Home / Browse projects / Mumbai Suburban, Maharashtra / THE ZONE

Registered No litigation declared Residential / Group Housing project

THE ZONE

By MS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION

RG-MH-24511 · RERA P51800006553 · Last updated on MahaRERA portal: 25 Jul 2026

Source: official MahaRERA filing

Red flags

  • 5 complaints at MahaRERA
  • Completion date moved by 71 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 71 months from the original
5 of 11Construction stages donefurthest along: Staircases, 85%
0 of 54Units unsoldnot recorded sold or booked
5Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

THE ZONE is a Residential / Group Housing project by MS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006553 on 14 Aug 2017. Possession is promised by 30 Dec 2026. The completion date has moved by 71 months from the original filing. 54 of the 54 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • NameTHE ZONE
  • TypeResidential / Group Housing
  • Location
    • JUHU AZAD NAGAR CHS LTD
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006553
  • ReraGenie IDRG-MH-24511

Builder

  • NameMS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION
  • Entity typeOthers
  • Named personsMS RELLIANCE CONSTRUCTION COMPANY, MR MOHD SALIM Y LASHKARIA, PRAKASH SURVE
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJan 2021Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Aug 2017
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 31 Jan 2021)
  • Buildings1 building record
  • Documents filed78 files

Current status

100%54 of 54 units booked
77.0%Work done, per cost certificate

Figures as on 25 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AMANN SOLITAIRE B WINGNA11005454

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 85%.

AMANN SOLITAIRE B WING: 69% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%

Progress on shared amenities15

As on 25 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes75%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes60%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed158

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots158
Closed/Covered158

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,248 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Jul 2025

Approvals and building plan

Sanctioning authoritySRA
Permissible FSI5101.0
Proposed, not sanctioned520 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchA-2, Model Co-operative Housing Society, Gazal, Gulmohar Road, Jvpd Scheme, Juhu Vile Parle, Mumbai
Estimated costRs 41.59 cr
Cost incurredRs 32.04 cr
Work done77.05%
BuildingWingEstimatedIncurred
AMANN SOLITAIRE B WINGNARs 41.59 crRs 32.04 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMS SHANTANOO RANE AND ASSOCIATES
Engineersura & associates
EngineerKRISHNA GOEL
Chartered Accountantsameer shah
Chartered AccountantDHANASHREE SALUNKHE
Chartered Accountantsiddharth gupta
PartnerRole in project
MS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008759Jan 2021 → Jan 2022

Reason as filed by the promoterDUE TO NON AVAILABILITY OF FURTHER CC AND COVID-19 PANDEMIC THE PROJECT WAS NOT ABLE TO BE COMPLETED ON ABOVE MENTIONED DATE.

EXT51800011587Jan 2021 → Jun 2025

Reason as filed by the promoterDUE TO NON AVAILABILITY OF FURTHER CC AND COVID-19 PANDEMIC THE PROJECT WAS NOT ABLE TO BE COMPLETED PLEASE GRANT FURTHER EXTENSION TILL 30/06/2025

EA14082502376Jan 2021 → Jun 2026

Reason as filed by the promoterThis letter is to formally inform Maharashtra Real Estate Regulatory Authority about the delay in the completion of our registered project, "The Zone." located in Chanadavarker road Borivali West, Mumbai 400092 The project with RERA Registration No. PS1800006553, had an original completion date of June 2025. The COVID-19 pandemic led to significant disruptions in the supply chain, severe labor shortages due to lockdowns, and a complete halt in construction activities for an extended period. These events were entirely beyond our control and created a domino effect of delays Furthermore, the pro

EA25052621088Jan 2021 → Dec 2026

Reason as filed by the promoterThis letter is to formally inform Maharashtra Real Estate Regulatory Authority about the delay in the completion of our registered project, "The Zone," located in Chanadavarker road, Borivali West, Mumbai 400092. The project, with RERA Registration No. P51800006553, had an original completion date of 30 June 2026, The COVID-19 pandemic led to significant disruptions in the supply chain, severe labor shortages due to lockdowns, and a complete halt in construction activities for an extended period. These events were entirely beyond our control and created a domino effect of delays. Furthermore,

