Tricity waterfront
RG-MH-92411 · RERA P52000048272 · Last updated on MahaRERA portal: 5 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
- Rs 35.00 crore secured on the land, in favour of ADITYA BIRLA HOUSING FINANCE LIMITED
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 4 earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Tricity waterfront is a Others project by Tricity Realty LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000048272 on 22 Dec 2022. Possession is promised by 31 Dec 2029. The completion date has moved by 24 months from the original filing. 137 of the 168 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameTricity waterfront
- TypeOthers
- Location
- Shiv Mandir Road
- Roadpali
- kalamboli
- Kalamboli
- Panvel
- Raigarh
- 410218
- Pincode410218
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000048272
- ReraGenie IDRG-MH-92411
Builder
- NameTricity Realty LLP
- Entity typePartnership
- GSTIN27AAKFT6601L1ZT
- PartnersAngad Kulbir Singh Rekhi, Kulbir Singh Dayal Singh Rekhi, Moksh Srichand Pardasani, Savinder Singh Devinder Singh Lamba, Harvinder Singh Devinder Singh Lamba, Manish Srichand Pardasani, Arjun Rekhi
- Other registrations13 more →
- Completed6 of 14
- Declared earlier projects14 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Dec 2022
- Promised completion31 Dec 2029
- Revised completionRevised to 31 Dec 2029 (originally 31 Dec 2027)
- Buildings1 building record
- Documents filed135 files
Current status
Figures as on 5 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tricity Waterfront | NA | 21 | 15 | 139 | 29 | 168 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 88%.
Tricity Waterfront: 68% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 88% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 32% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 66% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 38% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 68% |
Progress on shared amenities15
As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 90% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 10% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed190
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Tricity Waterfront | NA | Rs 54.00 cr | Rs 26.46 cr |
| - | NA | Rs 7.75 cr | Rs 54.26 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | The Firm |
| Engineer | CSE Consultants |
| Chartered Accountant | Vikas Kamra & Co |
| Chartered Accountant | Umesh Aswani & Co |
| Partner | Role in project |
|---|---|
| Tricity Realty LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWith reference to the observation that compliance was submitted after 166 days, we most respectfully submit that the delay was neither deliberate nor due to negligence. The delay occurred primarily due to the time required to obtain consents from allottees, which involved: • Extensive coordination and communication with numerous allottees; • Conducting meetings and follow-ups to explain revised timelines and project status; • Collection, verification, and compilation of written consents and supporting documentation; • Preparation of updated reports and the PERT Chart in compliance with procedu
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Nov 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Jun 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed135
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 135 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 WF 31032026.pdf | 5 May 2026 |
| Withdrawal Update Form 2File: Form 2 WF 31032026.pdf | 5 May 2026 |
| Withdrawal Update Form 3File: FORM 3 WF 31032026 final.pdf | 5 May 2026 |
| Form 1File: 3 Form 1 Tricity Waterfront 31122025 ok.pdf | 14 Feb 2026 |
| Form 2File: 3 form 2 waterfront 31122025 ok.pdf | 14 Feb 2026 |
| Form 3File: 3 Withdrawal Application Form3 Waterfront ok.pdf | 14 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: disclosure WF.pdf | 14 Feb 2026 |
| Form 1File: Form 1 WF 30092025.pdf | 8 Jan 2026 |
| Form 2File: Form 2 WF 30092025.pdf | 8 Jan 2026 |
| Form 3File: Form 3 WF 30092025 final.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure sold unsold wf.pdf | 8 Jan 2026 |
| Form 1File: Form 1 30062025.pdf | 8 Sep 2025 |
| Form 2File: Form 2 30062025.pdf | 8 Sep 2025 |
| Form 3File: form 3 WF 30062025 final.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure sold unsold 30062025.pdf | 8 Sep 2025 |
| Form 1File: 1 form 1 31122022.pdf | 8 Sep 2025 |
| Form 2File: 1 form 2 31122022.pdf | 8 Sep 2025 |
| Form 3File: 1 form 3 31122022.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 1 Disclosure Sold Unsold Inventory 31122022.pdf | 8 Sep 2025 |
| Form 1File: 2 form 1 31032023.pdf | 8 Sep 2025 |
| Form 2File: 2 Form 2 31032023.pdf | 8 Sep 2025 |
| Form 3File: 2 form 3 31032023.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 2 Disclosure Sold Unsold Inventory 31032023.pdf | 8 Sep 2025 |
| Form 1File: 3 form 1 30062023.pdf | 8 Sep 2025 |
| Form 2File: 3 form 2 30062023.pdf | 8 Sep 2025 |
| Form 3File: 3 form 3 30062023.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 3 Disclosure Sold Unsold Inventory 30062023.pdf | 8 Sep 2025 |
| Form 1File: 4 form 1 30092023.pdf | 8 Sep 2025 |
| Form 2File: 4 form 2 30092023.pdf | 8 Sep 2025 |
| Form 3File: 4 form 3 30092023.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 4 Disclosure Sold Unsold Inventory 30092023.pdf | 8 Sep 2025 |
| Form 1File: 5 form 1 31122023.pdf | 8 Sep 2025 |
| Form 2File: 5 form 2 31122023.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 5 Disclosure Sold Unsold Inventory 31122023.pdf | 8 Sep 2025 |
