ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Urban Skyline Phase I

Registered No litigation declared Residential / Group Housing project

Urban Skyline Phase I

By Urban Space Creators

RG-MH-16658 · RERA P52100026499 · Last updated on MahaRERA portal: 15 Feb 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedno revision filed
17 of 44Construction stages doneacross 4 buildings; furthest along: Sanitary Fittings within the flats /..., 90%
0Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

Urban Skyline Phase I is a Residential / Group Housing project by Urban Space Creators in Pune, Maharashtra, registered with MahaRERA as P52100026499 on 26 Sep 2020. Possession is promised by 30 Jun 2027.

At a glance

Project

  • NameUrban Skyline Phase I
  • TypeResidential / Group Housing
  • Location
    • Aundh Ravet Road
    • Near celestial City Phase I
    • Ravet
    • Haveli
    • Pune
    • 411044
  • Pincode411044
  • RERA no.P52100026499
  • ReraGenie IDRG-MH-16658

Builder

  • NameUrban Space Creators
  • Entity typePartnership
  • PartnersMohit Subhash Daga, Swapnil Gulabchand Sheth, Anil Balkishan Bhangdia

Key dates

this monthRegisteredSep 2020PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Sep 2020
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings4 building records
  • Documents filed94 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA190000
BNA200000
CNA150000
DNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 15 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

A88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
B84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
C47%
ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)0%
Plinth70%
Stilt Floor70%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D38%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes80%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed342

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots342
Closed/Covered80
Open Space262
BuildingClosed/CoveredOpen SpaceTotal
A2597122
B2599124
C246084
D6612

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,015 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI36089.45
Proposed, not sanctioned17,756 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOld Mumbai Pune Highway, Shop No 3 To 8, Ground Floor, F Wing Premier Plaza, Pune, Maharashtra 41101

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSwapnil Sheth
EngineerVinnayakk Narcke
Chartered AccountantDoshi Jethale and Associates
PartnerRole in project
Urban Space Creators-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf15 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 USC Ph 1.pdf31 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng Ph 1.pdf31 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 Phase I.pdf31 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Phase I.pdf31 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf30 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate.PDF30 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Phase I.pdf17 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2 engineer's certificate ph-1.pdf17 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Cert PH-I.pdf17 May 2023
Proforma of Agreement for saleFile: Draft Agreement USC PH I 2022.pdf17 May 2023
Layout approvalFile: 01 Layout_11zon.pdf6 Mar 2023
Building plan approvalFile: 02 Parking Plan.pdf6 Mar 2023
Building plan approvalFile: 03 Bldg A.pdf6 Mar 2023
Building plan approvalFile: 06 Bldg B.pdf6 Mar 2023
Building plan approvalFile: 08 Bldg B 2.pdf6 Mar 2023
Building plan approvalFile: 10 Bldg D.pdf6 Mar 2023
Building plan approvalFile: 12 Club House.pdf6 Mar 2023
Copy of Layout Approval (in case of layout)File: 01 Layout_11zon.pdf6 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 02 Parking Plan.pdf6 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 03 Bldg A.pdf6 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 06 Bldg B.pdf6 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 08 Bldg B 2.pdf6 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 10 Bldg D.pdf6 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 12 Club House.pdf6 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 20_12_2022_11zon.pdf6 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ph-1 FORM 2 ENGINEER dec 2022_11zon.pdf6 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022.pdf6 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2022_11zon.pdf6 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 2021-22.PDF6 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.PDF23 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.PDF23 Jan 2023
Declaration about Commencement CertificateFile: declaration CC.pdf30 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Form 1 USC march 2021.pdf30 Aug 2021
Disclosure of sold/ booked inventoryFile: Inventary A Bldg.pdf30 Aug 2021
Disclosure of sold/ booked inventoryFile: inventary B Bldg.pdf30 Aug 2021
Disclosure of sold/ booked inventoryFile: inventary C Bldg.pdf30 Aug 2021
Disclosure of sold/ booked inventoryFile: inventary D Bldg.pdf30 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 CA March 21.pdf30 Aug 2021
Proforma of Allotment letterFile: Draft Agreement USC 2020.pdf30 Aug 2021
Proforma of Allotment letterFile: PROVISIONAL ALLOTMENT LETTER USC.pdf30 Aug 2021
Building plan approvalFile: MYSCAN_20201228_0001.pdf29 Dec 2020
Building plan approvalFile: MYSCAN_20201228_0002.pdf29 Dec 2020
Building plan approvalFile: MYSCAN_20201228_0003.pdf29 Dec 2020
Building plan approvalFile: MYSCAN_20201228_0004.pdf29 Dec 2020
Building plan approvalFile: MYSCAN_20201228_0006.pdf29 Dec 2020
Building plan approvalFile: MYSCAN_20201228_0007.pdf29 Dec 2020
Building plan approvalFile: MYSCAN_20201228_0008.pdf29 Dec 2020
Building plan approvalFile: MYSCAN_20201228_0009.pdf29 Dec 2020
Building plan approvalFile: MYSCAN_20201228_0010.pdf29 Dec 2020
Building plan approvalFile: MYSCAN_20201228_0011.pdf29 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20201228_0001.pdf29 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20201228_0002.pdf29 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20201228_0003.pdf29 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20201228_0004.pdf29 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20201228_0006.pdf29 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20201228_0007.pdf29 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20201228_0008.pdf29 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20201228_0009.pdf29 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20201228_0010.pdf29 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20201228_0011.pdf29 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Dec 2020.pdf29 Dec 2020
Layout approvalFile: Lay out_compressed.pdf23 Sep 2020
Building plan approvalFile: 1 floor B bldg_compressed.pdf23 Sep 2020
Building plan approvalFile: 1 floor C Bldg_compressed.pdf23 Sep 2020
Building plan approvalFile: 1, 2, 4 Floor A bldg_compressed.pdf23 Sep 2020
Building plan approvalFile: 1,2,3,4,5,6,7 MHADA D Bldg_compressed.pdf23 Sep 2020
Building plan approvalFile: 2, 4, 3, 5 Floor B Bldg_compressed.pdf23 Sep 2020
Building plan approvalFile: 2,4,3,5 floor C Bldg_compressed.pdf23 Sep 2020
Building plan approvalFile: 3, 5 Floor A Bldg_compressed.pdf23 Sep 2020
Building plan approvalFile: Club House_compressed.pdf23 Sep 2020
Building plan approvalFile: Parking Layout_compressed.pdf23 Sep 2020
PAN CardFile: PAN No USC.pdf23 Sep 2020
Copy of the legal title reportFile: Search sept 2020_compressed.pdf23 Sep 2020
Details of encumbrancesFile: Self Decl Non Enc.pdf23 Sep 2020
Copy of Layout Approval (in case of layout)File: Lay out_compressed.pdf23 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: 1 floor B bldg_compressed.pdf23 Sep 2020

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Urban Skyline Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near celestial City Phase I13,700+ in Pune

Builder: Urban Space Creators

Urban Space Creators has 1 registration on MahaRERA, including Urban Skyline Phase I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Urban Skyline Phase I is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Urban Skyline Phase I?

The registered promoter entity is Urban Space Creators, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Urban Skyline Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Urban Skyline Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Urban Skyline Phase I?

The professionals named in the filing: Architect: Swapnil Sheth; Engineer: Vinnayakk Narcke; Chartered Accountant: Doshi Jethale and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Urban Skyline Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Urban Skyline Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Urban Skyline Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.