ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / TRIDENT BUSINESS CENTER

Completed No litigation declared Commercial project

TRIDENT BUSINESS CENTER

By SHIRISH BHASKAR JADHAV

RG-MH-24343 · RERA P52100008007 · Last updated on MahaRERA portal: 20 Jun 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 35 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

TRIDENT BUSINESS CENTER is a Commercial project by SHIRISH BHASKAR JADHAV in Pune, Maharashtra, registered with MahaRERA as P52100008007 on 18 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2023. The completion date has moved by 35 months from the original filing.

At a glance

Project

  • NameTRIDENT BUSINESS CENTER
  • TypeCommercial
  • Location
    • -
    • Baner
    • Haveli
    • Pune
    • 411007
  • Pincode411007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100008007
  • ReraGenie IDRG-MH-24343

Builder

  • NameSHIRISH BHASKAR JADHAV
  • Entity typeIndividual
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseJul 2020Revised toJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Aug 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 28 Jul 2020)
  • Buildings1 building record
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRIDENT BUSINESS CENTERNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

TRIDENT BUSINESS CENTER: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed13

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots13
Closed/Covered1
Open Space12

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,300 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2909.24
Proposed, not sanctioned2,611 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAshok Sankul 2, Ashok Coop Hsg Soc, Pune-411005

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNILESH SASWADE
EngineerGA Bhilare Consultants Pvt Ltd
PartnerRole in project
SHIRISH BHASKAR JADHAV-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100009095Jul 2020 → Dec 2022

Reason as filed by the promoterFINANCIAL, LABOUR AND MATERIAL AVAILABILITY PROBLEMS BECAUSE OF COVID 19, PANDEMIC.

EXT52100002224Jul 2020 → Jul 2020

Reason as filed by the promoterQQ

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Jun 2023

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA- ARCHITECT CERTIFICATE FORM 1 TRIDENT BUSINESS CENTER.pdf20 Jun 2023
Architect’s Certificate on Completion of Project (Form 4)File: RERA- ARCHITECT CERTIFICATE FORM 4 TRIDENT BUSINESS CENTER.pdf20 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: TRIDENT COMPLETION PART - 1.PDF7 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: TRIDENT PART COMPLETION- 2.pdf7 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: TRIDENT PART COMPLETION- 3.pdf7 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: TRIDENT PART COMPLETION -4.pdf7 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: TRIDENT PART COMPLETION -5.pdf7 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: TRIDENT PART COMPLETION NO -6.pdf7 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Trident Full And Final Completion dtd 25-04-2023.pdf7 Jun 2023
Declaration about Commencement CertificateFile: FORMAT D RERA (2).pdf20 Apr 2022
Building plan approvalFile: SANCTIONED 1ST AND 2ND FLOOR.pdf16 Apr 2022
Building plan approvalFile: SANCTIONED 3RD AND 4TH FLOOR.pdf16 Apr 2022
Building plan approvalFile: SANCTIONED 5TH AND 6TH FLOOR.pdf16 Apr 2022
Building plan approvalFile: SANCTIONED 7TH AND 8TH FLOOR.pdf16 Apr 2022
Building plan approvalFile: SANCTIONED 9TH AND 10TH FLOOR.pdf16 Apr 2022
Building plan approvalFile: SANCTIONED PLAN BASEMENT 1 and 2.pdf16 Apr 2022
Building plan approvalFile: SANCTIONED PLAN LGFLR AND UGFLR.pdf16 Apr 2022
Building Plan Approval (IOD)File: SANCTIONED 1ST AND 2ND FLOOR.pdf16 Apr 2022
Building Plan Approval (IOD)File: SANCTIONED 3RD AND 4TH FLOOR.pdf16 Apr 2022
Building Plan Approval (IOD)File: SANCTIONED 5TH AND 6TH FLOOR.pdf16 Apr 2022
Building Plan Approval (IOD)File: SANCTIONED 7TH AND 8TH FLOOR.pdf16 Apr 2022
Building Plan Approval (IOD)File: SANCTIONED 9TH AND 10TH FLOOR.pdf16 Apr 2022
Building Plan Approval (IOD)File: SANCTIONED PLAN BASEMENT 1 and 2.pdf16 Apr 2022
Building Plan Approval (IOD)File: SANCTIONED PLAN LGFLR AND UGFLR.pdf16 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE (2).pdf16 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1.PDF9 Nov 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEER QUALITY ASSURANCE CERTIFICATE.PDF9 Nov 2020
Building plan approvalFile: Scan_2639-01-10_compressed.pdf4 Jun 2019
Building plan approvalFile: Scan_2640-02-10_compressed.pdf4 Jun 2019
Building plan approvalFile: Scan_2641-03-10_compressed.pdf4 Jun 2019
Building plan approvalFile: Scan_2642-04-10_compressed.pdf4 Jun 2019
Building plan approvalFile: Scan_2643-05-10_compressed.pdf4 Jun 2019
Building plan approvalFile: Scan_2644-06-10_compressed.pdf4 Jun 2019
Building plan approvalFile: 8910.pdf4 Jun 2019
Building Plan Approval (IOD)File: Scan_2639-01-10_compressed.pdf4 Jun 2019
Building Plan Approval (IOD)File: Scan_2640-02-10_compressed.pdf4 Jun 2019
Building Plan Approval (IOD)File: Scan_2641-03-10_compressed.pdf4 Jun 2019
Building Plan Approval (IOD)File: Scan_2642-04-10_compressed.pdf4 Jun 2019
Building Plan Approval (IOD)File: Scan_2643-05-10_compressed.pdf4 Jun 2019
Building Plan Approval (IOD)File: Scan_2644-06-10_compressed.pdf4 Jun 2019
Building Plan Approval (IOD)File: 8910.pdf4 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE AS.pdf4 Jun 2019
Building plan approvalFile: 1.pdf31 Jul 2017
Layout approvalFile: Info Copy.pdf31 Jul 2017
PAN CardFile: PAN Card.pdf31 Jul 2017
Copy of the legal title reportFile: Trident Title Report (2).pdf31 Jul 2017
Details of encumbrancesFile: Info Copy.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Info Copy.pdf31 Jul 2017
Building Plan Approval (IOD)File: 1.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: commencement cert 45.pdf31 Jul 2017
Declaration in FORM BFile: Info Copy.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: certificate TRIDENT.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Info Copy.pdf31 Jul 2017
Certificates of CA (Form 3)File: Info Copy.pdf31 Jul 2017
Certificates of CA (Form 5)File: Info Copy.pdf31 Jul 2017
Proforma of Allotment letterFile: Info Copy.pdf31 Jul 2017
OtherFile: Info Copy.pdf31 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
OreanOrean Baner Sno.3110CompletedFeb 2015Feb 2015
Green JewelsBaner Sno.3816CompletedJan 2014Late, Mar 2014

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 35 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRIDENT BUSINESS CENTER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near -13,700+ in Pune

2 kmTRIDENT BUSINESS CENTERCompleted 129Lapsed / revoked 40Other 110Dot size: filed unitsN

Filed coordinates, straight-line distance. 279 registered projects within 2 km.

Builder: SHIRISH BHASKAR JADHAV

SHIRISH BHASKAR JADHAV has 1 registration on MahaRERA, including TRIDENT BUSINESS CENTER. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if TRIDENT BUSINESS CENTER is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRIDENT BUSINESS CENTER?

The registered promoter entity is SHIRISH BHASKAR JADHAV, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRIDENT BUSINESS CENTER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TRIDENT BUSINESS CENTER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRIDENT BUSINESS CENTER?

The professionals named in the filing: Architect: NILESH SASWADE; Engineer: GA Bhilare Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRIDENT BUSINESS CENTER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRIDENT BUSINESS CENTER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRIDENT BUSINESS CENTER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.