ReraGenieLog inGet a buyer report

Home / Browse projects / Solapur, Maharashtra / TULSI APARTMENT

Registration lapsed No litigation declared Residential / Group Housing project

TULSI APARTMENT

By SHRISAI VISHWA BUILDERS AND DEVELOPERS

RG-MH-74980 · RERA P52600050686 · Last updated on MahaRERA portal: 15 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

TULSI APARTMENT is a Residential / Group Housing project by SHRISAI VISHWA BUILDERS AND DEVELOPERS in Solapur, Maharashtra, registered with MahaRERA as P52600050686 on 28 Apr 2023. Possession was promised by 12 Dec 2024 and is now 22 months past that date.

At a glance

Project

  • NameTULSI APARTMENT
  • TypeResidential / Group Housing
  • Location
    • SAKHAR PETH
    • NEAR SAKHAR PETH POLICE STATION
    • Solapur (M Corp.)
    • Solapur North
    • Solapur
    • 413005
  • Pincode413005
  • RERA no.P52600050686
  • ReraGenie IDRG-MH-74980

Builder

  • NameSHRISAI VISHWA BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersLAXMINARAYAN PURUSHOTTAM DUSSA, VISHWAMBHAR BALAYYA MAMDYAL

Key dates

22 months past promisethis monthRegisteredApr 2023PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Apr 2023
  • Promised completion12 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TULSI APARTMENTNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

TULSI APARTMENT: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed21

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots21
Closed/Covered21

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area165 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI663.51
Proposed, not sanctioned664 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchC 4 MIDC AKKALKOT ROAD SOLAPUR 413003

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVISHWAMBHAR MAMDYAL
EngineerVYANKAPPA R CHOUGULE
Chartered AccountantPATIL UDGIRI AND ASSOCIATES
PartnerRole in project
SHRISAI VISHWA BUILDERS AND DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01 Form 1 Architect Certificate 31032025.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03 CA Certificate 31032025.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 Form 2 31032025.pdf15 Apr 2025
Disclosure of sold/ booked inventoryFile: 04 Booking Stetus 31032025.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01 FORM 1 30062024.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01 FORM 1 30092024.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01 FORM 1 31122024.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01 FORM 1 31032024.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03 CA Certificate 31032024.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03 CA Certificate 30062024.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03 CA Certificate 30092024.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03 CA Certificate 31122024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 Form 2 30062024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 Form 2 31122024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 Form 2 30092024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 Form 2 31032024.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: 04 Booking Stetus 31032024.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: 04 Booking Stetus 30062024.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: 04 Booking Status 30092024.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: 04 Booking Stetus 31122024.pdf19 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 06 FORM 2A 202324.pdf19 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 05 FORM 5 Shri Sai VISHWA BUILDER.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate Jan to March 2023.pdf12 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 April-June-2023.pdf12 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 July-Sept-2023.pdf12 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Oct-Dec-2023.pdf12 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan-March-2023.pdf12 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 April-June-2023.pdf12 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 July-Sept-2023.pdf12 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Oct-Dec-2023.pdf12 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate.pdf12 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure 31-03-2023.pdf12 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure 30-06-2023.pdf12 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure 30-09-2023.pdf12 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure 31-12-2023.pdf12 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountants Certificate March 2023.pdf12 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountants Certificate June2023.pdf12 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountants Certificate Sept 2023.pdf12 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountants Certificate Dec 2023 (2).pdf12 Mar 2024
Details of encumbrances concerned to FinanceFile: query.pdf22 Mar 2023
Details of encumbrances concerned to LegalFile: query.pdf22 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PROMOTOR LETTER.pdf15 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Deed-CA-Covering Letter.pdf10 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf10 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Revised-Format-A-Order-34.pdf6 Mar 2023
Details of encumbrances concerned to FinanceFile: Financial Encumbrance.pdf3 Feb 2023
Details of encumbrances concerned to LegalFile: Financial Encumbrance.pdf3 Feb 2023
Other - LegalFile: revised agreement to sale format.pdf3 Feb 2023
Other - LegalFile: Covering Letter.pdf3 Feb 2023
Other - LegalFile: Rera Registation Deed.pdf3 Feb 2023
Other - LegalFile: Building Permission_11zon.pdf3 Feb 2023
Other - LegalFile: Layout.pdf3 Feb 2023
Layout approvalFile: 04 COPY OF LAYOUT.pdf23 Jan 2023
Building plan approvalFile: 04 COPY OF LAYOUT.pdf23 Jan 2023
PAN CardFile: 01 Firm PAN Card.pdf23 Jan 2023
Copy of the legal title reportFile: 02 Legal Title Report.pdf23 Jan 2023
Details of encumbrances concerned to FinanceFile: 03 DETAILS OF ENUMBRANCE.pdf23 Jan 2023
Details of encumbrances concerned to LegalFile: 03 DETAILS OF ENUMBRANCE.pdf23 Jan 2023
Copy of Layout Approval (in case of layout)File: 04 COPY OF LAYOUT.pdf23 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: 04 COPY OF LAYOUT.pdf23 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: 05 Building Permission.pdf23 Jan 2023
Declaration about Commencement CertificateFile: 06 Format - D.pdf23 Jan 2023
Declaration in FORM BFile: 07 Form B.pdf23 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 08 ARCHITECH CERTIFICATE.pdf23 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 09 ENGINEERS CERTIFICATE.pdf23 Jan 2023
CERSAI detailsFile: Declaration CERCEI.pdf23 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report_200257099966_For_Asset_Based_Search_09_01_2023_14_53_03_952.pdf23 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_Dussa.pdf23 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_Mamdyal.pdf23 Jan 2023
Proforma of Agreement for saleFile: Agreement to sell.pdf23 Jan 2023
Proforma of Allotment letterFile: RERA allotment letter format.pdf23 Jan 2023
Deviation Report with respect to Allotment letterFile: deviation Allotment letter.pdf23 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement.pdf23 Jan 2023

How this compares with Solapur

15%of Solapur projects moved their completion datethis one has not
39%of Solapur registrations have lapsed or been cancelledthis one is among them

Computed across the 550+ Solapur projects on ReraGenie, from their own filings.

Keep TULSI APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR SAKHAR PETH POLICE STATION550+ in Solapur

Builder: SHRISAI VISHWA BUILDERS AND DEVELOPERS

SHRISAI VISHWA BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including TULSI APARTMENT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Solapur district page.

Frequently asked questions

What does it mean that TULSI APARTMENT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if TULSI APARTMENT is delayed beyond 12 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TULSI APARTMENT?

The registered promoter entity is SHRISAI VISHWA BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TULSI APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TULSI APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TULSI APARTMENT?

The professionals named in the filing: Architect: VISHWAMBHAR MAMDYAL; Engineer: VYANKAPPA R CHOUGULE; Chartered Accountant: PATIL UDGIRI AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TULSI APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TULSI APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TULSI APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.