Red flags

  • Rs 40.00 crore secured on the land, in favour of ADITYA BIRLA HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
29 of 66Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

URBANBRICK VISTA PH-1 is a Plotted project by MOHAR OMKAR ASSOCIATES LLP in Pune, Maharashtra, registered with MahaRERA as P52100056271 on 22 May 2024. Possession is promised by 31 Dec 2030. 37 of the 66 units on this registration are recorded sold or booked.

At a glance

Project

  • NameURBANBRICK VISTA PH-1
  • TypePlotted
  • Location
    • SUTARWADI ROAD OPPOSITE TO HELICAL COMPANY
    • AMADAVET VILLAGE
    • Ambadvet
    • Mulshi
    • Pune
    • 412115
  • Pincode412115
  • RERA no.P52100056271
  • ReraGenie IDRG-MH-05697

Builder

  • NameMOHAR OMKAR ASSOCIATES LLP
  • Entity typeOthers
  • PartnerKARAN RAJIVKUMAR KARNAWAT Karnawat
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2024PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 May 2024
  • Promised completion31 Dec 2030
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed69 files

Current status

56%37 of 66 units booked
65.0%Work done, per cost certificate

Figures as on 11 Jul 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 11 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceYes70%
Open ParkingNoNot applicable

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area26,763 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofADITYA BIRLA HOUSING FINANCE LIMITED
Secured amountRs 40.00 crore
CERSAI search filedYes
Declared on3 Jul 2026

