TRIMURTI SANTKRUPA HEIGHTS
RG-MH-90867 · RERA P52100050150 · Last updated on MahaRERA portal: 4 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 2 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TRIMURTI SANTKRUPA HEIGHTS is a Others project by SAMBHAJI BABAN BORHADE in Pune, Maharashtra, registered with MahaRERA as P52100050150 on 21 Mar 2023. Possession was promised by 26 Aug 2026 and is now 2 months past that date. 12 of the 40 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameTRIMURTI SANTKRUPA HEIGHTS
- TypeOthers
- Location
- PALAKHI MARG
- DEHU
- Haveli
- Pune
- 412109
- Pincode412109
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100050150
- ReraGenie IDRG-MH-90867
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on21 Mar 2023
- Promised completion26 Aug 2026
- Revised completionNone
- Buildings1 building record
- Documents filed94 files
Current status
Figures as on 4 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TRIMURTI SANTKRUPA HEIGHTS | NA | 7 | 6 | 20 | 20 | 40 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 80%.
TRIMURTI SANTKRUPA HEIGHTS: 51% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 4 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed67
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| BHAGWAN HARIBHAU MANSUKH | DEHU | Pune |
| KHANDU VITHHAL BARVE | Bhosari | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TRIMURTI SANTKRUPA HEIGHTS | NA | Rs 4.55 cr | Rs 2.78 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Milind Pokharkar |
| Engineer | Mahesh Gaddi |
| Engineer | Amol Nirmal |
| Chartered Accountant | Arti Abhinandan Jain |
| Chartered Accountant | NPSR & Associates |
| Chartered Accountant | Pankaj Patil |
| Chartered Accountant | MANATU KUMBHAR |
| Partner | Role in project |
|---|---|
| SAMBHAJI BABAN BORHADE | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Mar 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Mar 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed94
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A NAGHSHWAR PROPERTIES F Y 25 26 final.pdf | 4 Jun 2026 |
| Form 5 (FY 2025-2026)File: Form 5 NAGHESHWAR PROPERTIES 01.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3_compressed.pdf | 20 Apr 2026 |
| Form 2A (FY 2023-2024)File: new Form 2A NAGHEWAR PROPERTY F Y 23 24.pdf | 4 Apr 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A NAGHESHWAR PROPERTIE F Y 24 25.pdf | 4 Apr 2026 |
| Form 2A (FY 2022-2023)File: 2A MARCH 23.pdf | 28 Feb 2026 |
| Form 5 (FY 2022-2023)File: Nageshwar Properties (From 5 March 2023).pdf | 6 Feb 2026 |
| Form 5 (FY 2023-2024)File: Form 5 new upload.pdf | 6 Feb 2026 |
| Form 5 (FY 2024-2025)File: new SCAN Form 5 (NAGHESWAR PROPERTIES )F Y 24 25).pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: Nageshwar Form 3.pdf | 20 Jan 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 18 Oct 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_11zon.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_11zon.pdf | 18 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 (1).pdf | 19 Jul 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 19 Jul 2025 |
| Withdrawal Update Form 3File: FORM 3 ( TRIMURTI SANTKRUPA HEIGHTS)_11zon.pdf | 19 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect’s Certificate.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 UPDATD.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Trimurti Sant Krupa height Nageshwar Properties Form 3_11zon.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 (engineer form) mar-25.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD MAR-25.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 NAGESHWAR.pdf | 16 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf | 16 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 16 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: solddd unsold inventory.pdf | 16 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Nageshwar F Y 23-24 FORM 5.pdf | 14 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Trimurti Santkrupa Heights.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 SEP 24.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold SEP24.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A FY 23 24.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 JUNE 24.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: JUNE 24 sold unsold shops history - Copy.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 nageshwar properties TRIMURTI SANTKRUPA HEIGHTS_11zon.