Home / Browse projects / Mumbai Suburban, Maharashtra / VARDHMAN EMPIRE

Completed No litigation declared Residential / Group Housing project

VARDHMAN EMPIRE

By VARDHMAN DEVELOPERS LTD

RG-MH-00510 · RERA P51800006315 · Last updated on MahaRERA portal: 23 Jul 2021

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2020Possession promisedregistration recorded completed
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
2Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

VARDHMAN EMPIRE is a Residential / Group Housing project by VARDHMAN DEVELOPERS LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006315 on 14 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2020. The completion date has moved by 24 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameVARDHMAN EMPIRE
  • TypeResidential / Group Housing
  • Location
    • 1ST DOMINIC LANE
    • ORLEM
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006315
  • ReraGenie IDRG-MH-00510

Builder

  • NameVARDHMAN DEVELOPERS LTD
  • Entity typeCompany
  • ChairpersonRAMESH BABULAL VARDHAN
  • Managing DirectorRAJESH BABULAL VARDHAN
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Aug 2017
  • Promised completion30 Dec 2020
  • Revised completionRevised to 30 Dec 2020 (originally 31 Dec 2018)
  • Buildings2 building records
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA100000
B WINGNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

A WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed31

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots31
Closed/Covered31
BuildingClosed/CoveredTotal
A WING1515
B WING1616

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,751 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NEW EMPIRE CO-OP, HSG. SOCIETY LTD.BorivaliMumbai Suburban

Approvals and building plan

Permissible FSI4710.03
Proposed, not sanctioned4,710 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 2 AND 3 ATLANTA BUILDING , GROUND FLOOR, NARIMAN POINT, MUMBAI 400 021

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTEEARCH
EngineerMS R.D.MAGDUM
PartnerRole in project
VARDHMAN DEVELOPERS LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000888Dec 2018 → Jun 2020

Reason as filed by the promoter1. DCPR 2034 - TDR could not be loaded due to the implication of new DCPR 2034. 2. SWM NOC - Delay has been attributed due to the matter being sub-judice in the Hon’ble Supreme Court and subsequently, Bank Guarantee was submitted for getting the further approvals. 3. Due to unavailability of input material mainly sand and other material.

EXT51800005168Dec 2018 → Jun 2020

Reason as filed by the promoterThe project has 2 wings - A wing and B wing. We had received the Full IOD & CC for A wing and for B wing we have received the full IOD only on 9.9.2019 due to DCR 2034 implementation, thereafter we had tried to complete the project within the stipulated time as per RERA. We have already received the OC for A wing on 3.12.2019 and have completed 90% of work in B wing as on date. The Balance 10% work in B wing will take an approx. 3 more months and we shall be able to get the OC thereafter. Therefore we request the Authority to kindly grant us the extension for the period of 6 months upto 30.6.2

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000192841Melville DcunhaVardhman Developers Limited03/03/2020
CC006000000193347Indira SuvarnaVardhman Developers27/06/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Oct 2020

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf23 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2255319_OC_signed.pdf20 Oct 2020
Building plan approvalFile: 1.pdf23 Dec 2019
Building plan approvalFile: Drawing_Part2.pdf23 Dec 2019
Building plan approvalFile: Drawing_Part3.pdf23 Dec 2019
Building plan approvalFile: 2226190Amendletter_signed.pdf23 Dec 2019
Building Plan Approval (IOD)File: 2226190Amendletter_signed.pdf23 Dec 2019
Building Plan Approval (IOD)File: 1.pdf23 Dec 2019
Building Plan Approval (IOD)File: Drawing_Part2.pdf23 Dec 2019
Building Plan Approval (IOD)File: Drawing_Part3.pdf23 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: 2230236_FurtherCC_signed.pdf23 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Malad OC.pdf23 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EMPIRE-min.pdf1 Oct 2019
Certificates of CA (Form 5)File: Empire (3).pdf1 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC Approved.pdf3 May 2019
Certificates of CA (Form 5)File: form 5.pdf8 Jan 2019
Certificates of CA (Form 3)File: Empire (2) (1).pdf6 Nov 2018
Building plan approvalFile: DRAWING-compressed.pdf2 Nov 2018
Building plan approvalFile: IOD SEPT 2017.pdf2 Nov 2018
Building Plan Approval (IOD)File: DRAWING-compressed.pdf2 Nov 2018
Building Plan Approval (IOD)File: IOD SEPT 2017.pdf2 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: 2105571_furthercc_signed.pdf2 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Certificate (1).pdf2 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Empire Engineers Certificate.pdf2 Nov 2018
Certificates of CA (Form 3)File: ca CERTIFICATE WITH annexure.pdf30 Jul 2017
Declaration in FORM BFile: declaration.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer.pdf29 Jul 2017
Proforma of Allotment letterFile: sale agreement.pdf29 Jul 2017
Building plan approvalFile: SCAN1376.pdf28 Jul 2017
Building Plan Approval (IOD)File: SCAN1376.pdf28 Jul 2017
Layout approvalFile: layout.pdf27 Jul 2017
Details of encumbrancesFile: no encum.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: layout.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf27 Jul 2017
Building plan approvalFile: 1.pdf26 Jul 2017
Building plan approvalFile: 2.pdf26 Jul 2017
Building plan approvalFile: 3.pdf26 Jul 2017
Building plan approvalFile: 4.pdf26 Jul 2017
Building plan approvalFile: 5.pdf26 Jul 2017
Building plan approvalFile: 6.pdf26 Jul 2017
Building Plan Approval (IOD)File: 1.pdf26 Jul 2017
Building Plan Approval (IOD)File: 2.pdf26 Jul 2017
Building Plan Approval (IOD)File: 3.pdf26 Jul 2017
Building Plan Approval (IOD)File: 4.pdf26 Jul 2017
Building Plan Approval (IOD)File: 5.pdf26 Jul 2017
Building Plan Approval (IOD)File: 6.pdf26 Jul 2017
Building plan approvalFile: IOD.pdf17 Jul 2017
PAN CardFile: VDL PAN CARD.pdf17 Jul 2017
Copy of the legal title reportFile: title.pdf17 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf17 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf17 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VARDHMAN GALAXYMUMBAI74CompletedDec 2014Late, Oct 2015
VARDHMAN VISTAMUMBAI38CompletedApr 2014Late, Oct 2014

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VARDHMAN EMPIRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ORLEM6,700+ in Mumbai Suburban

2 kmVARDHMAN EMPIRECompleted 152Lapsed / revoked 101Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 405 registered projects within 2 km.

Builder: VARDHMAN DEVELOPERS LTD

VARDHMAN DEVELOPERS LTD has 6 registrations on MahaRERA, including VARDHMAN EMPIRE and VARDHMAN GRANDEUR. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if VARDHMAN EMPIRE is delayed beyond 30 Dec 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VARDHMAN EMPIRE?

The registered promoter entity is VARDHMAN DEVELOPERS LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VARDHMAN EMPIRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VARDHMAN EMPIRE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VARDHMAN EMPIRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VARDHMAN EMPIRE?

The professionals named in the filing: Architect: TEEARCH; Engineer: MS R.D.MAGDUM. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VARDHMAN EMPIRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VARDHMAN EMPIRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VARDHMAN EMPIRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.