Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
May 2026Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 78 documents Report an error

Tranquil is a Residential/Group Housing project by Tapovan Estates in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/291223/006519 on 29 Dec 2023. Possession is promised by 1 May 2026. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameTranquil
  • TypeResidential/Group Housing
  • Location
    • MYSORE
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1268/378/PR/291223/006519
  • ReraGenie IDRG-KA-59365

Builder

  • NameTapovan Estates
  • Entity typePartnership Firm
  • GSTIN29AAPFT4792B1ZP
  • Authorized SignatoryRajiv krishna
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2023First promiseMay 2025Revised toMay 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on29 Dec 2023
  • Promised completion1 May 2026
  • Revised completionRevised to 1 May 2026 (originally 1 May 2025)
  • Buildings2 building records
  • Documents filed78 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tapovan Estate Part A---30030
Tapovan Estate Part B---17017

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 9 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 9 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupNoNot applicable
Piped GasYes-
Water and SanitationYes-
Air ConditioningYes-
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
B M Pramod--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 21.00 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 21.00 cr-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectkokila K N
EngineerD V Yogisha Rao

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1268/378/PR/250718/006519May 2025 → May 2026

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed78

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/291223/006519 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Power Supply NOCFile: Electricity NOC.pdf9 Jul 2025
Quarterly UpdatesFile: Quarterly Return Update details.png2 Jul 2025
Annual Audit ReportFile: Annual Audit Report Submission.pdf2 Jul 2025
CA certificate Form - 7File: CA Certificate Form-7.pdf2 Jul 2025
ECFile: EC.pdf2 Jul 2025
Notarized Affidavit in form EX-7File: Form EX7.pdf2 Jul 2025
Form - BFile: Form B.pdf2 Jul 2025
Plan Sanction LetterFile: Plan Sanction letter.pdf2 Jul 2025
Building Plan SanctionFile: Plan Sanction.pdf2 Jul 2025
Engineer Certificate Form-Ex5File: Form EX5.pdf2 Jul 2025
Engineer Certificate Form-Ex6File: Form EX6.pdf2 Jul 2025
Water Supply NOCFile: Water NOC.pdf2 Jul 2025
CHARTERED ACCOUNTANT CERTIFICATE FORM -1File: Form 1 new.pdf28 Dec 2023
CA CERTIFICATEFile: Form 1.pdf18 Dec 2023
SOURCES OF FUNDFile: Source of Fund.jpeg18 Dec 2023
BALANCE SHEET AND PROFIT AND LOSS ACCOUNTFile: Balace sheet & P & L 2022-23.pdf18 Dec 2023
PARTNERSHIP CERTIFICATEFile: Partnership Certificate.pdf18 Dec 2023
HEIGHT OF THE BUILDINGFile: Height of the Building.pdf18 Dec 2023
KSPCBFile: KSPCB.pdf18 Dec 2023
SINGLE PLOT LAYOUTFile: Single Layout Plan.pdf18 Dec 2023
SINGLE PLOT ORDERFile: Single Layout Plan.pdf18 Dec 2023
CDPFile: CDP Map.pdf18 Dec 2023
VILLAGE MAPFile: Village map.pdf18 Dec 2023
COMMENCEMENT CERTIFICATEFile: Commencement Certificate.pdf18 Dec 2023
BUILDING LICENCEFile: Building Licence.pdf18 Dec 2023
STP DRAWINGFile: STP Drawing.pdf18 Dec 2023
ESTIMATION OF CONSTRUCTIONFile: Estimation of Construction Cost.pdf18 Dec 2023
FORM 3File: Form - 3.pdf18 Dec 2023
CIVIL WORKFile: Civil Work.pdf18 Dec 2023
GUIDENCE VALUEFile: Guidence Value.jpeg18 Dec 2023
STRUCTURAL SAFETYFile: Structural Safety Adopted.pdf18 Dec 2023
ALLOTMENT LETTERFile: Tranquil Allotment Letter.pdf18 Dec 2023
SALE AGREEMENTFile: Tranquil Sale Agreement.pdf18 Dec 2023
WATER NOC AND FEE RECEIPTFile: Water NOC & fees receipt.pdf18 Dec 2023
WATER NOCFile: Water NOC.pdf18 Dec 2023
AFFIDAVITFile: Affidavit.pdf18 Dec 2023
KHATAFile: Katha.pdf18 Dec 2023
ZONAL REGULATION COPYFile: 3 MUDA ZR Copy.pdf18 Dec 2023
PROJECT SPECIFICATIONFile: Project Specification.pdf18 Dec 2023
RTC, survey 167/1-
Mutation, survey 167/1-
Encumbrance Certificate, survey 167/1-
Conversion/Alienation Order, survey 167/1-
Sale/Title/Gift Deed, survey 167/1-
JDA, survey 167/1-
Khatha, survey 167/1-
Registration CertificateFile: Partnership Certificate.pdf-
Partnership DeedFile: Reconstitute of partneship deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1 new.pdf-
Certificate issued by Architect Form 2File: Form-2.pdf-
Certificate issued by Engineer Form 3File: Form - 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit No-Litigation.pdf-
Certificate from Chartered AccountFile: Form 1 new.pdf-
Balance Sheet 2021 - 2022File: ITR & Balanace Sheet & P & L 2021-22.pdf-
Balance Sheet 2020 - 2021File: ITR & Balance sheet & P & L 2020-2021.pdf-
Audited Profit and Loss Statement 2021 - 2022File: ITR & Balanace Sheet & P & L 2021-22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: ITR & Balance sheet & P & L 2020-2021.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR 2021-22.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 2020-2021.pdf-
Layout Aproval-
Plan Sanction-
Plan Sanction-
Legal Opinion-
Form-B-
Affidavit-
affidavit cum declaration-
KSPCB NOC-
Guidence Value-
General Power Of Authorny-
Work Order-
Form - 6-
Layout Plan-
Latest Encumbrance CertificateFile: EC.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
HARMONY NIRVANA Phase -IHarmony Nirvana, Hadajana Village, Varuna Hobli, Mysuru taluk,OngoingAug 2023Not delivered

How this compares with Mysore

28%of Mysore projects moved their completion datethis one moved by 12 months
0%of Mysore registrations are shown as withdrawn or revokedthis one is not

Computed across the 700+ Mysore projects on ReraGenie, from their own filings.

Keep Tranquil on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mysore700+ in Mysore

Builder: Tapovan Estates

Tapovan Estates has 2 registrations on RERA Karnataka, including HARMONY NIRVANA Phase -I and Tranquil. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Mysore district page.

Frequently asked questions

What are my rights if Tranquil is delayed beyond 1 May 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Tranquil?

The registered promoter entity is Tapovan Estates, a partnership firm as per the filing. Its GSTIN 29AAPFT4792B1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Tranquil?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Tranquil?

The professionals named in the filing: Architect: kokila K N; Engineer: D V Yogisha Rao. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Tranquil?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Tranquil. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Tranquil to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.