| Form 3File: 5 form 3 31122023.pdf | 8 Sep 2025 |
| Form 1File: 6 form 1 31032024.pdf | 8 Sep 2025 |
| Form 2File: 6 form 2 31032024.pdf | 8 Sep 2025 |
| Form 3File: 6 form 3 31032024.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 6 Disclosure Sold Unsold Inventory 31032024.pdf | 8 Sep 2025 |
| Form 1File: 7 form 1 30062024.pdf | 8 Sep 2025 |
| Form 2File: 7 form 2 30062024.pdf | 8 Sep 2025 |
| Form 3File: 7 form 3 30062024.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 7 Disclosure Sold Unsold Inventory 30062024.pdf | 8 Sep 2025 |
| Form 1File: 8 form 1 30092024.pdf | 8 Sep 2025 |
| Form 2File: 8 form 2 30092024.pdf | 8 Sep 2025 |
| Form 3File: 8 form 3 30092024.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 8 Disclosure Sold Unsold Inventory 30092024.pdf | 8 Sep 2025 |
| Form 1File: 9 form 1 31122024.pdf | 8 Sep 2025 |
| Form 2File: 9 form 2 31122024.pdf | 8 Sep 2025 |
| Form 3File: 9 form 3 31122024.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 9 Disclosure Sold Unsold Inventory 31122024.pdf | 8 Sep 2025 |
| Form 1File: 10 form 1 31032025.pdf | 8 Sep 2025 |
| Form 2File: 10 form 2 31032025.pdf | 8 Sep 2025 |
| Form 3File: 10 form 3 31032025.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 10 Disclosure Sold Unsold Inventory 31032025.pdf | 8 Sep 2025 |
| Declaration in FORM BFile: Form -B.pdf | 14 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 6 (5).pdf | 7 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tricity Waterfront.pdf | 4 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Cert Q4 FY 24-25 waterfont.pdf | 4 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Cert Q4 FY 24-25 waterfront.pdf | 4 May 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Sold Unsold Q4 FY 24-25 waterefront.pdf | 4 May 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 1 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tricity Waterfront Architects Certificate.pdf | 31 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Waterfront CA Cert.pdf | 31 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Tricity Waterfront Engineers'S Certificate.pdf | 31 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: tricity Waterfront Disclosure of Sold_0001.pdf | 31 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tricity waterfront Architects certificate.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cert.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Tricity Waterfront.pdf | 25 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Tricity Waterfront Disclosure Of Sold Booked Inventory.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Waterfront Architects Certificate.pdf | 3 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Waterfront Engineers Cetificate.pdf | 3 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: WF Disclosure Of Sold And Booked Inventory.pdf | 3 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: WF CA Certificate.pdf | 3 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 5 Waterfront.pdf | 22 Jun 2024 |
| Building plan approvalFile: Drawing 1 to 3 pg.pdf | 20 Jun 2024 |
| Building plan approvalFile: Drawing 4 to 6 pg.pdf | 20 Jun 2024 |
| Building plan approvalFile: Drawing 7 to 9 pg.pdf | 20 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Drawing 1 to 3 pg.pdf | 20 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Drawing 4 to 6 pg.pdf | 20 Jun 2024 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Tricity Promenade | Plot No.20A Sector-38 Nerul Navi Mumbai-400706 | 69 | Completed | Sep 2023 | Oct 2019 |
| Tricity Panache | Plot No.7 Sector-38 Nerul Navi Mumbai-400706 | 64 | Completed | Sep 2023 | Sep 2019 |
| Tricity Palacio | Plot No.5 Sector-38 Nerul Navi Mumbai-400706 | 52 | Completed | Sep 2023 | Oct 2019 |
| Tricity Luxuria | Plot No.104 Sector-17 New Panvel West-410206 | 158 | Completed | Sep 2023 | Jul 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 13 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 135 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Tricity waterfront on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Roadpali, kalamboli5,900+ in Raigarh
Filed coordinates, straight-line distance. 79 registered projects within 2 km.
Plot No -77 Sector -17 Kalamboli Bus Depot
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
BHAVESHWAR AQUA - 1
BHAVESHWAR INFRATECH
ETERNIA
GREENSCAPE DEVELOPERS PRIVATE LIMITED
MONARCH BROOKEFIELDS
MONARCH BROOKEFIELDS LLP
BHAVESHWAR AQUA - 2
BHAVESHWAR INFRATECH
OM REGENCY
OSCAR INFRASTRUCTURE PRIVATE LIMITED
See every Raigarh project, with the district possession charts
Builder: Tricity Realty LLP
TRICITY REALTY LLP has 14 registrations on MahaRERA, including TRICITY PALACIO and TRICITY PANACHE. Its filings disclose 14 earlier MahaRERA projects: declares 12 of 14 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Tricity waterfront is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Tricity waterfront?
The registered promoter entity is Tricity Realty LLP, a partnership as per the filing. Its GSTIN 27AAKFT6601L1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Tricity waterfront?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Tricity waterfront?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Tricity waterfront?
The professionals named in the filing: Architect: The Firm; Engineer: CSE Consultants; Chartered Accountant: Vikas Kamra & Co; Chartered Accountant: Umesh Aswani & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Tricity waterfront?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback