Home / Browse projects / Raigarh, Maharashtra / United Emporio

Completed No litigation declared Others project

United Emporio

By SMB PropertiesLLP

RG-MH-42371 · RERA P52000019207 · Last updated on MahaRERA portal: 26 Sep 2025

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 17 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
2 of 46Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 137 documents Report an error

United Emporio is a Others project by SMB PropertiesLLP in Raigarh, Maharashtra, registered with MahaRERA as P52000019207 on 9 Jan 2019. The registration is recorded completed; possession was promised by 12 Jun 2025. The completion date has moved by 17 months from the original filing. 44 of the 46 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameUnited Emporio
  • TypeOthers
  • Location
    • Sector 11
    • Kharghar
    • Panvel
    • Raigarh
    • 410210
  • Pincode410210
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000019207
  • ReraGenie IDRG-MH-42371

Builder

  • NameSMB PropertiesLLP
  • Entity typePartnership
  • PartnersRavi Sundaram Iyer, Amit Suresh Kalra

Key dates

this monthRegisteredJan 2019First promiseJan 2024Revised toJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Jan 2019
  • Promised completion12 Jun 2025
  • Revised completionRevised to 12 Jun 2025 (originally 30 Jan 2024)
  • Buildings1 building record
  • Documents filed137 files

Current status

96%44 of 46 units booked
84.0%Work done, per cost certificate

Figures as on 26 Sep 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EMPORIONA171439746

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

EMPORIO: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 26 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed27

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots27
Closed/Covered27

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,427 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCity And Industrial Development Corporation Of Maharashtra
Permissible FSI4548.97
Proposed, not sanctioned4,549 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchArti CHS LTD, Plot 29, Sector-2, Vashi, Navi Mumbai-400703
Estimated costRs 21.00 cr
Cost incurredRs 17.65 cr
Work done84.04%
BuildingWingEstimatedIncurred
EMPORIONARs 19.95 crRs 16.77 cr
-NARs 1.05 crRs 88.24 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDESTINATION ARCHITECTURE INTERIOR DESIGNS
EngineerSK Consultants & Engineers
Chartered AccountantN B Sayed & Associates
Chartered AccountantVikas Abhang & Associated
PartnerRole in project
SMB PropertiesLLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000019097Jan 2024 → Jan 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

EXT52000027509Jan 2024 → May 2025

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-05-2025 to complete the project and fulf

EA02082502288Jan 2024 → Jun 2025

Reason as filed by the promoterwe, M/s. Smb Properties LLP, hereby declare the following with respect to the project Unite Emporio bearing registration number. P52000019207 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 12/06/2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timely e

Litigation declared2

CaseCourtStatus
157/2012/2012The Civil Judge J D PanvelPending
SLP 9527/2018/2018The Supreme Court of IndiaDisposed

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000196702Mr. Bhupender Singh BhandariM/s SMB properties LLP29/05/2021
CC12400458Garima SinghSMB PropertiesLLP19/10/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jul 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Jun 2025

