Home / Browse projects / Bengaluru Rural, Karnataka / Varnam Phase 1A

Registration approved No litigation declared Residential/Group Housing project

Varnam Phase 1A

By ONE BANGALORE LUXURY PROJECTS LLP

RG-KA-02053 · RERA PRM/KA/RERA/1250/303/PR/110825/007988 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2030Possession promisedno revision filed
1 of 17Construction stages donefurthest along: Foundation footing work, 40%
0 of 48Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 172 documents Report an error

Varnam Phase 1A is a Residential/Group Housing project by ONE BANGALORE LUXURY PROJECTS LLP in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/110825/007988 on 11 Aug 2025. Possession is promised by 31 Aug 2030. 48 of the 48 units on this registration are recorded sold or booked, and 1 of 17 construction stages are filed complete.

At a glance

Project

  • NameVarnam Phase 1A
  • TypeResidential/Group Housing
  • Location
    • Devanahalli
    • Bengaluru Rural
    • 562157
  • Pincode562157
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/303/PR/110825/007988
  • ReraGenie IDRG-KA-02053

Builder

  • NameONE BANGALORE LUXURY PROJECTS LLP
  • Entity typePartnership Firm
  • GSTIN29AAEFO5442Q1ZL
  • Authorized SignatoryVishram Marathe
  • Other registrations7 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2025PromisedAug 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on11 Aug 2025
  • Promised completion31 Aug 2030
  • Revised completionNone
  • Buildings4 building records
  • Documents filed172 files

Current status

100%48 of 48 units booked
13.4%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RH---24024
TH1---808
TH2---808
TH3---808

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 17 construction stages are filed complete. The stage furthest along is Foundation footing work, at 40%.

Building: 9% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work40%
Upto Plinth Level20%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)Not applicable
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymNoNot applicable
ParksYes0%
Power BackupYes0%
Piped GasYes0%
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes20%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallNoNot applicable
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesYes0%

Land and ownership8

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,125 sq m
Named landowners8
LandownerVillageDistrict
MS Ramaiah Realty LLP--
MS Ramaiah Realty LLP--
MS Ramaiah Realty LLP--
MS Ramaiah Realty LLP--
MS Ramaiah Realty LLP--
MS Ramaiah Realty LLP--
MS Ramaiah Realty LLP--
MS Ramaiah Realty LLP--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 87.09 cr
Cost incurredRs 11.64 cr
Spent of the estimate13.37%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 74.36 crRs 8.27 cr
Administrative CostsRs 6.22 cr-
On-site expenditure-Consultants FeesRs 4.73 crRs 3.00 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 91.59 lakh-
Payment of taxesRs 86.85 lakhRs 37.18 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSrimathi J Adiga
EngineerVishnu Kumar
Chartered AccountantMutra Rajasekhar Reddy