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 .pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 MARCH 24 .pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold shops history.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 TRIMURTI SANTKRUPA HEIGHTS_11zon.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 dec 23.pdf | 20 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: DEC 23 sold unsold shops history - Copy.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nageshwar_Properties form 3_compressed (1).pdf | 20 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Nageshwar Properties (From 5 March 2023).pdf | 5 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 MARCH 23.pdf | 2 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JUNE 23 FORM 2_compressed.pdf | 2 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 SEP 23.pdf | 2 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A MARCH 23.pdf | 2 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Trimurti Santkrupa Heights (March 2023).pdf | 29 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Trimurti Santkrupa Heights ( June 2023).pdf | 29 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Trimurti Santkrupa Heights (sept 2023).pdf | 29 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 MARCH 23.pdf | 17 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 JUNE 23.pdf | 17 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SEP 23.pdf | 17 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: sold unsold shops history - Copy MARCH 23.pdf | 17 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: sold unsold shops history JUNE .pdf | 17 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: SEP 23 sold unsold shops history - Copy.pdf | 17 Nov 2023 |
| Proforma of Agreement for saleFile: Nageshwar Agreement new.pdf | 17 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL FORM 3 RESIZE.pdf | 16 Mar 2023 |
| Layout approvalFile: 1.pdf | 11 Mar 2023 |
| Layout approvalFile: 2.pdf | 11 Mar 2023 |
| Layout approvalFile: 3.pdf | 11 Mar 2023 |
| Building plan approvalFile: 1.pdf | 11 Mar 2023 |
| Building plan approvalFile: commencement certificate NEW.pdf | 11 Mar 2023 |
| PAN CardFile: PAN PDF.pdf | 11 Mar 2023 |
| Copy of the legal title reportFile: all merged-PDF resize.pdf | 11 Mar 2023 |
| Copy of the legal title reportFile: 2 DEHU SATBARA.pdf | 11 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: self declaration regarding no encumbrances.pdf | 11 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: no encumbrances legal technical financial .pdf | 11 Mar 2023 |
| Details of encumbrances concerned to LegalFile: self declaration regarding no encumbrances.pdf | 11 Mar 2023 |
| Details of encumbrances concerned to LegalFile: no encumbrances legal technical financial .pdf | 11 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 11 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: 2.pdf | 11 Mar 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| TRIMURTI NAGARI NAGESHWAR PROPERTIES | 133 PART DEHU Haveli Pune 412109 | 148 | Completed | May 2022 | Oct 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 94 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep TRIMURTI SANTKRUPA HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DEHU13,700+ in Pune
Filed coordinates, straight-line distance. 228 registered projects within 2 km.
Gathagram Sector 2
HARIT LANDMARKS LLP
ANANDI VIHAR
SANSKRUTI DEVELOPERS
GATHAGRAM SECTOR-3 PHASE-1
HARIT LANDMARKS LLP
KESHAV KUNJ
M/S SANSKRUTI DEVELOPERS AND BUILDERS
VRUNDAVAN PARK
BG ASSOCIATES
Rivereast Residency
KRUSHNA PARADISE DEVELOPERS
Builder: SAMBHAJI BABAN BORHADE
SAMBHAJI BABAN BORHADE has 2 registrations on MahaRERA, including TRIMURTI SANTKRUPA HEIGHTS and TRIMURTI SAROJ HEIGHTS. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if TRIMURTI SANTKRUPA HEIGHTS is delayed beyond 26 Aug 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TRIMURTI SANTKRUPA HEIGHTS?
The registered promoter entity is SAMBHAJI BABAN BORHADE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TRIMURTI SANTKRUPA HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for TRIMURTI SANTKRUPA HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TRIMURTI SANTKRUPA HEIGHTS?
The professionals named in the filing: Architect: Milind Pokharkar; Engineer: Mahesh Gaddi; Engineer: Amol Nirmal; Chartered Accountant: Arti Abhinandan Jain; Chartered Accountant: NPSR & Associates; Chartered Accountant: Pankaj Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TRIMURTI SANTKRUPA HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback