Home / Browse projects / Mumbai Suburban, Maharashtra / VALLETTA

Registered Litigation declared Residential / Group Housing project

VALLETTA

By K RAHEJA CORP REAL ESTATE PRIVATE LIMITED

RG-MH-80471 · RERA P51800046901 · Last updated on MahaRERA portal: 17 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Litigation declared, 3 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 250.00 crore secured on the land, in favour of Standard Chartered Bank

Clear

  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
3 of 3Construction stages doneevery applicable stage filed complete
14 of 25Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 134 documents Report an error

VALLETTA is a Residential / Group Housing project by K RAHEJA CORP REAL ESTATE PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046901 on 16 Sep 2022. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 12 months from the original filing. 11 of the 25 units on this registration are recorded sold or booked, and 3 of 3 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVALLETTA
  • TypeResidential / Group Housing
  • Location
    • JUHU TARA ROAD
    • VILE PARLE WEST
    • Andheri
    • Mumbai Suburban
    • 400049
  • Pincode400049
  • RERA no.P51800046901
  • ReraGenie IDRG-MH-80471

Builder

  • NameK RAHEJA CORP REAL ESTATE PRIVATE LIMITED
  • Entity typeCompany
  • CINU40300MH2007PTC287012
  • GSTIN27AABCF1838M1ZF
  • DirectorsSUNIL MADHAV HINGORANI, RAMESH RANGANATHAN, RAVI CHANDRU RAHEJA, NEEL CHANDRU RAHEJA
  • Company SecretoryJIGNASHA CHETAN THAKKAR
  • Other registrations20 more →
  • Completed1 of 21
  • No longer live8 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

1 months past promisethis monthRegisteredSep 2022First promiseSep 2025Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Sep 2022
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Sep 2025)
  • Buildings1 building record
  • Documents filed134 files

Current status

44%11 of 25 units booked
79.5%Work done, per cost certificate

Figures as on 17 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VALLETTANA161425025

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 3 construction stages are filed complete.

VALLETTA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes50%
Street LightingYes90%
Community BuildingsYes95%
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes60%
Open ParkingNoNot applicable

Parking filed72

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots72
Closed/Covered72

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,200 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofStandard Chartered Bank
Secured amountRs 250.00 crore
Declared on19 May 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI8300.0
Proposed, not sanctioned7,422 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCrescenzo Building, Bandra Kurla Complex, Bandra East, Mumbai 400051
Estimated costRs 72.69 cr
Cost incurredRs 57.77 cr
Work done79.47%
BuildingWingEstimatedIncurred
VALLETTANARs 67.22 crRs 57.19 cr
-NARs 5.46 crRs 57.23 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectG K Vanwari
EngineerVaibhav Samarth
EngineerRupesh Kanakia
Chartered AccountantS N Doshi & Associates
Chartered AccountantAKPJ & Associates
Chartered AccountantG.M. Kapadia & Co.
Chartered AccountantG M Kapadia & Co
PartnerRole in project
K RAHEJA CORP REAL ESTATE PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017908Sep 2025 → Sep 2026

Reason as filed by the promoterThe Project Site is situated in the residential zone of Juhu Village and is surrounded by old residential buildings. The Project Site is adjacent to the seacoast. After initiating the construction works on Project Site, Promoter has at the excavation stage encountered unforeseen difficulties thereby delaying the milestone completion dates. The difficulties are broadly setout as under: (a) while carrying out the piling work i.e. before commencing the excavation work, the Project Site experienced higher water ingress through sub soil due to its proximity to the sea which had slowed down the pili

Litigation declared3

CaseCourtStatus
1383/2008Bombay High CourtClosed
5/2006Small Causes Court BandraClosed
1383/2008Bombay High CourtOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600056Bhakti AchrekarK RAHEJA CORP REAL ESTATE PRIVATE LIMITED11/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Oct 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed134

