Home / Browse projects / Dhule, Maharashtra / TIRTH PUSHPAM
TIRTH PUSHPAM
By PIYUSH LIFESPACES PRIVATE LIMITED
RG-MH-13254 · RERA P49800023856 · Last updated on MahaRERA portal: 15 Apr 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 4 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Dhule registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TIRTH PUSHPAM is a Residential / Group Housing project by PIYUSH LIFESPACES PRIVATE LIMITED in Dhule, Maharashtra, registered with MahaRERA as P49800023856 on 7 Jan 2020. The registration is recorded completed; possession was promised by 30 Dec 2024.
At a glance
Project
- NameTIRTH PUSHPAM
- TypeResidential / Group Housing
- Location
- SURVEY NO 8 JAIHIND COLONY DEOPUR DHULE
- JAIHIND COLONY DEOPUR
- Dhule (M Corp.)
- Dhule
- 424002
- Pincode424002
- MapView location on Google Maps (as filed on RERA)
- RERA no.P49800023856
- ReraGenie IDRG-MH-13254
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on7 Jan 2020
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed76 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TIRTH PUSHPAM | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
TIRTH PUSHPAM: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities20
As on 15 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
| SOLAR WATER SYSTEM | Yes | 100% |
| OVERHEAD TANK | Yes | 100% |
| MAIN ENTRANCE GATES | Yes | 100% |
| LIFT ELEVATOR | Yes | 100% |
| CCTV AND INTERCOM SYSTEM | Yes | 100% |
Parking filed16
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| PIYUSH LIFESPACES PRIVATE LIMITED | Dhule (M Corp.) | Dhule |
| PURUSHOTTAM GOPALRAO KAUJALGI | Dhule (M Corp.) | Dhule |
| VENKATESH GOPALRAO KAUJALGI | Aanandwali | Nashik |
| PURUSHOTTAM GOPALRAO KAUJALGI AND OTHERS | Dhule (M Corp.) | Dhule |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR RAJENDRA SWARUPCHAND CHHAJED |
| Engineer | MR RAJENDRA SWARUPCHAND CHHAJED |
| Engineer | MR ABHAY RAVINDRA BOBDE |
| Engineer | MR RAHUL RAVIKUMAR TOLANI |
| Chartered Accountant | MR ANIL MADHUSUDAN GUJRATHI |
| Chartered Accountant | MR SHRIRAM KESHAV DESHPANDE |
| Partner | Role in project |
|---|---|
| PIYUSH LIFESPACES PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Sep 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 28 Mar 2023
Documents filed76
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of ConveyanceFile: TIRTHPUSHPAM STATUS OF CONVEYANCE 14 APRIL 2025.pdf | 15 Apr 2025 |
| Status of ConveyanceFile: TP STATUS OF CONVEYANCE APRIL 25.pdf | 11 Apr 2025 |
| Status of ConveyanceFile: TIRTHPUSHPAM STATUS OF CONV.pdf | 13 Jan 2025 |
| Status of ConveyanceFile: Status Of Conveyance TP October 2024.pdf | 11 Oct 2024 |
| Status of ConveyanceFile: Status Of Conveyance TP October 2024.pdf | 11 Oct 2024 |
| Status of ConveyanceFile: STATUS OF CONVEYANCE TP JUNE24.pdf | 6 Jul 2024 |
| Status of ConveyanceFile: Status Of Conveyance March 2024 TP.pdf | 3 Apr 2024 |
| Status of ConveyanceFile: STATUS OF CONVEYANCE TP DECEMBER 2023.pdf | 10 Jan 2024 |
| Status of ConveyanceFile: Status of Conveyance TP sept 2023.pdf | 21 Oct 2023 |
| Deviation Report with respect to Allotment letterFile: Declaration Regarding Deviation report with respect to Allotment letter TP Sept 23.pdf | 21 Oct 2023 |
| Deviation Report with respect to model copy of AgreementFile: Declaration regarding deviation report with respect to model copy of the agreement to sale | 21 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Engineer's Certificate Tirthpushpam June 2023.pdf | 11 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Disclousure Of Sold and Booked Inventory Tirthpushpam June 2023.pdf | 11 Jul 2023 |
| Status of ConveyanceFile: Status of Conveyance Tirthpushpam June 2023.pdf | 11 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect's certificate TP APRIL23.pdf | 22 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 Engineer's Certificate TP APRIL23.pdf | 22 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A TP APRIL23.pdf | 22 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure Of Sold And Booked Inventory TP APRIL23.PDF | 22 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3 TP APRIL23.PDF | 22 Apr 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architechts certificate TP APRIL23.pdf | 22 Apr 2023 |
| Status of ConveyanceFile: Status of Conveyance TP APRIL23.pdf | 22 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate Tirthapushpam.pdf | 28 Mar 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 ARCHITECT CERTIFICATE TIRTHPUSHPMA.pdf | 28 Mar 2023 |
| Other - TechnicalFile: COMPLETION CERTIFICATE of ARCHITECT TP.pdf | 16 Mar 2023 |
| Other - TechnicalFile: Application for OC TP.pdf | 16 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 REVISED TP.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 17-18 TP 24 01 2023.pdf | 24 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19 TP 24 01 2023.pdf | 24 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 TP 21 22 24 01 23.pdf | 24 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 TP 23 01 2023.pdf | 23 Jan 2023 |
| Proforma of Agreement for saleFile: AGREEMENT FOR SALE Flat no 5 Mr Narandra borase PDF.pdf | 17 Jan 2023 |
| Proforma of Allotment letterFile: MODEL FORMAT OF ALLOTMENT LETTER TP JAN23 PDF.pdf | 17 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: FORM 1 B TP 16 01 23.pdf | 16 Jan 2023 |
