Urja Cornerstone Building 1

By Vimal Gordhanbhai Pipalia

RG-MH-20016 · RERA P52100004993 · Last updated on MahaRERA portal: 28 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 78 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
17 of 98Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 68 documents Report an error

Urja Cornerstone Building 1 is a Residential / Group Housing project by Vimal Gordhanbhai Pipalia in Pune, Maharashtra, registered with MahaRERA as P52100004993 on 9 Aug 2017. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 78 months from the original filing. 81 of the 98 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameUrja Cornerstone Building 1
  • TypeResidential / Group Housing
  • Location
    • Nashik Hwy
    • Grampanchayat
    • Chakan (CT)
    • Khed
    • Pune
    • 410501
  • Pincode410501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004993
  • ReraGenie IDRG-MH-20016

Builder

  • NameVimal Gordhanbhai Pipalia
  • Entity typeIndividual
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed68 files

Current status

83%81 of 98 units booked

Figures as on 28 Feb 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Urja Cornerstone Building 1NA9798098

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Urja Cornerstone Building 1: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes30%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes25%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed35

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots35
Closed/Covered35

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,497 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Shalan Mahadev DeshmukhChakan (CT)Pune

Approvals and building plan

Sanctioning authorityDeputy Divisional Officer
Permissible FSI4314.94
Proposed, not sanctioned4,315 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch KHARGHAR SHOP NO 46 47, PATEL HERITAGE, SECTOR 7, KHARGAR NAVI MUMBAI 410210

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/s.Vistaar Architects and Planners
EngineerM/s.Adharshila Consultant
Chartered AccountantJSSK & Co.
PartnerRole in project
Vimal Gordhanbhai Pipalia-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005256Dec 2018 → Apr 2020

Reason as filed by the promoterUrja Cornerstone Building no. 1 is completed 99% in all aspects and we will apply for OC as soon as remaining work completed, we expect OC within six months.

EXT52100000940Dec 2018 → Apr 2020

Reason as filed by the promoterOur project "Urja Cornerstone Building 1", RCC work completed 100% as per Architect Certificate. Project is delayed due to material, labour and other unavoidable reasons. we will try to complete our project by December 2019.

EXT52100010925Dec 2018 → Dec 2024

Reason as filed by the promoterTo, Maharashtra Real Estate Regulatory Authority (MAHA RERA), BKC, HousefinBhavan, Near RBI, E Block, Bandra Kurla Complex, Bandra East, Mumbai, Maharashtra 400051 Subject:- Extension of Project Date for Project “Urja Cornerstone Building 1” Dear Sir, Madam, We have registered our project “UrjaCornerstone Building 1” Located at Bearing / CTS / Survey /Final PlotNo.: Gut No.2440/1 Village Chakan Taluka Khedat Chakan (CT),Khed, Pune, 410501 vide MAHA RERA No. P52100004993 with RERA authority in the month of Aug 2017, due to COVID - 19 Pandemic scenario and overall MarketScenario has badly impact

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC005000000053834Mr.Rahul Subhash JagtapM/s Urja Developers Through its Prop Mr VImal G.Pipalia25/12/2019
CC005000000053841Mrs.Sangita pravin SolankiM/s Urja Developers through its prop Mr. Vimal G. Pipalia26/12/2019
CC005000000064786Mrs Ashwini Tushar ShindeM/s Urja Developers through its proprietor Mr.Vimal G.Pipalia31/10/2020
CC005000000064788Mrs Jyoti Prashant JadhavM/s Urja Develpers through its prop Mr.Vimal G.Pipalia31/10/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Feb 2025