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLOHIA JAIN CAPITAL, SENAPATI BAPAT MARG, PUNE 411016
Estimated costRs 7.85 cr
Cost incurredRs 5.11 cr
Work done65.0%
BuildingWingEstimatedIncurred
-NARs 7.85 crRs 5.11 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCUBIX ARCHITECTS ASSOCIATES
ArchitectHarshad N Sharma
EngineerPANKAJ NAVALAKHA
Chartered AccountantDEVESH NAVSALKAR
PartnerRole in project
MOHAR OMKAR ASSOCIATES LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form1_Architect Certificate_UV Phase I.pdf11 Jul 2026
Withdrawal Update Form 2File: Form2_Eng Certificate_UV Phase I.pdf11 Jul 2026
Withdrawal Update Form 3File: Form3_CA Certificate_UV Phase I.pdf11 Jul 2026
Form 5 (FY 2024-2025)File: FORM 5 CA CERTIFICATE 3132025 VISTA PH 1.pdf3 Jun 2026
Form 1File: ARCHITECT FORM 1 UB Vista Ph1 31122025.pdf22 Apr 2026
Form 2File: Engg Certificate UB Vista Ph 1 31122025.pdf22 Apr 2026
Form 3File: Form 3 MO 31122025 Ub Vista Ph 1.pdf22 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory UB Vista Ph 1 31122025.pdf22 Apr 2026
Form 1File: ARCHITECT FORM 1 UB Vista Ph 1 30092025.pdf2 Feb 2026
Form 2File: Engg Certificate UB Vista Ph 1 30092025.pdf2 Feb 2026
Form 3File: CA Certificate UB Vista Ph 1 30092025.pdf2 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory UB Vista Ph 1 30092025.pdf2 Feb 2026
Form 1File: Form 1 UB Vista Ph 1 30062025.pdf10 Jan 2026
Form 2File: Engg Certificate UB Vista Ph 1 30062025.pdf10 Jan 2026
Form 3File: Form 3 Urbanbrick Vista Ph 1 30062025.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory UB Vista Ph 1 30062025.pdf10 Jan 2026
Form 1File: Architect Certificate UB Vista Ph1 31032025.pdf12 Nov 2025
Form 2File: Engg Certificate UB Vista Ph 1 31032025.pdf12 Nov 2025
Form 3File: CA Certificate UB Vitsa Ph1 31032025.pdf12 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory UB Vista Ph1 31032025.pdf12 Nov 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 UB Vista Ph 1 31122024.pdf28 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate UB Vista Ph1 31122024.pdf28 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate UB Vista Ph1 31122024.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate UB Vista Ph1 300924.pdf14 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certicate UB Vista Ph1 30092024.pdf14 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate UB Vista Ph 1 30092024.pdf14 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate UB Vista Ph1 300624.pdf6 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE UB VISTA PH1 30062024.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate UB Vista Ph1 30062024.pdf27 Nov 2024
Layout approvalFile: A Sector_Final (1).pdf14 May 2024
Layout approvalFile: B Sector_Final (1).pdf14 May 2024
Layout approvalFile: C Sector_FInal (1).pdf14 May 2024
Layout approvalFile: B Sector 2_rotated.pdf14 May 2024
Copy of Layout Approval (in case of layout)File: A Sector_Final (1).pdf14 May 2024
Copy of Layout Approval (in case of layout)File: B Sector_Final (1).pdf14 May 2024
Copy of Layout Approval (in case of layout)File: C Sector_FInal (1).pdf14 May 2024
Copy of Layout Approval (in case of layout)File: B Sector 2_rotated.pdf14 May 2024
Details of encumbrances concerned to FinanceFile: Financial Encumbrance.pdf10 May 2024
Details of encumbrances concerned to LegalFile: Financial Encumbrance.pdf10 May 2024
Declaration about Commencement CertificateFile: Declaration on cemmecement certificate.pdf10 May 2024
CERSAI detailsFile: Cersai Explanation (2).pdf7 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration Revised.pdf6 May 2024
Other - TechnicalFile: Annexure A No Real estate project.pdf6 May 2024
CERSAI detailsFile: CERSAI_Search_Report_200304993257_For_Asset_Based_Search_26_04_2024_16_33_08_596.pdf26 Apr 2024
Details of encumbrances concerned to FinanceFile: 2 a Details of encumbrances of Legal.pdf21 Apr 2024
Details of encumbrances concerned to LegalFile: 2 a Details of encumbrances of Legal.pdf21 Apr 2024
Proforma of Agreement for saleFile: 1 Agreement Draft Ph 1.pdf21 Apr 2024
Other - TechnicalFile: Explanation_merged (1).pdf21 Apr 2024
Building plan approval or NA orderFile: NA ORDER_AMB 99 1 99 2 119.pdf20 Apr 2024
Building plan approval or NA orderFile: NA ORDER AMB 117 4 118 3 118 4.pdf20 Apr 2024
Building plan approval or NA orderFile: NA Order Amb 120 1 120 2 120 3 122 2 122 4_compressed.pdf20 Apr 2024
PAN CardFile: PAN Card Mohar Omkar Associates LLP.pdf20 Apr 2024
Copy of the legal title reportFile: Search Report Ambadvet Merged 20 04 24.pdf20 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER_AMB 99 1 99 2 119.pdf20 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER AMB 117 4 118 3 118 4.pdf20 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: NA Order Amb 120 1 120 2 120 3 122 2 122 4_compressed.pdf20 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: PMRDA ORDER AMB 11 4 118 3 118 4 compressed.pdf20 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: PMRDA ORDER AMB 119P 99 1 99 2 compressed.pdf20 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: PMRDA ORDER AMB 120 122 compressed.pdf20 Apr 2024
Declaration in FORM BFile: Form B Mohar.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE MOHAR.pdf20 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: MOHAR BD Disclosure of Interest 17 04 24.pdf20 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: MOHAR KK Disclosure of Interest 17 04 24.pdf20 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: MOHAR PN Disclosure of Interest 17 04 24.pdf20 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: MOHAR PS Disclosure of Interest 17 04 24.pdf20 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: MOHAR VG Disclosure of Interest 19 04 24.pdf20 Apr 2024
Proforma of Allotment letterFile: 1 Allottment Letter Ph 1 (2).pdf20 Apr 2024
Deviation Report with respect to Allotment letterFile: 1 Deviation Allotment.pdf20 Apr 2024
Deviation Report with respect to model copy of AgreementFile: 5 Deviation_ATS.pdf20 Apr 2024

How this compares with Pune

56%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep URBANBRICK VISTA PH-1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMADAVET VILLAGE13,700+ in Pune

Builder: MOHAR OMKAR ASSOCIATES LLP

MOHAR OMKAR ASSOCIATES LLP has 2 registrations on MahaRERA, including URBANBRICK VISTA PH-1 and URBANBRICK VISTA PH-2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if URBANBRICK VISTA PH-1 is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of URBANBRICK VISTA PH-1?

The registered promoter entity is MOHAR OMKAR ASSOCIATES LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in URBANBRICK VISTA PH-1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for URBANBRICK VISTA PH-1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at URBANBRICK VISTA PH-1?

The professionals named in the filing: Architect: CUBIX ARCHITECTS ASSOCIATES; Architect: Harshad N Sharma; Engineer: PANKAJ NAVALAKHA; Chartered Accountant: DEVESH NAVSALKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in URBANBRICK VISTA PH-1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About URBANBRICK VISTA PH-1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save URBANBRICK VISTA PH-1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.