| Details of encumbrances concerned to LegalFile: FORM 1 B TP 16 01 23.pdf | 16 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 TP 16 01 2023.pdf | 16 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 TP 16 0123.pdf | 16 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SALE TP 16 01 2023.pdf | 16 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 TP 16 01 2023.pdf | 16 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOUSERE OF INTEREST IN OTHER REAL ESTATE ORGNISATIONS TP 16 01 23.pdf | 16 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A TP 16 01 2023.pdf | 16 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2 A 21 22.pdf | 6 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2021 22.pdf | 19 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY JUNE MONTH.pdf | 19 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERT TP 23 FEB 2022.pdf | 24 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE TP 23 FEB 2022.pdf | 24 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY 24 FEB 2022.pdf | 24 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CHARTERED ACCOUNTANT CERTIFICATE 24 FEB 2022.pdf | 24 Feb 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200228140620_For_Asset_Based_Search_15_01_2022_13_52_20_723 TIRTHPUSH | 15 Jan 2022 |
| Declaration about Commencement CertificateFile: Form D TP.pdf | 5 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Sold and Booked Inventory TP.pdf | 5 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 20 07 21.pdf | 21 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 tp 19-20.pdf | 21 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf | 21 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Foem 2A 310321.pdf | 7 Apr 2021 |
| Building plan approvalFile: sanction plan after tdr tirthpushpam.pdf | 11 Sep 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: sanction plan after tdr tirthpushpam.pdf | 11 Sep 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: After TDR commencement.pdf | 11 Sep 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: After TDR commencement.pdf | 11 Sep 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A 07 07 2020.pdf | 7 Jul 2020 |
| Details of Restarting of Construction work post lockdownFile: Restarting construction letter.pdf | 16 Jun 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf | 7 Apr 2020 |
| Layout approvalFile: LAY OUT JAIHIND TP PDF.pdf | 3 Jan 2020 |
| Building plan approvalFile: N A ORDER TIRTHPUSHPAM.pdf | 3 Jan 2020 |
| Building plan approvalFile: APPROVED PLAN.pdf | 3 Jan 2020 |
| PAN CardFile: PLPL PAN.pdf | 3 Jan 2020 |
| Copy of the legal title reportFile: TITLE CLEARANCE CERTIFICATE.pdf | 3 Jan 2020 |
| Details of encumbrancesFile: NON ENCUMBRANCES CERTIFICATE.pdf | 3 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: LAY OUT JAIHIND TP PDF.pdf | 3 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: N A ORDER TIRTHPUSHPAM.pdf | 3 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: APPROVED PLAN.pdf | 3 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE TIRTH PUSHPAM.pdf | 3 Jan 2020 |
| Declaration in FORM BFile: FORM B COMMON TP.pdf | 3 Jan 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO 1 TP.pdf | 3 Jan 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM NO 2 TP.pdf | 3 Jan 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM NO 3 TP.pdf | 3 Jan 2020 |
| Proforma of Allotment letterFile: PROFORMA OF ALLOTMENT LETTER AGREEMET FOR SALE TP.pdf | 3 Jan 2020 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| CHANDRAVEL PHASE 3 | NEAR CHANDRAVEL PHASE 2 NAKANE ROAD WALWADI DHULE | 42 | Completed | Dec 2019 | Dec 2017 |
| JASMINE | JAIHIND COLONY DEOPUR DHULE | 10 | Completed | Mar 2017 | Jan 2017 |
| AMRUTVEL PHASE 2 | VIMALNATH NAGAR NEAR STATION ROAD DHULE | 4 | Completed | Sep 2016 | Feb 2016 |
| CHANDRAVEL PHASE 2 | NEAR CHANDRAVEL PHASE 1 WALWADI DEOPUR DHULE | 25 | Completed | Dec 2015 | Jun 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dhule
Computed across the 71 Dhule projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 76 filed documents as one ZIP, foldered, with a manifest
Keep TIRTH PUSHPAM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near JAIHIND COLONY DEOPUR71 in Dhule
Filed coordinates, straight-line distance. 24 registered projects within 2 km.
SHIVAM PLAZA
ALKA VASANTRAO WANKHEDE
Bhalchandra Regency
Om Shiv Infra
Nakshatram Athashri
Divine Infrastructure
Dreams Anuram
Dream House Builders And Developers
Dream's GTP
New Dream House Builders and Developers
NAKSHATRA AVENUE
DHARMNITI CONSTRUCTION PRIVATE LIMITED
See every Dhule project, with the district possession charts
Builder: PIYUSH LIFESPACES PRIVATE LIMITED
PIYUSH LIFESPACES PRIVATE LIMITED has 3 registrations on MahaRERA, including CHANDRAVEL3 and BRAHMAKAMAL. Its filings disclose 18 earlier MahaRERA projects: declares 18 of 18 past projects completed on time. Read the full track record. See more projects on the Dhule district page.
Frequently asked questions
What are my rights if TIRTH PUSHPAM is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TIRTH PUSHPAM?
The registered promoter entity is PIYUSH LIFESPACES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TIRTH PUSHPAM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for TIRTH PUSHPAM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TIRTH PUSHPAM?
The professionals named in the filing: Architect: MR RAJENDRA SWARUPCHAND CHHAJED; Engineer: MR RAJENDRA SWARUPCHAND CHHAJED; Engineer: MR ABHAY RAVINDRA BOBDE; Engineer: MR RAHUL RAVIKUMAR TOLANI; Chartered Accountant: MR ANIL MADHUSUDAN GUJRATHI; Chartered Accountant: MR SHRIRAM KESHAV DESHPANDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TIRTH PUSHPAM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback