UMA RESIDENCY, PHASE I

By ADARSH INFRA DEVELOPERS

RG-MH-55777 · RERA P51700011302 · Last updated on MahaRERA portal: 21 May 2026

Source: official MahaRERA filing

Red flags

  • Possession 2 months past the filed date
  • Completion date moved by 62 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Aug 2026Possession promised2 months past this date
24 of 55Construction stages doneacross 5 buildings; furthest along: Installation of Lifts, 95%
89 of 120Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 143 documents Report an error

UMA RESIDENCY, PHASE I is a Residential / Group Housing project by ADARSH INFRA DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700011302 on 31 Aug 2017. Possession was promised by 31 Aug 2026 and is now 2 months past that date. The completion date has moved by 62 months from the original filing. 31 of the 120 units on this registration are recorded sold or booked, and 24 of 55 construction stages are filed complete.

At a glance

Project

  • NameUMA RESIDENCY, PHASE I
  • TypeResidential / Group Housing
  • Location
    • NA
    • Khardi (CT)
    • Shahapur
    • Thane
    • 421601
  • Pincode421601
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700011302
  • ReraGenie IDRG-MH-55777

Builder

  • NameADARSH INFRA DEVELOPERS
  • Entity typePartnership
  • PartnersJIVRAJ BHANJI PATEL, SAVITRI JIVRAJ PATEL, VIMALA PARSHOTAM PATEL, MANSUKH NANJI PATEL, HEMLATA MANSUKH PATEL

Key dates

2 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 30 Jun 2021)
  • Buildings5 building records
  • Documents filed143 files

Current status

26%31 of 120 units booked
89.2%Work done, per cost certificate

Figures as on 21 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building E4NA5540040
Building F3NA5020020
Building F4NA5020020
Building G1NA5020020
Building G2NA5020020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 21 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Installation of Lifts, at 95%.

Building E481%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Building F381%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Building F481%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Building G10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building G20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes95%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes80%
Energy managemcntYes75%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Open Space50
BuildingOpen SpaceTotal
Building E41010
Building F31010
Building F41010
Building G11010
Building G21010

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,470 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
SANJAY SHRICHAND AHUJAGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban
JEETU SHRICHAND AHUJAGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authorityThane Municiple Corporation
Permissible FSI3929.64
Proposed, not sanctioned3,930 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRoad No-22,Waghale Industrial Estate,Thane-400 604
Estimated costRs 6.83 cr
Cost incurredRs 6.10 cr
Work done89.25%
BuildingWingEstimatedIncurred
Building E4NARs 2.88 crRs 2.71 cr
Building F3NARs 1.58 crRs 1.57 cr
Building F4NARs 1.58 crRs 1.55 cr
-NARs 30.00 lakhRs 28.00 lakh
Building G1NARs 25.00 lakh-
Building G2NARs 25.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSuyog Sanjay Pande Prop of Parth Consultant & Town Planners
ArchitectParth Consultant and Town Planners
EngineerK B Consultants (Partner K K Patel)
Chartered AccountantGANPATH JAIN
PartnerRole in project
ADARSH INFRA DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700010567Jun 2021 → Jun 2022

Reason as filed by the promoterAt the time of applying for RERA registration we envisaged to complete the project on or before 31/12/2020.However the construction work was delayed due to COVID 19 and we could not complete the project on or before the 31/12/2020. RERA Authority also granted 6 months extension up to 30/06/2021. But due COVID 19 situation we could not finished some work of Project. We expect finish construction work on or before 30/06/2022.

