

The professionals named in the filing: Architect: Pranav Ajay Lakhotiya; Engineer: RAKESH SURESH MARASKOLHE; Chartered Accountant: Suresh A Kewalramani; Chartered Accountant: Swarupa s Wazalwar; Chartered Accountant: Shikha Kodwani; Chartered Accountant: Atul Bhaiyya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VED HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VED HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VED HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.