ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Tower - One 52

Registered No litigation declared Commercial project

Tower - One 52

By ANU CONSTRUCTIONS

RG-MH-23059 · RERA P52100032655 · Last updated on MahaRERA portal: 24 Mar 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 68%
0Complaints at MahaRERAon this registration
Jump to the 129 documents Report an error

Tower - One 52 is a Commercial project by ANU CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100032655 on 17 Jan 2022. Possession is promised by 20 Dec 2027.

At a glance

Project

  • NameTower - One 52
  • TypeCommercial
  • Location
    • SOLAPUR ROAD
    • HADAPSAR
    • Haveli
    • Pune
    • 411013
  • Pincode411013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100032655
  • ReraGenie IDRG-MH-23059

Builder

  • NameANU CONSTRUCTIONS
  • Entity typePartnership
  • PartnersABHAY NIVRITTI BHOSALE, TEJPAL NAVALMAL JAIN, CHETAN BHAIRULAL RATHOD

Key dates

this monthRegisteredJan 2022PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Jan 2022
  • Promised completion20 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed129 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A 1NA97000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 68%.

A 1: 6% average across the applicable activities

ActivityProgress
Excavation68%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed140

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots140
Closed/Covered140

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,381 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
ANUSUYA AJIT KUMAR MEHTAPune (M Corp.)Pune
TUSHAR AJITKUMAR MEHTAPune (M Corp.)Pune
Jairaj Ajitkumar MehtaPune (M Corp.)Pune
Deepti Ashok SahaPune (CB)Pune

Approvals and building plan

Sanctioning authorityPUNE MUNCIPAL CORPORATION
Permissible FSI11339.62
Proposed, not sanctioned6,115 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDECCAN GYMKHANA

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKANHEKAR PRAKASH
EngineerVineet Deshmukh
Chartered AccountantRSVA & Co.
Chartered AccountantSPAK & CO
PartnerRole in project
ANU CONSTRUCTIONS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 20 Dec 2027

Documents filed129

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 129 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: March 22.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 22.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: June 22.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 22.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 23.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: June 23.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 23.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 23.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 24.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 24.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 24.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 24.pdf24 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_Anu Construction_March 2022_compressed.pdf21 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form -2A_Anu Construction_March 2023_compressed.pdf21 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_Anu Construction_March 2024_compressed.pdf21 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dec 2024_compressed.pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: June 2024_compressed (1).pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: March 2024_compressed (2).pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dec 2023_compressed (1).pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: June 2023_compressed.pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dec 2022_compressed.pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sep 2022_compressed.pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: June 2022_compressed.pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: March 2022_compressed.pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: March 2023_compressed.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June 23.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 24_compressed.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sep 2024_compressed.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June 2024_compressed.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: March 2024_compressed (1).pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 2023_compressed.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sep 23.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 23.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 22.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sep 22.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June 22.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 22.pdf20 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2) Form-1 Anu Construction june22.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1) Form-1 Anu Construction Mar22.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12) Form-1 Anu Construction Dec24.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11) Form-1 Anu Construction Sep24.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10) Form-1 Anu Construction June24.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9) Form-1 Anu Construction Mar24.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8) Form-1 Anu Construction Dec23.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7) Form-1 Anu Construction Sep23.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6) Form-1 Anu Construction june23.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5) Form-1 Anu Construction Mar23.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4) Form-1 Anu Construction Dec22.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3) Form-1 Anu Construction Sep22.pdf18 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anu Construction F3 Sep 24_11zon.pdf27 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Anu Construction F5 2023-24.pdf27 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Tower - One 52.pdf15 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect certificate.pdf2 Mar 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold,booked inventory.pdf1 Mar 2023
Layout approvalFile: Approval Layout Page 1.pdf28 Feb 2023
Layout approvalFile: Approval Layout Page 2.pdf28 Feb 2023
Building plan approvalFile: Building pg1.pdf28 Feb 2023
Building plan approvalFile: Building pg2.pdf28 Feb 2023
Building plan approvalFile: Building pg3.pdf28 Feb 2023
Building plan approvalFile: Building pg4.pdf28 Feb 2023
Building plan approvalFile: Building pg5.pdf28 Feb 2023
Building plan approvalFile: Building pg6.pdf28 Feb 2023
Building plan approvalFile: Building pg7.pdf28 Feb 2023
Building plan approvalFile: Building pg8.pdf28 Feb 2023
Building plan approvalFile: Building pg9.pdf28 Feb 2023
Building plan approvalFile: Building pg10.pdf28 Feb 2023
Building plan approvalFile: Building pg11.pdf28 Feb 2023
Building plan approvalFile: Building pg12.pdf28 Feb 2023
Building plan approvalFile: Building pg13.pdf28 Feb 2023
Building plan approvalFile: Building pg14.pdf28 Feb 2023
Copy of Layout Approval (in case of layout)File: Approval Layout Page 1.pdf28 Feb 2023
Copy of Layout Approval (in case of layout)File: Approval Layout Page 2.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Building pg1.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Building pg2.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Building pg3.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Building pg4.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Building pg5.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Building pg6.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Building pg7.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Building pg8.pdf28 Feb 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Tower - One 52 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HADAPSAR13,700+ in Pune

2 kmTower - One 52Completed 25Lapsed / revoked 17Other 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 74 registered projects within 2 km.

Builder: ANU CONSTRUCTIONS

ANU CONSTRUCTIONS has 1 registration on MahaRERA, including Tower - One 52. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Tower - One 52 is delayed beyond 20 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Tower - One 52?

The registered promoter entity is ANU CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Tower - One 52?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Tower - One 52?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Tower - One 52?

The professionals named in the filing: Architect: KANHEKAR PRAKASH; Engineer: Vineet Deshmukh; Chartered Accountant: RSVA & Co.; Chartered Accountant: SPAK & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Tower - One 52?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Tower - One 52. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Tower - One 52 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.