ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / VAMANASHRAM

Registered No litigation declared Residential / Group Housing project

VAMANASHRAM

By VAMANASHRAM CO-OPERATIVE HOUSING SOCIETY LIMITED

RG-MH-06241 · RERA P51800052574 · Last updated on MahaRERA portal: 10 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedmoved 24 months from the original
8 of 11Construction stages donefurthest along: Installation of Lifts, 85%
1 of 20Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 68 documents Report an error

VAMANASHRAM is a Residential / Group Housing project by VAMANASHRAM CO-OPERATIVE HOUSING SOCIETY LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800052574 on 11 Sep 2023. Possession is promised by 31 Mar 2028. The completion date has moved by 24 months from the original filing. 19 of the 20 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameVAMANASHRAM
  • TypeResidential / Group Housing
  • Location
    • OF TPS BORIVALI NO. III
    • OFF DR. GIRIJA P. HEBLE MARG
    • SHIMPOLI ROAD
    • BORIVALI WEST
    • Shimpoli
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • RERA no.P51800052574
  • ReraGenie IDRG-MH-06241

Builder

  • NameVAMANASHRAM CO-OPERATIVE HOUSING SOCIETY LIMITED
  • Entity typeSociety
  • ChairpersonSATISH DEVIDAS UDIAVER
  • SecretoryGOURANG JAYANT MUDBIDRI

Key dates

this monthRegisteredSep 2023First promiseMar 2026Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2023
  • Promised completion31 Mar 2028
  • Revised completionRevised to 31 Mar 2028 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed68 files

Current status

95%19 of 20 units booked
82.6%Work done, per cost certificate

Figures as on 10 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VAMANASHRAMNA8720020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 85%.

VAMANASHRAM: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 10 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes75%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed27

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots27
Closed/Covered27

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area897 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Jul 2025
LandownerVillageDistrict
THE VISAWA CHARITABLE TRUSTShimpoliMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2401.29
Proposed, not sanctioned1,682 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVAZIRA NAKA
Estimated costRs 15.52 cr
Cost incurredRs 12.82 cr
Work done82.64%
BuildingWingEstimatedIncurred
-NARs 8.02 crRs 6.85 cr
VAMANASHRAMNARs 7.50 crRs 5.97 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNIRMITHI
EngineerMr. Girish T. Wadhwa
EngineerNIRMITHI
Chartered AccountantNEHALI & CO
Chartered AccountantNEHALI DHAVAL DOSHI
Chartered AccountantNIRANJAN S. KARMARKAR & ASSOCIATES
PartnerRole in project
VAMANASHRAM CO-OPERATIVE HOUSING SOCIETY LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA27032620396Mar 2026 → Mar 2028

Reason as filed by the promoter1. Charity Commissioner's NOC was granted after almost one year after application for the same was made without which the Society could not have started. 2. The inspection after the Plinth Construction was delayed almost 3 months due to General Elections in the year 3. The only access road to the plot through which all construction material was being transported, was being concretized, so work of proposed building was practically stopped. 4. Now we are facing a problem in construction of the Compound Wall (IOD Requirement) on North side of our building due to the objection taken by the neighbo