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 134 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 1 Architects Certificate 2026-01-05 VALLETTA Dec2025 KRCREPL UPLOAD.pdf17 Jul 2026
Withdrawal Update Form 1File: 1 Architects Certificate 2026-01-05 VALLETTA Dec2025 KRCREPL UPLOAD.pdf17 Jul 2026
Withdrawal Update Form 2File: 2 Engineering Certificate 2026-01-15 VALLETTA Dec2025 krcrepl UPLOAD.pdf17 Jul 2026
Withdrawal Update Form 2File: 2 Engineering Certificate 2026-01-15 VALLETTA Dec2025 krcrepl UPLOAD.pdf17 Jul 2026
Withdrawal Update Form 3File: 3 CA Certificate 2026-07-16 VALLETTA Dec2025 UPLOAD.pdf17 Jul 2026
Withdrawal Update Form 3File: 3 CA Certificate 2026-07-16 VALLETTA Dec2025 UPLOAD.pdf17 Jul 2026
Form 2A (FY 2025-2026)File: 2A Engineers Quality Assurance Certificate FY 25-26 Valletta UPLOAD.pdf8 Jun 2026
Withdrawal Update Form 1File: 1 Architects Certificate 2025-07-10 VALLETTA Jun2025 KRCREPL UPLOAD.pdf13 Apr 2026
Withdrawal Update Form 1File: 1 Architects Certificate 2025-07-10 VALLETTA Jun2025 KRCREPL UPLOAD.pdf13 Apr 2026
Withdrawal Update Form 2File: 2 Engineering Certificate 2025-07-15 VALLETTA Jun2025 krcrepl UPLOAD.pdf13 Apr 2026
Withdrawal Update Form 2File: 2 Engineering Certificate 2025-07-15 VALLETTA Jun2025 krcrepl UPLOAD.pdf13 Apr 2026
Withdrawal Update Form 3File: 3 CA Certificate 2025-08-06 VALLETTA Jun2025 krcrepl UPLOAD.pdf13 Apr 2026
Withdrawal Update Form 3File: 3 CA Certificate 2025-08-06 VALLETTA Jun2025 krcrepl UPLOAD.pdf13 Apr 2026
Withdrawal Update Form 1File: 1 Architects Certificate 2025-07-10 VALLETTA Jun2025 KRCREPL UPLOAD.pdf9 Jan 2026
Withdrawal Update Form 1File: 1 Architects Certificate 2025-07-10 VALLETTA Jun2025 KRCREPL UPLOAD.pdf9 Jan 2026
Withdrawal Update Form 2File: 2 Engineering Certificate 2025-07-15 VALLETTA Jun2025 krcrepl UPLOAD.pdf9 Jan 2026
Withdrawal Update Form 2File: 2 Engineering Certificate 2025-07-15 VALLETTA Jun2025 krcrepl UPLOAD.pdf9 Jan 2026
Withdrawal Update Form 3File: 3 CA Certificate 2024-08-06 VALLETTA Jun2025 krcrepl UPLOAD.pdf9 Jan 2026
Withdrawal Update Form 3File: 3 CA Certificate 2024-08-06 VALLETTA Jun2025 krcrepl UPLOAD.pdf9 Jan 2026
Building plan approvalFile: Valletta Amended Approval 2025-07-11 Letter UPLOAD.pdf10 Oct 2025
Building plan approvalFile: Valletta Amended Approval 2025-07-11 Drawings Part1 UPLOAD.pdf10 Oct 2025
Building plan approvalFile: Valletta Amended Approval 2025-07-11 Drawings Part2 UPLOAD.pdf10 Oct 2025
Withdrawal Update Form 1File: 1 Architects Certificate 2025-07-10 VALLETTA Jun2025 KRCREPL UPLOAD.pdf10 Oct 2025
Withdrawal Update Form 2File: 2 Engineering Certificate 2025-07-15 VALLETTA Jun2025 krcrepl UPLOAD.pdf10 Oct 2025
Withdrawal Update Form 3File: 3 CA Certificate 2024-08-06 VALLETTA Jun2025 krcrepl UPLOAD.pdf10 Oct 2025
Form 5 (FY 2024-2025)File: 5 Valletta FY 2024-25 KRCREPL Form5 Report-Annx1-Annx2 UPLOAD.pdf29 Sep 2025
Withdrawal Update Form 1File: 1 Architects Certificate 2025-07-10 VALLETTA Jun2025 KRCREPL UPLOAD.pdf12 Aug 2025
Withdrawal Update Form 2File: 2 Engineering Certificate 2025-07-15 VALLETTA Jun2025 krcrepl UPLOAD.pdf12 Aug 2025
Withdrawal Update Form 3File: 3 CA Certificate 2024-08-06 VALLETTA Jun2025 krcrepl UPLOAD.pdf12 Aug 2025
Withdrawal Update Form 1File: 1 Architects Certificate 2025-04-15 VALLETTA Mar2025 KRCREPL UPLOAD.pdf23 Jul 2025
Withdrawal Update Form 2File: 2 Engineering Certificate 2025-04-15 VALLETTA Mar2025 krcrepl UPLOAD.pdf23 Jul 2025
