ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / VARDAAN HEIGHTS

Registered No litigation declared Others project

VARDAAN HEIGHTS

By DINESH RAJKUMAR ANAJE

RG-MH-30112 · RERA P52000030005 · Last updated on MahaRERA portal: 23 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 45 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 45 months from the original
4 of 11Construction stages donefurthest along: Internal walls, 90%
8 of 16Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

VARDAAN HEIGHTS is a Others project by DINESH RAJKUMAR ANAJE in Raigarh, Maharashtra, registered with MahaRERA as P52000030005 on 20 Jul 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 45 months from the original filing. 8 of the 16 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameVARDAAN HEIGHTS
  • TypeOthers
  • Location
    • SEC 25 A
    • PUSHPAK
    • Wahal
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000030005
  • ReraGenie IDRG-MH-30112

Builder

  • NameDINESH RAJKUMAR ANAJE
  • Entity typeIndividual
  • GSTIN27AHEPA2267N2Z8

Key dates

this monthRegisteredJul 2021First promiseMar 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Jul 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2023)
  • Buildings1 building record
  • Documents filed49 files

Current status

50%8 of 16 units booked
95.0%Work done, per cost certificate

Figures as on 23 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VARDAAN HEIGHTSNA7416016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

VARDAAN HEIGHTS: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes60%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered3
Open Space3

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area230 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Declared on17 Sep 2024
LandownerVillageDistrict
BALIRAM KOLIKhargharRaigarh
RAJAN KOLIUlaweRaigarh

Approvals and building plan

Sanctioning authorityCity And Industrial Development Corporation Of Maharashtra Ltd
Permissible FSI344.62
Proposed, not sanctioned345 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCBD BELAPUR
Estimated costRs 1.38 cr
Cost incurredRs 1.31 cr
Work done95.0%
BuildingWingEstimatedIncurred
VARDAAN HEIGHTSNARs 1.38 crRs 1.31 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKEDAR SATAM ARCHITECTS
EngineerB A SUKTHANKAR AND ASSOCIATES
EngineerImpact Designerr
EngineerKOMAL MAHENDRA PAWAR
Chartered AccountantJ B PATEL AND ASSOCIATES
Chartered AccountantManish K Ramawati & Company
Chartered AccountantSingh Ranjan & Co
Chartered AccountantM.S K Hemant & CO
PartnerRole in project
DINESH RAJKUMAR ANAJE-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000017291Mar 2023 → Mar 2024

Reason as filed by the promoterThe project was delayed for reasons beyond our control on account of various unforeseen events.

EXT52000025133Mar 2023 → Sep 2025

Reason as filed by the promoterwe have mentioned in details why we want extension till 31-09-2025 and how we can complete our project till 30-09-2025

