Home / Browse projects / Mumbai Suburban, Maharashtra / TRISHAAN

Registered No litigation declared Residential / Group Housing project

TRISHAAN

By RAJA BUILDER

RG-MH-40092 · RERA P51800047581 · Last updated on MahaRERA portal: 14 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
5 of 11Construction stages donefurthest along: Internal walls, 90%
25 of 27Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

TRISHAAN is a Residential / Group Housing project by RAJA BUILDER in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800047581 on 14 Nov 2022. Possession was promised by 30 Sep 2026 and is now 1 months past that date. 2 of the 27 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameTRISHAAN
  • TypeResidential / Group Housing
  • Location
    • 16TH ROAD
    • KHAR WEST
    • Andheri
    • Mumbai Suburban
    • 400052
  • Pincode400052
  • RERA no.P51800047581
  • ReraGenie IDRG-MH-40092

Builder

  • NameRAJA BUILDER
  • Entity typePartnership
  • PartnersNARENDRA VISHWAMITRA BHATIA, MAMTA NARENDRA BHATIA
  • Declared earlier projects2 →

Key dates

1 months past promisethis monthRegisteredNov 2022PromisedSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Nov 2022
  • Promised completion30 Sep 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed62 files

Current status

7%2 of 27 units booked
92.3%Work done, per cost certificate

Figures as on 14 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRISHAANNA101027027

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

TRISHAAN: 68% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.4%

Progress on shared amenities15

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered15
Open Space2

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area461 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Jun 2026
LandownerVillageDistrict
RAMSAY JOSEPH FERNANDESBandraMumbai Suburban
ROOSEVELT FERNANDESBandraMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI1668.28
Proposed, not sanctioned1,368 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMeghana Apartment CHS 64 SV ROAD SANTACRUZ WEST MUMBAI 400054
Estimated costRs 30.57 cr
Cost incurredRs 28.22 cr
Work done92.31%
BuildingWingEstimatedIncurred
TRISHAANNARs 30.57 crRs 28.22 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSWAPNIL SAWANT SAWANT
EngineerHARESH SUTAR
Chartered AccountantABHILASH DARDA
Chartered AccountantA K Kocchar and Associates
PartnerRole in project
RAJA BUILDER-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600169Bhakti AchrekarRAJA BUILDER23/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Jul 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jul 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: AMENDED PLANS DATED .pdf14 Jul 2026
Commencement certificateFile: Further CC.pdf14 Jul 2026
Withdrawal Update Form 1File: form 1.pdf14 Jul 2026
Withdrawal Update Form 2File: Form 2 - TRISHAAN.pdf14 Jul 2026
Withdrawal Update Form 3File: FORM 3 TRISHAAN.pdf14 Jul 2026
Withdrawal Update Form 1File: form 1.pdf29 Apr 2026
Withdrawal Update Form 2File: FORM 2 - TRISHAN.pdf29 Apr 2026
Withdrawal Update Form 3File: FORM 3 - TRISHAN.pdf29 Apr 2026
Withdrawal Update Form 1File: form 1.pdf13 Feb 2026
Withdrawal Update Form 2File: FORM 2 TRISHAAN.pdf13 Feb 2026
Withdrawal Update Form 3File: FORM 3 TRISHAN r.pdf13 Feb 2026
Withdrawal Update Form 1File: arch.pdf10 Nov 2025
Withdrawal Update Form 2File: FORM 2 TRISHAAN.pdf10 Nov 2025
Withdrawal Update Form 3File: TRISHAN RERA FORM NO 3.pdf10 Nov 2025
Form 1File: form 1.pdf25 Jun 2025
Form 2File: form 2.pdf25 Jun 2025
Form 3File: form 3_compressed.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf25 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: TRISHAAN RERA Form 1 .pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: TRISHAAN - FORM - 3_compressed.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf24 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RAJA BUILDER - FORM 2A_0001.pdf14 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RAJA BUILDER - FORM 5 - TRISHAAN.pdf14 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 .pdf5 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf5 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf5 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf29 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RAJA BUILDERS FORM 5 781.pdf13 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FOMR 1.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 A 3rd.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf18 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architech's Certificate.pdf23 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate.pdf23 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf23 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RB FORM 1.pdf24 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RB FORM 2.pdf24 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB FORM 3 CA_compressed.pdf24 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1 q4 22-23.pdf15 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2 - TRISHAAN - REUMA_compressed.pdf15 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3 - TRISHAAN - REUMA_compressed.pdf15 May 2023
Commencement Certificates / NA Order for plotted developmentFile: 2363960_FurtherCC_signed.pdf28 Feb 2023
Proforma of Agreement for saleFile: RERA AGREEMENT REUMA HOUSE fresh 123.pdf2 Nov 2022
Deviation Report with respect to model copy of AgreementFile: No Deviation agreement for sale.pdf2 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE FINAL.pdf1 Nov 2022
Copy of the legal title reportFile: TITLE report final.pdf21 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format A.pdf8 Oct 2022
Layout approvalFile: IOD-Drawing.pdf22 Sep 2022
Building plan approvalFile: IOD-Drawing.pdf22 Sep 2022
PAN CardFile: Raja Builder PAN.pdf22 Sep 2022
Details of encumbrances concerned to FinanceFile: Non Encumbrances declaration Financial.pdf22 Sep 2022
Details of encumbrances concerned to LegalFile: Non Encumbrances declaration Legal.pdf22 Sep 2022
Copy of Layout Approval (in case of layout)File: IOD-Drawing.pdf22 Sep 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD-Drawing.pdf22 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf22 Sep 2022
Declaration about Commencement CertificateFile: Declaration About Commencement certificate.pdf22 Sep 2022
Declaration in FORM BFile: FORM B - Pramoter.pdf22 Sep 2022
CERSAI detailsFile: cersai report.pdf22 Sep 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER PROFORMA.pdf22 Sep 2022
Deviation Report with respect to Allotment letterFile: No deviation in Allotment Letter format.pdf22 Sep 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
AARYA BUILDING7TH ROAD20CompletedDec 2020Late, Dec 2021
KISHAN ABODE14TH ROAD BANDRA WEST19CompletedDec 2012Sep 2012

How this compares with Mumbai Suburban

7%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRISHAAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHAR WEST6,700+ in Mumbai Suburban

Builder: RAJA BUILDER

RAJA BUILDER has 1 registration on MahaRERA, including TRISHAAN. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if TRISHAAN is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRISHAAN?

The registered promoter entity is RAJA BUILDER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRISHAAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against TRISHAAN?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for TRISHAAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRISHAAN?

The professionals named in the filing: Architect: SWAPNIL SAWANT SAWANT; Engineer: HARESH SUTAR; Chartered Accountant: ABHILASH DARDA; Chartered Accountant: A K Kocchar and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRISHAAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRISHAAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRISHAAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.