Home / Browse projects / Nashik, Maharashtra / VAISHNAVI PLAZA

Registered No litigation declared Commercial project

VAISHNAVI PLAZA

By TRIMURTI CONSTRUCTION

RG-MH-14224 · RERA P51600032657 · Last updated on MahaRERA portal: 16 Feb 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 36 months from the original
5 of 11Construction stages donefurthest along: External plumbing and external plaster, 80%
0Complaints at MahaRERAon this registration
Jump to the 83 documents Report an error

VAISHNAVI PLAZA is a Commercial project by TRIMURTI CONSTRUCTION in Nashik, Maharashtra, registered with MahaRERA as P51600032657 on 17 Jan 2022. Possession is promised by 25 Apr 2027. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameVAISHNAVI PLAZA
  • TypeCommercial
  • Location
    • NH3 Highway
    • ADGOAN SHIVAR
    • Nashik (M Corp.)
    • Nashik
    • 422003
  • Pincode422003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600032657
  • ReraGenie IDRG-MH-14224

Builder

  • NameTRIMURTI CONSTRUCTION
  • Entity typePartnership
  • PartnersBHAGAWATIBEN GANGARAM PATEL, MANGALABAI SATISH DEVARE, MANDA MALHARI MATE, MALHARI BHAGUJI MATE, VARSHA NILKANTH UGALE, KONDAJI BALVANT MATE, KAILAS PUNDLIK DEORE
  • Other registrations7 more →
  • Completed4 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2022First promiseApr 2024Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Jan 2022
  • Promised completion25 Apr 2027
  • Revised completionRevised to 25 Apr 2027 (originally 26 Apr 2024)
  • Buildings1 building record
  • Documents filed83 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VAISHANVI PLAZANA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 80%.

VAISHANVI PLAZA: 57% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed148

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots148
Closed/Covered120
Open Space28

Land and ownership7

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,566 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Sep 2024
LandownerVillageDistrict
Bhagawatiben Gangaram PatelNashikNashik
Manda Malhari MateNashik (M Corp.)Nashik
Mangalabai Satish DevareNashik (M Corp.)Nashik
Malhari Bhaguji MateNashik (M Corp.)Nashik
Kailas Pundlik DeoreNashik (M Corp.)Nashik
Varsha Nilkanth UgaleJopulNashik
Kondaji Balvant MateNashik (M Corp.)Nashik

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI7792.14
Proposed, not sanctioned7,792 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1 AND 2 PRITAM COMPLEX PLOT NO 9 ADGAON ROAD MUMBAI AGRA ROD NASHIK

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPankaj Jadhav
EngineerSagar Shah
Chartered AccountantNirav Shailesh Shah & Co
Chartered AccountantJaushri B Khandave & Company
PartnerRole in project
TRIMURTI CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600024666Apr 2024 → Apr 2027

Reason as filed by the promoterWe have revised our plan and hence we are applying for extension of project under section 7(3) till 25.04.2027. All the documents are prepared and uploaded as per revised plans and hence we are also applying for application for correction simultaneously. Please grant us the project extension at the earliest.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Dec 2024