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed68

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1.pdf10 Jul 2026
Withdrawal Update Form 110 Jul 2026
Withdrawal Update Form 2File: Engineer_s_Certificate_Form_2_Jun_26_Finishing_stage.pdf10 Jul 2026
Withdrawal Update Form 210 Jul 2026
Withdrawal Update Form 3File: form 3.pdf10 Jul 2026
Withdrawal Update Form 310 Jul 2026
Withdrawal Update Form 1File: Architect Certificate - Mar 26.pdf13 Apr 2026
Withdrawal Update Form 2File: Engineer Certificate - Mar 26.pdf13 Apr 2026
Withdrawal Update Form 3File: CA Certificate Mar 26.pdf13 Apr 2026
Withdrawal Update Form 1File: Architect Certificate - Dec 25.pdf5 Mar 2026
Withdrawal Update Form 2File: forrm 2.pdf5 Mar 2026
Withdrawal Update Form 3File: form 3.pdf5 Mar 2026
Withdrawal Update Form 1File: Architect Certificate Form-1 Sept 25.pdf30 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate Form-2 Sept 25.pdf30 Oct 2025
Withdrawal Update Form 3File: Signed CA Certificate Form-3 Sept 25.pdf30 Oct 2025
Form 2A (FY 2024-2025)File: vananashram for 2 a.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: C A Certificate in Annexure F FORM 5.pdf30 Sep 2025
Commencement certificateFile: FurtherCC_signed.pdf29 Jul 2025
Building plan approvalFile: Amended Plan Approval Letter.pdf29 Jul 2025
Building plan approvalFile: Approved Plan.pdf29 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf9 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf9 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf9 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf15 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 23-24.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf4 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf4 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf4 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf3 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 03 24.pdf12 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 03 24.pdf11 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 03 24.pdf11 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate Dec 23.pdf15 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineers Certificate Dec 23.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA Certificate Dec 23.pdf15 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1 - Sep 23.pdf12 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2 - Sep 23.pdf12 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Sep 23.pdf12 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Sep 23 1_compressed.pdf12 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Vamanashram CHSL - Format A.pdf25 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vamanashram CHSL - CA Report (1).pdf19 Jul 2023
Proforma of Allotment letterFile: DRAFT ALLOTMENT LETTER (1).pdf19 Jul 2023
Proforma of Agreement for saleFile: AGREEMENT FOR SALE NEW.pdf19 Jul 2023
Deviation Report with respect to Allotment letterFile: No Deviation report allotment letter (1).pdf19 Jul 2023
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement.pdf19 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A DOI.pdf6 Jul 2023
Building plan approvalFile: 15 - IOD_signed_12052023.pdf29 Jun 2023
Layout approvalFile: Approved Plan 1-2.pdf29 Jun 2023
Layout approvalFile: Approved Plan 3-4.pdf29 Jun 2023
Layout approvalFile: Approved Plan 5.pdf29 Jun 2023
PAN CardFile: VCHS PAN Card.pdf29 Jun 2023
Copy of the legal title reportFile: VCHS Clear Title Certificate (2)_1-30.pdf29 Jun 2023
Details of encumbrances concerned to FinanceFile: No Encumbrance Certificate.pdf29 Jun 2023
Details of encumbrances concerned to LegalFile: No Encumbrance Certificate.pdf29 Jun 2023
Copy of Layout Approval (in case of layout)File: Approved Plan 1-2.pdf29 Jun 2023
Copy of Layout Approval (in case of layout)File: Approved Plan 3-4.pdf29 Jun 2023
Copy of Layout Approval (in case of layout)File: Approved Plan 5.pdf29 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 15 - IOD_signed_12052023.pdf29 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: 16 - FirstCC_signed.pdf29 Jun 2023
Declaration about Commencement CertificateFile: Declaration of Commencement Certificate.pdf29 Jun 2023
Declaration in FORM BFile: From-B.pdf29 Jun 2023
CERSAI detailsFile: CERSAI Declaration (2).pdf29 Jun 2023

How this compares with Mumbai Suburban

95%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VAMANASHRAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORIVALI WEST6,700+ in Mumbai Suburban

Builder: VAMANASHRAM CO-OPERATIVE HOUSING SOCIETY LIMITED

VAMANASHRAM CO-OPERATIVE HOUSING SOCIETY LIMITED has 1 registration on MahaRERA, including VAMANASHRAM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if VAMANASHRAM is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VAMANASHRAM?

The registered promoter entity is VAMANASHRAM CO-OPERATIVE HOUSING SOCIETY LIMITED, a society as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VAMANASHRAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VAMANASHRAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VAMANASHRAM?

The professionals named in the filing: Architect: NIRMITHI; Engineer: Mr. Girish T. Wadhwa; Engineer: NIRMITHI; Chartered Accountant: NEHALI & CO; Chartered Accountant: NEHALI DHAVAL DOSHI; Chartered Accountant: NIRANJAN S. KARMARKAR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VAMANASHRAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VAMANASHRAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VAMANASHRAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.