Withdrawal Update Form 3File: 3 CA Certificate 2024-07-22 VALLETTA Mar2025 krcrepl UPLOAD.pdf23 Jul 2025
Withdrawal Update Form 1File: 1 Architects Certificate 2025-01-14 VALLETTA Dec2024 KRCREPL UPLOAD.pdf15 Jul 2025
Withdrawal Update Form 2File: 2 Engineering Certificate 2025-01-14 VALLETTA Dec2024 krcrepl UPLOAD.pdf15 Jul 2025
Withdrawal Update Form 3File: 3 CA Certificate 2025-01-14 VALLETTA Dec2024 krcrepl UPLOAD.pdf15 Jul 2025
Form 2A (FY 2024-2025)File: 2A Engineer's Quality Assurance Certificate FY 24-25 Valletta UPLOAD.pdf19 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Valletta Self Declaration on Form 1-2-3 Q4 FY25 UPLOAD.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Valletta Self Declaration on Form 1-2-3 Q4 FY25 UPLOAD.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Valletta Self Declaration on Form 1-2-3 Q4 FY25 UPLOAD.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: Valletta Inventory 2025-03-31 UPLOAD.pdf17 Apr 2025
Home Buyer /Allottee Grievance Redressal CellFile: Valletta - Greivance Cell and Complaints Status Q4FY25 UPLOAD.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architects Certificate 2025-01-14 VALLETTA Dec2024 KRCREPL UPLOAD.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 CA Certificate 2025-01-14 VALLETTA Dec2024 krcrepl UPLOAD.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineering Certificate 2025-01-14 VALLETTA Dec2024 krcrepl UPLOAD.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Valletta Inventory 2024-12-31 UPLOAD.pdf17 Jan 2025
Home Buyer /Allottee Grievance Redressal CellFile: Valletta - Status of Complaints Q3FY25 UPLOAD.pdf17 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Valletta CC-3 (updated) 2024-11-12 UPLOAD.pdf19 Nov 2024
Declaration about Commencement CertificateFile: CC Declaration Valletta 2024-11-18 UPLOAD.pdf19 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: Valletta CC-3 (updated) 2024-11-12 UPLOAD.pdf19 Nov 2024
Declaration about Commencement CertificateFile: CC Declaration Valletta 2024-11-18 UPLOAD.pdf19 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Valletta Self Declaration on Form 1-2-3 Q2 FY25 UPLOAD.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Valletta Self Declaration on Form 1-2-3 Q2 FY25 UPLOAD.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Valletta Self Declaration on Form 1-2-3 Q2 FY25 UPLOAD.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Valletta Inventory 2024-09-30 UPLOAD.pdf18 Oct 2024
Other - FinanceFile: Valletta Self-Certification for No Withdrawal No Deposit 2024-10-17 UPLOAD.pdf18 Oct 2024
Home Buyer /Allottee Grievance Redressal CellFile: Valletta - Status of Complaints Q2FY25 UPLOAD.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 5 Valletta FY 2023-24 KRCREPL Report-Annexure1-Annexure2 UPLOAD 2.pdf18 Oct 2024
Form 5 (FY 2023-2024)File: 5 Valletta FY 2023-24 KRCREPL Report-Annexure1-Annexure2 UPLOAD.pdf29 Sep 2024
Form 5 (FY 2022-2023)File: 5 Valletta FY 2022-23 KRCPL Report-Certificate-Annexures UPLOAD.pdf18 Sep 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Valletta Self Declaration on Form 1-2-3 Q1 FY25 UPLOAD.pdf17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Valletta Self Declaration on Form 1-2-3 Q1 FY25 UPLOAD.pdf17 Jul 2024
Disclosure of sold/ booked inventoryFile: Valletta Inventory 2024-06-30 UPLOAD.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Valletta Self Declaration on Form 1-2-3 Q1 FY25 UPLOAD.pdf17 Jul 2024
