ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / TOWN CENTRE

Registration lapsed No litigation declared Mixed project

TOWN CENTRE

By FANNAN BUILDERS AND DEVELOPERS

RG-MH-93314 · RERA P52000011650 · Last updated on MahaRERA portal: 29 Sep 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 49 months past the filed date
  • 5 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Sep 2022Possession promised49 months past this date
3 of 33Construction stages doneacross 4 buildings; furthest along: Excavation, 80%
5Complaints at MahaRERAon this registration
Jump to the 19 documents Report an error

TOWN CENTRE is a Mixed project by FANNAN BUILDERS AND DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000011650 on 31 Aug 2017. Possession was promised by 15 Sep 2022 and is now 49 months past that date. 5 complaints are on record with the regulator.

At a glance

Project

  • NameTOWN CENTRE
  • TypeMixed
  • Location
    • OLD MUMBAI PUNE HIGHWAY
    • KHOPOLI
    • Khalapur
    • Raigarh
    • 410203
  • Pincode410203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000011650
  • ReraGenie IDRG-MH-93314

Builder

  • NameFANNAN BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnerMOHD ZAHID HUSSAIN SHAIKH

Key dates

49 months past promisethis monthRegisteredAug 2017PromisedSep 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion15 Sep 2022
  • Revised completionNone
  • Buildings3 building records
  • Documents filed19 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING 2NA50000
BUILDING 3NA50000
BUILDING NO 1 PROPOSEDNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 29 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 33 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 80%.

BUILDING 27%
ActivityProgress
Excavation80%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING 341%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 1 PROPOSED0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 29 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Open Space1

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,105 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
DILIP GOPAL JADHAVKhopoliRaigarh
DEEPAK GOPAL JADHAVKhopoliRaigarh
SUNIL RAMCHANDRA GHAWATEKhopoliRaigarh
ANIL RAM GHAVATEKhopoliRaigarh

Approvals and building plan

Permissible FSI7259.05
Proposed, not sanctioned4,449 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMARATHA MANDIR MUMBAI 400008

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKISHOR VITHAL SHINDE
PartnerRole in project
FANNAN BUILDERS AND DEVELOPERS-

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000396170Amita Prakash Chawarem/s Fannan bUILDERS & DEVELOPERS12/06/2023
CC006000000364700Viju Namdev HangeM/s. Fannan Builders and Developers through its authorized partners & Ors.09/03/2023
CC006000000395949Vijay Khemraj Rathourmohammad zahid hussain03/06/2023
CC12500393Zakir U DinwareFANNAN BUILDERS AND DEVELOPERS05/02/2025
CC12503548manyar vasim dagadu shaikhFANNAN BUILDERS AND DEVELOPERS05/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Aug 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed19

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5.pdf29 Sep 2021
Annual Audit Report of Statutory CA (Form 5)File: Form 5 Signed.pdf29 Sep 2020
Annual Audit Report of Statutory CA (Form 5)File: 1718 Town Centre Form 5.pdf30 Sep 2019
Annual Audit Report of Statutory CA (Form 5)File: 1819 Town Centre Form 5.pdf30 Sep 2019
Layout approvalFile: Building 2 Layout.pdf16 Aug 2017
Layout approvalFile: Building 3 Layout.pdf16 Aug 2017
Building plan approval or NA orderFile: Location Plan.pdf16 Aug 2017
PAN CardFile: pan FIRM.pdf16 Aug 2017
Copy of the legal title reportFile: Search Report.pdf16 Aug 2017
Details of encumbrancesFile: Encumbrance.pdf16 Aug 2017
Copy of Layout Approval (in case of layout)File: Building 2 Layout.pdf16 Aug 2017
Copy of Layout Approval (in case of layout)File: Building 3 Layout.pdf16 Aug 2017
Building Plan Approval (IOD)File: Location Plan.pdf16 Aug 2017
Declaration in FORM BFile: Form B Developer.pdf16 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 BUilding No 2 and 3.pdf16 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 FInal.pdf16 Aug 2017
Certificates of CA (Form 3)File: Form 3222.pdf16 Aug 2017
Proforma of Allotment letterFile: Agreement and Allotment Letter.pdf16 Aug 2017
OtherFile: Aadhar Card declaration.pdf16 Aug 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TOWN CENTRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHOPOLI5,900+ in Raigarh

2 kmTOWN CENTRECompleted 37Lapsed / revoked 27Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: FANNAN BUILDERS AND DEVELOPERS

FANNAN BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including TOWN CENTRE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that TOWN CENTRE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if TOWN CENTRE is delayed beyond 15 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TOWN CENTRE?

The registered promoter entity is FANNAN BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TOWN CENTRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against TOWN CENTRE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for TOWN CENTRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TOWN CENTRE?

The professionals named in the filing: Architect: KISHOR VITHAL SHINDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TOWN CENTRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TOWN CENTRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TOWN CENTRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.