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed172

As listed on the registration, under the names the promoter filed them with; the newest 80 of 172 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/110825/007988 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 VARNAM PHASE 1A Q2 26-27.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-5 VARNAM PHASE 1A Q2 26-27.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 VARNAM PHASE 1A Q2 26-27.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Varnam Phase 1A Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Varnam Phase 1A Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Varnam Phase 1A Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 VARNAM PHASE 1A Q4 25-26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM-5 VARNAM PHASE 1A Q4 25-26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 VARNAM PHASE 1A Q4 25-26.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Varnam 1A Q3 25-26.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Varnam 1A Q3 25-26.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Varnam 1A Q3 25-26.pdf14 Jan 2026
Clarification on JDA Sy No Phase-1AFile: 1 Clarification on JDA Sy No Phase-1A.pdf8 Aug 2025
Mother Conversion OrdersFile: 2 Mother Conversion Orders.pdf8 Aug 2025
First Amendment to JDAFile: 3 First Amendment to JDA.pdf8 Aug 2025
Second Amendment to JDAFile: 4 Second Amendment to JDA.pdf8 Aug 2025
Third Amendment to JDAFile: 5 Third Amendment to JDA.pdf8 Aug 2025
Clarification on Terrace AreaFile: 6 Clarification on Terrace Area.pdf8 Aug 2025
Allotment Letter Varnam Ph 1AFile: 8 Allotment Letter Varnam Ph 1A.pdf8 Aug 2025
Clarification on Source of Water Phase 1AFile: 9 Clarification on Source of Water Phase 1A.pdf8 Aug 2025
SEIAA NOC Valid oneFile: 10 SEIAA NOC Valid one.pdf8 Aug 2025
Screenshots from EC (SEIAA) websiteFile: 11 Screenshots from EC website.pdf8 Aug 2025
AREA BIFURCATION Details VarnamFile: 12 AREA BIFURCATION Details Varnam.pdf8 Aug 2025
Panchayath Water NOCFile: 13 Panchayath Water NOC.pdf8 Aug 2025
Land Calculation Sheet Varnam Phase 1AFile: 14 Land Calculation Sheet Varnam Phase 1A.pdf8 Aug 2025
Title ReportFile: 15 Title Report.pdf8 Aug 2025
ITR FY 2023-24File: 16 ITR FY 2023-24.pdf8 Aug 2025
AFS_Varnam Phase 1A_V2File: 7 AFS_Varnam Phase 1A_V2.pdf8 Aug 2025
Mortgage DeedFile: 17 Mortgage Deed.pdf8 Aug 2025
RTC, survey 1/P-
Mutation, survey 1/P-
Encumbrance Certificate, survey 1/P-
Conversion/Alienation Order, survey 1/P-
Sale/Title/Gift Deed, survey 1/P-
JDA, survey 1/P-
Khatha, survey 1/P-
RTC, survey 2/2-
Mutation, survey 2/2-
Encumbrance Certificate, survey 2/2-
Conversion/Alienation Order, survey 2/2-
Sale/Title/Gift Deed, survey 2/2-
JDA, survey 2/2-
Khatha, survey 2/2-
RTC, survey 7/P-
Mutation, survey 7/P-
Encumbrance Certificate, survey 7/P-
Conversion/Alienation Order, survey 7/P-
Sale/Title/Gift Deed, survey 7/P-
JDA, survey 7/P-
Khatha, survey 7/P-
RTC, survey 37/1-
Mutation, survey 37/1-
Encumbrance Certificate, survey 37/1-
Conversion/Alienation Order, survey 37/1-
Sale/Title/Gift Deed, survey 37/1-
JDA, survey 37/1-
Khatha, survey 37/1-
RTC, survey 37/2-
Mutation, survey 37/2-
Encumbrance Certificate, survey 37/2-
Conversion/Alienation Order, survey 37/2-
Sale/Title/Gift Deed, survey 37/2-
JDA, survey 37/2-
Khatha, survey 37/2-
RTC, survey 37/4-
Mutation, survey 37/4-
Encumbrance Certificate, survey 37/4-
Conversion/Alienation Order, survey 37/4-

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date2 under way, not due yet1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
RAAGAM PHASE-IISY. NO. 37/1(P), 37/2(P), 37/4(P), 37/5(P), 37/7(P), 37/10(P), 37/13 (P) & 37/16(P) OF , AKKALENAHALLI-MALLENAHALLI VILLAGE , KASABA HOBLI , Devanahalli , Bengaluru Rural, Karnataka - 562157OngoingJun 2028Not due yet
RAAGAM PHASE-1SY. NO. 37/1(P), 37/2(P), 37/4(P), 37/5(P), 37/7(P), 37/10(P), 37/13 (P) & 37/16(P) OF AKKALENAHALLI-MALLENAHALLI VILLAGE , KASABA HOBLI , Devanahalli , Bengaluru Rural, Karnataka - 562157OngoingDec 2026Not due yet
SWARAM PHASE-2Sy. No. 1(P) & 37/2(P) of JODI AKKALENA HALLI - MALLENA HALLI VILLAGE , KASABA HOBLI , Devanahalli , Bengaluru Rural, Karnataka - 562129OngoingMar 2026Not delivered
SWARAM PHASE-1Sy. No. 1(P) & 37/2(P) of JODI AKKALENA HALLI - MALLENA HALLI VILLAGE , KASABA HOBLI , Devanahalli , Bengaluru Rural, Karnataka - 562129Completed-No date filed

How this compares with Bengaluru Rural

100%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Varnam Phase 1A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmVarnam Phase 1AOther 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: ONE BANGALORE LUXURY PROJECTS LLP

ONE BANGALORE LUXURY PROJECTS LLP has 8 registrations on RERA Karnataka, including Varnam Phase 1A and Varnam Phase 1B. Its filings declare 4 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Varnam Phase 1A is delayed beyond 31 Aug 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Varnam Phase 1A?

The registered promoter entity is ONE BANGALORE LUXURY PROJECTS LLP, a partnership firm as per the filing. Its GSTIN 29AAEFO5442Q1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Varnam Phase 1A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Varnam Phase 1A?

The professionals named in the filing: Architect: Srimathi J Adiga; Engineer: Vishnu Kumar; Chartered Accountant: Mutra Rajasekhar Reddy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Varnam Phase 1A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Varnam Phase 1A. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Varnam Phase 1A to a free account