Documents filed137

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 137 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Full OC and OC verification Mail.pdf26 Sep 2025
Withdrawal Update Form 1File: Form 1 - United Emporio.pdf10 Sep 2025
Withdrawal Update Form 2File: United Emporio - Form 2.pdf10 Sep 2025
Withdrawal Update Form 3File: Form 3 - UE.pdf10 Sep 2025
Form 1File: Form 1 - United Emporio as on June 2025.pdf19 Jul 2025
Form 2File: Form 2 - United Emporio as on June 2025.pdf19 Jul 2025
Form 3File: Form 3 - United Emporio as on June 2025.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - United Emporio as on June 2025.pdf19 Jul 2025
Layout approvalFile: OC Drawing.pdf15 Jul 2025
Copy of Layout Approval (in case of layout)File: OC Drawing.pdf15 Jul 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC COPY.pdf12 Jun 2025
Certificates of CA (Form 3)File: Form 3 - United Emporio as on 17-04-2025.pdf28 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - United Emporio as on March 2025.pdf3 Apr 2025
Certificates of CA (Form 3)File: Form 3 - United Emporio as on March 2025.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - United Emporio as on March 2025.pdf3 Apr 2025
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION03022025.pdf12 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Stamped06022025.pdf12 Feb 2025
Certificates of CA (Form 3)File: Form 3_11022025_11zon.pdf12 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_11022025.pdf12 Feb 2025
Disclosure of sold/ booked inventoryFile: Circular 29_11022025.pdf12 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_11022025.pdf12 Feb 2025
Certificates of CA (Form 3)File: Form 3 United Emporio 30th Sep 2024_compressed.pdf17 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - United Emporio as on June 2024.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 United Emporio Sep 24.pdf14 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - United Emporio as on June 2024.pdf18 Jul 2024
Certificates of CA (Form 3)File: Form 3 United Emporio 30th June 2024.pdf18 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - United Emporio as on June 2024.pdf15 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 112062024.pdf13 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 207062024.pdf7 Jun 2024
Certificates of CA (Form 3)File: FORM 307062024_compressed.pdf7 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ARCHITECTS CERTIFICATE 28-05-2024.pdf28 May 2024
Building plan approvalFile: REVISED CC DRAWING-1.pdf27 May 2024
Building plan approvalFile: REVISED CC DRAWING-2.pdf27 May 2024
Building plan approvalFile: REVISED CC DRAWING-3.pdf27 May 2024
Building plan approvalFile: REVISED CC DRAWING-4.pdf27 May 2024
Building Plan Approval (IOD)File: REVISED CC DRAWING-1.pdf27 May 2024
Building Plan Approval (IOD)File: REVISED CC DRAWING-2.pdf27 May 2024
Building Plan Approval (IOD)File: REVISED CC DRAWING-3.pdf27 May 2024
Building Plan Approval (IOD)File: REVISED CC DRAWING-4.pdf27 May 2024
Commencement Certificates / NA Order for plotted developmentFile: REVISED CC COPY.pdf27 May 2024
Declaration about Commencement CertificateFile: DECLARATION13052024.pdf18 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A13052024.pdf18 May 2024
Declaration in FORM BFile: Form B.pdf17 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec_11zon.pdf16 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec_11zon.pdf16 Feb 2024
Form 2AFile: Form 2A 19-20.pdf16 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf16 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf16 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf16 Feb 2024
Certificates of CA (Form 3)File: Form 3 Dec_11zon.pdf16 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SMB Form 5_19-20.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf16 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 United Emporio FY 21-22.pdf2 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 United Emporio FY 22-23.pdf2 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - United Emporio as on Dec 2023.pdf9 Jan 2024
Certificates of CA (Form 3)File: Form 3 - United Emporio as on Dec 2023.pdf9 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- United Emporio as on Sept 2023.pdf3 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - United Emporio as on Dec 2023.pdf3 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- United Emporio as on September 2023.pdf12 Oct 2023
Certificates of CA (Form 3)File: Form 3- United Emporio as on September 2023.pdf12 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1 ARCHITECTS CERTIFICATE.pdf9 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- United Emporio as on 1-10-2023.pdf4 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- United Emporio.pdf27 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- United Emporio as on June 2023.pdf24 Jul 2023
Certificates of CA (Form 3)File: Form 3- United Emporio as on June 2023.pdf24 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: United Emporio Mar 23 - Form 2.pdf10 Apr 2023
Certificates of CA (Form 3)File: Form 3 United Emporio 31st March 2023.pdf10 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ARCHITECT'S CERTIFICATE-.pdf1 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 (18-19) - United Emporio.pdf27 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 United Emporio as on March 2019.pdf25 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 United Emporio as on March 2020.pdf25 Mar 2023
Certificates of CA (Form 3)File: Form 3 United Emporio as on March 2019.pdf25 Mar 2023
Certificates of CA (Form 3)File: Form 3 United Emporio as on March 2020.pdf25 Mar 2023
Disclosure of sold/ booked inventoryFile: Circular 29- United Emporio_compressed.pdf14 Jan 2023

How this compares with Raigarh

96%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 17 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep United Emporio on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kharghar5,900+ in Raigarh

2 kmUnited EmporioCompleted 22Lapsed / revoked 4Other 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 59 registered projects within 2 km.

Builder: SMB PropertiesLLP

SMB PropertiesLLP has 1 registration on MahaRERA, including United Emporio. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if United Emporio is delayed beyond 12 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of United Emporio?

The registered promoter entity is SMB PropertiesLLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in United Emporio?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against United Emporio?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for United Emporio?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at United Emporio?

The professionals named in the filing: Architect: DESTINATION ARCHITECTURE INTERIOR DESIGNS; Engineer: SK Consultants & Engineers; Chartered Accountant: N B Sayed & Associates; Chartered Accountant: Vikas Abhang & Associated. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in United Emporio?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About United Emporio. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save United Emporio to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.