EA12092502577Mar 2023 → Dec 2026

Reason as filed by the promoter1) Poor booking response from customer. 2) Because of poor response our work was very slow.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Vardan 30-06-2026.pdf23 Jul 2026
Withdrawal Update Form 2File: FORM 2 Vardan 30-06-2026.pdf23 Jul 2026
Withdrawal Update Form 3File: FORM 3 Vardan 30-06-2026.pdf23 Jul 2026
Withdrawal Update Form 1File: Form 1 - 30-09-2025.pdf20 Jun 2026
Withdrawal Update Form 1File: FORM 1 Vardan 31-12-2025.pdf20 Jun 2026
Withdrawal Update Form 1File: FORM 1 Vardan 31-03-2026.pdf20 Jun 2026
Withdrawal Update Form 2File: FORM 2 Vardan 30-09-2025.pdf20 Jun 2026
Withdrawal Update Form 2File: FORM 2 Vardan 31-12-2025.pdf20 Jun 2026
Withdrawal Update Form 2File: FORM 2 Vardan 31-03-2026.pdf20 Jun 2026
Withdrawal Update Form 3File: FORM 3 Vardan 30-09-2025 Signed.pdf20 Jun 2026
Withdrawal Update Form 3File: FORM 3 Vardan 31-12-2025 Signed.pdf20 Jun 2026
Withdrawal Update Form 3File: FORM 3 Vardan 31-03-2026.pdf20 Jun 2026
Form 1File: Form 1 30-06-25.pdf12 Sep 2025
Form 2File: FORM 2 Vardan 30-06-2025.pdf12 Sep 2025
Form 3File: FORM 3 Vardan 30-06-2025.pdf12 Sep 2025
Disclosure of Sold and Booked InventoryFile: sold unsold 30-06-25.pdf12 Sep 2025
Form 1File: Form 1.pdf12 Sep 2025
Form 2File: FORM 2 Vardan 31-03-2025.pdf12 Sep 2025
Form 3File: FORM 3 Vardan 31-03-2025.pdf12 Sep 2025
Disclosure of Sold and Booked InventoryFile: sold unsold 31-03-25.pdf12 Sep 2025
Form 2A (FY 2021-2022)File: Form 2A Sys G 21-22.pdf12 Sep 2025
Form 2A (FY 2022-2023)File: Form 2A Sys G 22-23.pdf12 Sep 2025
Form 2A (FY 2023-2024)File: Form 2A Sys G 23-24.pdf12 Sep 2025
Form 2A (FY 2024-2025)File: Form 2A Sys G 24-25.pdf12 Sep 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: to upload.pdf14 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE.pdf12 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A_2022.pdf2 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A_2023.pdf2 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3.pdf24 Jan 2024
Declaration in FORM BFile: Form B.pdf11 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5_final.pdf3 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf28 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf28 Jul 2023
Disclosure of sold/ booked inventoryFile: disclosure.pdf28 Jul 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT CC.pdf2 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE (1).pdf2 Jul 2021
Copy of the legal title reportFile: Search n title report.pdf1 Jul 2021
Declaration in FORM BFile: Form B - Dinesh Anaje (1).pdf16 Jun 2021
Layout approvalFile: PLAN.pdf15 Jun 2021
Building plan approvalFile: PLAN.pdf15 Jun 2021
PAN CardFile: DINESH ANAJE - PANCARD.pdf15 Jun 2021
Details of encumbrancesFile: Encumbrance certificate.pdf15 Jun 2021
Copy of Layout Approval (in case of layout)File: PLAN.pdf15 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN.pdf15 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf15 Jun 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 1.pdf15 Jun 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate (1).pdf15 Jun 2021
Proforma of Allotment letterFile: ALLOTMENT LETTER -.pdf15 Jun 2021
Proforma of Allotment letterFile: model Agreement.pdf15 Jun 2021

How this compares with Raigarh

50%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 45 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VARDAAN HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUSHPAK5,900+ in Raigarh

2 kmVARDAAN HEIGHTSCompleted 79Lapsed / revoked 29Other 106Dot size: filed unitsN

Filed coordinates, straight-line distance. 214 registered projects within 2 km.

Builder: DINESH RAJKUMAR ANAJE

DINESH RAJKUMAR ANAJE has 1 registration on MahaRERA, including VARDAAN HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if VARDAAN HEIGHTS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VARDAAN HEIGHTS?

The registered promoter entity is DINESH RAJKUMAR ANAJE, an individual as per the filing. Its GSTIN 27AHEPA2267N2Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VARDAAN HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VARDAAN HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VARDAAN HEIGHTS?

The professionals named in the filing: Architect: KEDAR SATAM ARCHITECTS; Engineer: B A SUKTHANKAR AND ASSOCIATES; Engineer: Impact Designerr; Engineer: KOMAL MAHENDRA PAWAR; Chartered Accountant: J B PATEL AND ASSOCIATES; Chartered Accountant: Manish K Ramawati & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VARDAAN HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VARDAAN HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VARDAAN HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.