Home Buyer /Allottee Grievance Redressal CellFile: Valletta - Status of Complaints Q1FY25 UPLOAD.pdf17 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A Engineer's Quality Assurance Certificate FY 23-24 Valletta UPLOAD.pdf29 May 2024
Proforma of Allotment letterFile: Allotment Letter Valleta 2024-04-19 UPLOAD.pdf19 Apr 2024
Copy of the legal title reportFile: Title Report Valletta 2024-03-08 krcrepl UPLOAD.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Valletta Self Declaration on Form 1-2-3 Q4 FY24 UPLOAD.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Valletta Self Declaration on Form 1-2-3 Q4 FY24 UPLOAD.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Valletta Inventory 2024-03-31 UPLOAD.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Valletta Self Declaration on Form 1-2-3 Q4 FY24 UPLOAD.pdf17 Apr 2024
Proforma of Agreement for saleFile: AFS Valletta 2023-12-23 FINAL VERSION V6 NCLT order and revised registration dated capture17 Apr 2024
Proforma of Agreement for saleFile: AFS Valletta 2024-04-07 Revision pursuant to Demerger Clean UPLOAD.pdf17 Apr 2024
Home Buyer /Allottee Grievance Redressal CellFile: Valletta Greivance Redressal Cell with Complaints Status Q4 FY24 UPLOAD.pdf17 Apr 2024
Declaration in FORM BFile: Form B - KRCREPL (New Intending Promoter) for VALLETTA compressed UPLOAD.pdf28 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architects Certificate 2024-03-12 VALLETTA (Jan 2024) KRCREPL UPLOAD.pdf28 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineering Certificate 2024-03-13 VALLETTA (JAN 2024) krcrepl UPLOAD.pdf28 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 CA Certificate 2024-03-27 VALLETTA (Jan 2024) krcrepl UPLOAD.pdf28 Mar 2024
Other - LegalFile: NCLT Order dated 20Dec2023 Certified Copy on 04Jan2024 compressed UPLOAD.pdf28 Mar 2024
Disclosure of sold/ booked inventoryFile: Valletta Inventory 2023-12-31 UPLOAD.pdf18 Jan 2024

How this compares with Mumbai Suburban

44%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VALLETTA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILE PARLE WEST6,700+ in Mumbai Suburban

Builder: K RAHEJA CORP REAL ESTATE PRIVATE LIMITED

K Raheja Corp Real Estate Private Limited has 21 registrations on MahaRERA, including Estrella, Viva, Pirangut and Orion, Viva, Pirangut. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 16 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if VALLETTA is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VALLETTA?

The registered promoter entity is K RAHEJA CORP REAL ESTATE PRIVATE LIMITED, a company as per the filing. Its CIN U40300MH2007PTC287012 and GSTIN 27AABCF1838M1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VALLETTA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VALLETTA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VALLETTA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VALLETTA?

The professionals named in the filing: Architect: G K Vanwari; Engineer: Vaibhav Samarth; Engineer: Rupesh Kanakia; Chartered Accountant: S N Doshi & Associates; Chartered Accountant: AKPJ & Associates; Chartered Accountant: G.M. Kapadia & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VALLETTA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VALLETTA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VALLETTA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.