Completed No litigation declared Residential / Group Housing project

valera chsl

By KAMPA PROJECTS LLP

RG-MH-76415 · RERA P51800017210 · Last updated on MahaRERA portal: 5 Nov 2024

Source: official MahaRERA filing

Red flags

  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2021Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

valera chsl is a Residential / Group Housing project by KAMPA PROJECTS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800017210 on 23 Jul 2018. The registration is recorded completed; possession was promised by 30 Nov 2021.

At a glance

Project

  • Namevalera chsl
  • TypeResidential / Group Housing
  • Location
    • RAM GULLY
    • MUMBAI
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800017210
  • ReraGenie IDRG-MH-76415

Builder

  • NameKAMPA PROJECTS LLP
  • Entity typePartnership
  • PartnersBHALCHANDRA VANRAVANDAS TURAKHIA, sagar bhalchandra turakhia
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2018PromisedNov 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2018
  • Promised completion30 Nov 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NAMO HERITAGENA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

NAMO HERITAGE: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 5 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes98%
Storm Water DrainsYes98%
Landscaping & Tree PlantingYes98%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes98%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes98%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Closed/Covered50

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,166 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3470.0
Proposed, not sanctioned3,011 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchS V ROAD KANDIVALI WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRASHANT SUKHTANKAR
EngineerVATSAL GOKANI
PartnerRole in project
KAMPA PROJECTS LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800010574Nov 2021 → Apr 2022

Reason as filed by the promoterDue to the lockdown, the supply chain for obtaining construction material had been disrupted and the labours also went back to their home states. Due to these circumstances, our project were take some time to restart work.

EXT51800012691Nov 2021 → Feb 2023

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Mar 2023

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Architect form 4 (signed) (1).pdf5 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION CERTIFICATE 28-02-2023.pdf6 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC PLAN 28-02-2023_00001.pdf6 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC PLAN 28-02-2023_00002.pdf6 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC PLAN 28-02-2023_00003.pdf6 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC PLAN 28-02-2023_00004.pdf6 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC PLAN 28-02-2023_00005.pdf6 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 - 2021-22 (1).pdf19 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECT CERTIFICATE.pdf29 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A - 2022.pdf21 Oct 2022
CERSAI detailsFile: CERSAI declaration.pdf11 Oct 2022
Disclosure of sold/ booked inventoryFile: INVENTORY.pdf11 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: KAMPA-ANNUAL REPORT FY 17-18.pdf31 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: KAMPA-ANNUAL REPORT FY 18-19.pdf31 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: KAMPA-ANNUAL REPORT FY 19-20.pdf31 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: KAMPA-ANNUAL REPORT FY 20-21.pdf31 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A - 2020_compressed.pdf19 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A - 2021_compressed.pdf19 Jul 2021
Declaration about Commencement CertificateFile: DECLARATION FOR CC-compressed.pdf13 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 -- ARCHITECT CERTIFICATE-compressed.pdf13 Jul 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 -- ENGINEER CERTIFICATE.pdf13 Jul 2021
Disclosure of sold/ booked inventoryFile: BOOKED-SOLD INVENTORY.pdf21 May 2021
Layout approvalFile: 15 FLOOR.pdf27 Apr 2021
Copy of Layout Approval (in case of layout)File: 15 FLOOR.pdf27 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: 4TH --- till 15th floor.pdf27 Apr 2021
OtherFile: resolution - NAMO HERITAGE.pdf5 Mar 2021
Building plan approvalFile: Approval Letter.pdf19 Sep 2020
Building plan approvalFile: 2234615Amendletter_signed.pdf19 Sep 2020
Layout approvalFile: Drawing 01.pdf19 Sep 2020
Copy of Layout Approval (in case of layout)File: Drawing 01.pdf19 Sep 2020
Building Plan Approval (IOD)File: Approval Letter.pdf19 Sep 2020
Building Plan Approval (IOD)File: 2234615Amendletter_signed.pdf19 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: 3RD --- till 13th (pt) .pdf19 Sep 2020
Building plan approvalFile: Approval Letter.pdf2 May 2019
Building Plan Approval (IOD)File: Approval Letter.pdf2 May 2019
Commencement Certificates / NA Order for plotted developmentFile: Further CC - 1st to 5th.pdf2 May 2019
Commencement Certificates / NA Order for plotted developmentFile: Further CC - 1st to 5th.pdf2 May 2019
Layout approvalFile: DRAWING.pdf5 Jul 2018
Copy of Layout Approval (in case of layout)File: DRAWING.pdf5 Jul 2018
Certificates of CA (Form 3)File: CA CERTIFICATE -- FORM 3.pdf5 Jul 2018
Details of encumbrancesFile: ENCUMBRANCES LETTER.pdf22 Jun 2018
Declaration in FORM BFile: FORM B.pdf22 Jun 2018
Proforma of Allotment letterFile: Valera Allotment Letter.pdf22 Jun 2018
Building plan approvalFile: DRAWING.pdf21 Jun 2018
PAN CardFile: PANCARD.pdf21 Jun 2018
Copy of the legal title reportFile: TITLE REPORT.pdf21 Jun 2018
Building Plan Approval (IOD)File: DRAWING.pdf21 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: 2181504_firstcc_signed valera.pdf21 Jun 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY REGISTRATION CERTIFICATE.pdf21 Jun 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHANTI DHAM CHSLEKSAR ROAD BORIVALI WEST21CompletedJul 2015Jul 2015

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep valera chsl on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MUMBAI6,700+ in Mumbai Suburban

Builder: KAMPA PROJECTS LLP

KAMPA PROJECTS LLP has 2 registrations on MahaRERA, including valera chsl and NEW KANDIVALI CHSL. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if valera chsl is delayed beyond 30 Nov 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of valera chsl?

The registered promoter entity is KAMPA PROJECTS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in valera chsl?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for valera chsl?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at valera chsl?

The professionals named in the filing: Architect: PRASHANT SUKHTANKAR; Engineer: VATSAL GOKANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in valera chsl?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About valera chsl. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save valera chsl to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.