Documents filed83

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2021-2022)File: Form 5 - 2021-22.pdf16 Feb 2026
Form 5 (FY 2022-2023)File: Form 5 - 2022-23.pdf16 Feb 2026
Form 5 (FY 2023-2024)File: Form 5 - 2023-24.pdf16 Feb 2026
Form 1File: Form 1 25-26 Q1.pdf11 Feb 2026
Form 2File: Form 2 25-26 Q1.pdf11 Feb 2026
Form 3File: Form 3 SD 25-26 Q1.pdf11 Feb 2026
Disclosure of Sold and Booked InventoryFile: Inventory 30-06-2025.pdf11 Feb 2026
Form 1File: Form 1 25-26 Q2.pdf11 Feb 2026
Form 2File: Form 2 25-26 Q2.pdf11 Feb 2026
Form 3File: Form 3 SD 25-26 Q2.pdf11 Feb 2026
Disclosure of Sold and Booked InventoryFile: Inventory 30-09-2025.pdf11 Feb 2026
Form 1File: Form 1 25-26 Q3.pdf11 Feb 2026
Form 2File: Form 2 25-26 Q3.pdf11 Feb 2026
Form 3File: Form 3 SD 25-26 Q3.pdf11 Feb 2026
Disclosure of Sold and Booked InventoryFile: Inventory 31-12-2025.pdf11 Feb 2026
Form 1File: Form 1 - 31-03-2025.pdf20 Jan 2026
Form 2File: Form 2 - 31-03-2025.pdf20 Jan 2026
Form 3File: Form 3 SD - 31-03-2025.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: Inventory 31-03-2025.pdf20 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q4.pdf4 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24-25 Q4.pdf4 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q4.pdf4 May 2025
Disclosure of sold/ booked inventoryFile: Inventory 31-03-2025.pdf4 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (2).pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (3).pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (4).pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q3.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (1).pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-06-24.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 24-25 Q3.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-09-24.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-09-23.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-06-23.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31-03-23.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-09-22.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (1).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (2).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (3).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (4).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (5).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q3.pdf25 Mar 2025
Building plan approvalFile: Revised SP 1.pdf24 Dec 2024
Building plan approvalFile: Revised SP 2.pdf24 Dec 2024
Declaration in FORM BFile: Form B.pdf24 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf24 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate.pdf24 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: Revised SP 1.pdf24 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: Revised SP 2.pdf24 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC.pdf24 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf24 Dec 2024
CERSAI detailsFile: Cersai Declaration.pdf24 Dec 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account.pdf24 Dec 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account.pdf24 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2021-22.pdf24 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 2022.pdf24 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf24 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 2023.pdf24 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 2022-23.pdf24 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 2024.pdf24 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 2023-24.pdf24 Dec 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: HDFC BANK BANK CHANAGE.pdf4 Feb 2023
CERSAI detailsFile: CERSAI_ Search_ Report.pdf17 Dec 2021
Proforma of Allotment letterFile: draft allotement letter.pdf9 Dec 2021
Proforma of Allotment letterFile: draft allotement letter.pdf9 Dec 2021
OtherFile: CERTIFICATE FOR.pdf9 Dec 2021
Proforma of Allotment letterFile: Trimurti Construction Vaishnavi Plaza Agreement.pdf30 Oct 2021
PAN CardFile: 1 Trimurti Construction PAN Card.pdf21 Oct 2021
Layout approvalFile: 4 VISHANVI_PLAZA__ layout.pdf8 Oct 2021
Building plan approvalFile: 5 VISHANVI_PLAZA_Building Plan Approval.pdf8 Oct 2021
Copy of the legal title reportFile: tital_report_final.pdf8 Oct 2021
Details of encumbrancesFile: Declaration for Encrumbances.pdf8 Oct 2021
Copy of Layout Approval (in case of layout)File: 4 VISHANVI_PLAZA__ layout.pdf8 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: 5 VISHANVI_PLAZA_Building Plan Approval.pdf8 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: 7 Commeancement_certificate_Vashnvi_plaza_.pdf8 Oct 2021
Declaration about Commencement CertificateFile: Format D- For Commencement.pdf8 Oct 2021
Declaration in FORM BFile: 1_Kailas_Deore final pdf.pdf8 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 ARC_JADHAV_CERTIFICATE VAISHANIVI PLAZA.pdf8 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: TRIMURTI ENGINNER.pdf8 Oct 2021

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 36 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VAISHNAVI PLAZA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ADGOAN SHIVAR4,100+ in Nashik

2 kmVAISHNAVI PLAZACompleted 43Lapsed / revoked 12Other 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 90 registered projects within 2 km.

Builder: TRIMURTI CONSTRUCTION

TRIMURTI CONSTRUCTION has 8 registrations on MahaRERA, including TRIMURTI PARK and DURVA HERITAGE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if VAISHNAVI PLAZA is delayed beyond 25 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VAISHNAVI PLAZA?

The registered promoter entity is TRIMURTI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VAISHNAVI PLAZA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VAISHNAVI PLAZA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VAISHNAVI PLAZA?

The professionals named in the filing: Architect: Pankaj Jadhav; Engineer: Sagar Shah; Chartered Accountant: Nirav Shailesh Shah & Co; Chartered Accountant: Jaushri B Khandave & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VAISHNAVI PLAZA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VAISHNAVI PLAZA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VAISHNAVI PLAZA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.