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000303673Omega Realtech LimitedAmann Raj Housing & Development Corporation14/12/2022
CC006000000333861Sangita Bharat Thakkar and Sahil Bharat ThakkarM/s Amann Raj Housing and Development Corporation03/01/2023
CC006000000333865Mr Rajan Thakkar and Mr. Bharat ThakkarM/s Amann Raj Housing and Development Corporation03/01/2023
CC006000000333866Mr Bharat Thakkar and Sangita ThakkarM/s Amann Raj Housing and Development Corporation03/01/2023
CC006000000333867Bharat Thakkar and Sangita ThakkarM/s Amann Raj Housing and Development Corporation03/01/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: form 2A 25-26.pdf25 Jul 2026
Withdrawal Update Form 1File: form 1 april to june 2026.pdf20 Jul 2026
Withdrawal Update Form 2File: form 2 april to june 2026.pdf20 Jul 2026
Withdrawal Update Form 3File: form 3 april to june 2026.pdf20 Jul 2026
Withdrawal Update Form 1File: form 1 architect certificate jan to march 2026.pdf20 May 2026
Withdrawal Update Form 2File: form 2 engineer certificate jan to march 2026.pdf20 May 2026
Withdrawal Update Form 3File: form 3 Ca certificate jan to march 2026.pdf20 May 2026
Withdrawal Update Form 1File: form 1 Architect certificate oct to dec.pdf22 Jan 2026
Withdrawal Update Form 2File: form 2 ENGINEER certificate oct to dec.pdf22 Jan 2026
Withdrawal Update Form 3File: form 3 CA certificate oct to dec.pdf22 Jan 2026
Withdrawal Update Form 1File: form 1 architect with sign.pdf13 Nov 2025
Withdrawal Update Form 2File: form 2 engineer with sign.pdf13 Nov 2025
Withdrawal Update Form 3File: form 3 with sign.pdf13 Nov 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 sep 17.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 sep 18.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 sep 19.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 sep 20.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 sep 21.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 sep 22.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 dec 22.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 june 23.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 sep 23.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 dec 23.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 march 24.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 june 24.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 sep 24.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 march 25.pdf2 May 2025
Declaration in FORM BFile: form B RERA Borivali.pdf1 Feb 2024
Disclosure of sold/ booked inventoryFile: INVENTORY DISCLOSURE.pdf17 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 Archetect.pdf10 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 Engineer.pdf10 Jan 2024
Certificates of CA (Form 3)File: form 3.pdf9 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 19-20.pdf9 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 20-21.pdf9 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 21-22.pdf9 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 22-23.pdf9 Jan 2024
Layout approvalFile: Plans _1-2.pdf8 Jan 2024
Layout approvalFile: Plans _3-4.pdf8 Jan 2024
Layout approvalFile: Plans _5-6.pdf8 Jan 2024
Layout approvalFile: Plans _7-8.pdf8 Jan 2024
Layout approvalFile: Plans _9-end.pdf8 Jan 2024
Copy of Layout Approval (in case of layout)File: Plans _1-2.pdf8 Jan 2024
Copy of Layout Approval (in case of layout)File: Plans _3-4.pdf8 Jan 2024
Copy of Layout Approval (in case of layout)File: Plans _5-6.pdf8 Jan 2024
Copy of Layout Approval (in case of layout)File: Plans _7-8.pdf8 Jan 2024
Copy of Layout Approval (in case of layout)File: Plans _9-end.pdf8 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: amann raj housing 2020.pdf19 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: amann raj housing 2021.pdf19 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: amann raj housing 2022.pdf19 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: amann raj housing 2023.pdf19 Dec 2023
Declaration about Commencement CertificateFile: CC Declaration.pdf24 May 2023
CERSAI detailsFile: Cerai Declaration.pdf24 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: parag shah (2).pdf28 Dec 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 - RERA (Borivali - 17-18) -.pdf16 Dec 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5.pdf16 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: CC 01.pdf21 Feb 2020
Commencement Certificates / NA Order for plotted developmentFile: CC 02.pdf21 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: borivali.pdf19 Apr 2019
PAN CardFile: PAN CARD.pdf30 Jul 2017
Details of encumbrancesFile: 07 - BORIVALI DECLARATION FORM.pdf30 Jul 2017
Declaration in FORM BFile: 06 - BORIVALI FORM B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRL ARCHITECT FROM 1.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 04 - BORIVALI ENGINEERS CERTIFICATE.pdf30 Jul 2017
Certificates of CA (Form 3)File: 05 - BORIVALI CHARTERED CERTIFICATE.pdf30 Jul 2017
Certificates of CA (Form 3)File: 20170730141038.pdf30 Jul 2017
Proforma of Allotment letterFile: AGREEMENT FOR SALE Borivali Final.pdf30 Jul 2017
Layout approvalFile: PLAN -1.pdf29 Jul 2017
Layout approvalFile: PLAN - 2.pdf29 Jul 2017
Layout approvalFile: Approved.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: PLAN -1.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: PLAN - 2.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Approved.pdf29 Jul 2017
Building plan approvalFile: I O D Copy.pdf27 Jul 2017
Copy of the legal title reportFile: Title certificatee.pdf27 Jul 2017
Building Plan Approval (IOD)File: I O D Copy.pdf27 Jul 2017
OtherFile: MAR15 ITR.pdf27 Jul 2017
OtherFile: MAR 16 ITR.pdf27 Jul 2017
OtherFile: MAR 14 ITR.pdf27 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
THE ZONE MALL AND AMANN SOLITARE A WINGVILLAGE BORIVALI AMAN ADARSH NAGAR CHANDAVARKAR ROAD298CompletedDec 2015Late, Jul 2017

How this compares with Mumbai Suburban

100%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 71 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE ZONE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmTHE ZONECompleted 166Lapsed / revoked 97Other 222Dot size: filed unitsN

Filed coordinates, straight-line distance. 485 registered projects within 2 km.

Builder: MS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION

MS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION has 1 registration on MahaRERA, including THE ZONE. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if THE ZONE is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE ZONE?

The registered promoter entity is MS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE ZONE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against THE ZONE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for THE ZONE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE ZONE?

The professionals named in the filing: Architect: MS SHANTANOO RANE AND ASSOCIATES; Engineer: sura & associates; Engineer: KRISHNA GOEL; Chartered Accountant: sameer shah; Chartered Accountant: DHANASHREE SALUNKHE; Chartered Accountant: siddharth gupta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE ZONE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE ZONE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE ZONE to a free account