EXT51700019249Jun 2021 → Aug 2025

Reason as filed by the promoterAs the Number of Booking are very less

EA19122518781Jun 2021 → Aug 2026

Reason as filed by the promoterAs the Number of Booking are very less

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed143

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 143 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf21 May 2026
Withdrawal Update Form 1File: Form 1.pdf21 May 2026
Withdrawal Update Form 2File: Form 2.pdf21 May 2026
Withdrawal Update Form 2File: Form 2.pdf21 May 2026
Withdrawal Update Form 3File: Form 3.pdf21 May 2026
Withdrawal Update Form 3File: Form 3.pdf21 May 2026
Form 5 (FY 2024-2025)File: Form 5.pdf25 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf20 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf20 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf20 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf19 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf19 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf19 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf19 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf19 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf19 Dec 2025
Withdrawal Update Form 1File: Form 1 June 25.pdf13 Dec 2025
Withdrawal Update Form 2File: Form 2 June 25.pdf13 Dec 2025
Withdrawal Update Form 3File: Form 3 June 25.pdf13 Dec 2025
Withdrawal Update Form 1File: Form 1 - Mar 25.pdf18 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf18 Nov 2025
Withdrawal Update Form 3File: Form 3 - Adarsh Infra Developers.pdf18 Nov 2025
Form 1File: Form 1.pdf26 Jul 2025
Form 2File: Form 2.pdf26 Jul 2025
Form 3File: Form 3.pdf26 Jul 2025
Disclosure of Sold and Booked InventoryFile: Discloser Sold Unsold Inventory.pdf26 Jul 2025
Certificates of CA (Form 3)File: Form 3_compressed.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Mar 25.pdf1 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf1 May 2025
Certificates of CA (Form 3)File: Adarsh Infra Q3.pdf7 Feb 2025
Certificates of CA (Form 3)File: Adarsh Infra Q2.pdf7 Feb 2025
Certificates of CA (Form 3)File: Adarsh Infra Q1.pdf7 Feb 2025
Certificates of CA (Form 3)File: Adarsh Infra 23-24 Q4.pdf7 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A- 23-24 Adarsh Infra Developers.pdf3 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 310324.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 300624.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 300924.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 311224.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 311224.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 310324.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 310324.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 till 310324.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 till 300624.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 till 300924.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 till 311224.pdf28 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Signed.pdf29 Nov 2024
Disclosure of sold/ booked inventoryFile: Flat details signed.pdf21 Mar 2024
Declaration in FORM BFile: Form B_organized.pdf19 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A mar 20.pdf19 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A mar 22.pdf19 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A mar 23.pdf19 Mar 2024
Certificates of CA (Form 3)File: 1 31 03 2021.pdf7 Mar 2024
Certificates of CA (Form 3)File: 2 30 06 2021.pdf7 Mar 2024
Certificates of CA (Form 3)File: 3 30 09 2021.pdf7 Mar 2024
Certificates of CA (Form 3)File: 4 31 12 2021.pdf7 Mar 2024
Certificates of CA (Form 3)File: 5 31 03 2022.pdf7 Mar 2024
Certificates of CA (Form 3)File: 6 30 06 2022.pdf7 Mar 2024
Certificates of CA (Form 3)File: 7 30 09 2022.pdf7 Mar 2024
Certificates of CA (Form 3)File: 8 31 12 2022.pdf7 Mar 2024
Certificates of CA (Form 3)File: 9 31 03 2023.pdf7 Mar 2024
Certificates of CA (Form 3)File: 10 30 06 2023.pdf7 Mar 2024
Certificates of CA (Form 3)File: 11 30 09 2023.pdf7 Mar 2024
Certificates of CA (Form 3)File: 12 31 12 2023.pdf7 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Form 2 till 30 06 21.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Form 2 till 30 09 21.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Form 2 till 31 12 21.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Form 2 till 31 03 22.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Form 2 till 30 06 22.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 Form 2 till 30 09 22.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 Form 2 till 31 12 22.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 Form 2 till 31 03 23.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 9 Form 2 till 30 06 23.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10 Form 2 till 30 09 23.pdf27 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11 Form 2 till 31 12 23.pdf27 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 30 June 21.pdf15 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 30 Sep 21.pdf15 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 31 Dec 21.pdf15 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 31 Mar 22.pdf15 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 30 June 22.pdf15 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 30 Sep 22.pdf15 Feb 2024

How this compares with Thane

26%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 62 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep UMA RESIDENCY, PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NA7,600+ in Thane

2 kmUMA RESIDENCY, PHASE ICompleted 1Lapsed / revoked 4Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 6 registered projects within 2 km.

Builder: ADARSH INFRA DEVELOPERS

ADARSH INFRA DEVELOPERS has 1 registration on MahaRERA, including UMA RESIDENCY, PHASE I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if UMA RESIDENCY, PHASE I is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UMA RESIDENCY, PHASE I?

The registered promoter entity is ADARSH INFRA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UMA RESIDENCY, PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for UMA RESIDENCY, PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UMA RESIDENCY, PHASE I?

The professionals named in the filing: Architect: Suyog Sanjay Pande Prop of Parth Consultant & Town Planners; Architect: Parth Consultant and Town Planners; Engineer: K B Consultants (Partner K K Patel); Chartered Accountant: GANPATH JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UMA RESIDENCY, PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UMA RESIDENCY, PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UMA RESIDENCY, PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.