Documents filed68

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Comption Certificate of Building 1.pdf28 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A FY 2022-23.pdf28 Feb 2025
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to legal.pdf27 Mar 2024
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to legal.pdf27 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A March 2020.pdf27 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March 2022.pdf27 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organisation.pdf27 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: scan form 5 builidng 1.pdf27 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 builidng 1 Signed.pdf27 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Deviation Report with respect to Allotment Letter - No Devi.pdf27 Mar 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment Letter - No Devi.pdf27 Mar 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement -.pdf27 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: URJA_DEV-1.pdf13 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: URJA_DEV-2.pdf13 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: URJA_DEV-3.pdf13 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Building no 1 certificate.pdf7 Oct 2021
Certificates of CA (Form 3)File: FORM 3 Urja building No 1 5 10 2021.pdf6 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BLDG NO 1_compressed.pdf17 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ilovepdf_merged.pdf15 Sep 2021
Details of encumbrancesFile: Cersei B1.pdf6 Sep 2021
Declaration about Commencement CertificateFile: CC1.pdf6 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: URJA CORNERSTONRE BLDG 01 --- - EC 30-06-21.pdf6 Sep 2021
Disclosure of sold/ booked inventoryFile: Dis 1.pdf6 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 - Architect's Certificate as per RERA Bldg - 1( 210825)-R1.pdf2 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BLDG NO-1 FORM 1.pdf25 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Urja Cornerstone Bldg 01 FORM 2 30-04-19.pdf25 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Urja Building 1 Arch Cer.pdf30 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Urja Building 1 Engg Cer (1).pdf30 Jan 2019
Certificates of CA (Form 5)File: Building 1 - Form 5.pdf6 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 BLDG 1- Feb 18.pdf27 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 BLDG 1- July 18.pdf27 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate bldg 1.pdf9 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineering certificate bldg 1.pdf9 Mar 2018
Details of encumbrancesFile: Encmbeance Certficate -.pdf19 Jan 2018
Declaration in FORM BFile: form B.pdf19 Jan 2018
Proforma of Allotment letterFile: Sale Agreement- Bldg 1 for RERA Updation 11 JAN 2018.pdf19 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: urja cornerstone -architect certificate-bldg no-1.pdf8 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate-bldg no-1 table -a.pdf8 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate-bldg no-1, 2, 3 table -b.pdf8 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGNIEER CERTIFICATE.pdf8 Nov 2017
Proforma of Allotment letterFile: Sale Agreement as per RERA Building 1.pdf27 Sep 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S Certificate BUILDING 01.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE BUILDING 01.pdf29 Jul 2017
Building plan approvalFile: N A ORDERPart1.pdf28 Jul 2017
Building plan approvalFile: N A ORDERPart2.pdf28 Jul 2017
Building plan approvalFile: N A ORDERPart3.pdf28 Jul 2017
Layout approvalFile: 1.pdf28 Jul 2017
Layout approvalFile: 2.pdf28 Jul 2017
Layout approvalFile: 3.pdf28 Jul 2017
Layout approvalFile: 7.pdf28 Jul 2017
PAN CardFile: pan card Vimal sir.pdf28 Jul 2017
Copy of the legal title reportFile: Title Report.pdf28 Jul 2017
Copy of the legal title reportFile: Title Report1.pdf28 Jul 2017
Copy of the legal title reportFile: Title Report2.pdf28 Jul 2017
Details of encumbrancesFile: No encumbrances Certificate Bldg 1.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: 1.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: 2.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: 3.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: 7.pdf28 Jul 2017
Building Plan Approval (IOD)File: N A ORDERPart1.pdf28 Jul 2017
Building Plan Approval (IOD)File: N A ORDERPart2.pdf28 Jul 2017
Building Plan Approval (IOD)File: N A ORDERPart3.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: N A ORDERPart1.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: N A ORDERPart2.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: N A ORDERPart3.pdf28 Jul 2017
Declaration in FORM BFile: affidavit developer building1.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf28 Jul 2017
Proforma of Allotment letterFile: affidavit for allotment agreement building 1.pdf28 Jul 2017

How this compares with Pune

83%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 78 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Urja Cornerstone Building 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Grampanchayat13,700+ in Pune

2 kmUrja Cornerstone BuildinCompleted 14Lapsed / revoked 19Other 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 61 registered projects within 2 km.

Builder: Vimal Gordhanbhai Pipalia

Vimal Gordhanbhai Pipalia has 3 registrations on MahaRERA, including Urja Cornerstone Building 1 and Urja Cornerstone Building 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Urja Cornerstone Building 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Urja Cornerstone Building 1 is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Urja Cornerstone Building 1?

The registered promoter entity is Vimal Gordhanbhai Pipalia, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Urja Cornerstone Building 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Urja Cornerstone Building 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Urja Cornerstone Building 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Urja Cornerstone Building 1?

The professionals named in the filing: Architect: M/s.Vistaar Architects and Planners; Engineer: M/s.Adharshila Consultant; Chartered Accountant: JSSK & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Urja Cornerstone Building 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Urja Cornerstone Building 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Urja Cornerstone Building 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.