Home / Browse projects / Mumbai Suburban, Maharashtra / THE VIBE

Registered No litigation declared Others project

THE VIBE

By SAHAKAR BUILDERS & DEVELOPERS

RG-MH-18760 · RERA P51800077570 · Last updated on MahaRERA portal: 18 May 2026

Source: official MahaRERA filing

Red flags

  • Rs 50.00 crore secured on the land, in favour of GODREJ FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2028Possession promisedno revision filed
8 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 40%
137 of 174Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 110 documents Report an error

THE VIBE is a Others project by SAHAKAR BUILDERS & DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800077570 on 11 Oct 2024. Possession is promised by 30 Jun 2028. 37 of the 174 units on this registration are recorded sold or booked, and 8 of 44 construction stages are filed complete.

At a glance

Project

  • NameTHE VIBE
  • TypeOthers
  • Location
    • BORASPADA ROAD
    • KANDIVALI
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • RERA no.P51800077570
  • ReraGenie IDRG-MH-18760

Builder

  • NameSAHAKAR BUILDERS & DEVELOPERS
  • Entity typePartnership
  • GSTIN27ACJFS1180N1ZN
  • PartnersNIHIR BHOGILAL THAKKAR, SARJU BHOGILAL THAKKAR, KARAN SARJU THAKKAR
  • Other registrations5 more →
  • Past their filed date1
  • Declared earlier projects4 →

Key dates

this monthRegisteredOct 2024PromisedJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Oct 2024
  • Promised completion30 Jun 2028
  • Revised completionNone
  • Buildings4 building records
  • Documents filed110 files

Current status

21%37 of 174 units booked
23.0%Work done, per cost certificate

Figures as on 18 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA2120583290
Wing BNA212029029
Wing CNA141330030
Wing DNA181725025

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 18 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 40%.

WING A26%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure38%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B26%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure38%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C26%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure38%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing D26%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure38%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed261

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots261
Closed/Covered261
BuildingClosed/CoveredTotal
WING A6565
Wing B6565
Wing C6565
Wing D6666

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,275 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofGODREJ FINANCE LIMITED
Secured amountRs 50.00 crore
CERSAI search filedYes
Declared on21 Aug 2025
LandownerVillageDistrict
OM PUSHPANJALI CO-OPERATIVE HOUSING SOCIETY LIMITEKandivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI13695.38
Proposed, not sanctioned11,548 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchP T OFFICIALS CHS LTD BHUVNESHWARI RAMNAGAR SAIBABABAGAR BORIVALI WEST MUMBAI 400092
Estimated costRs 101.41 cr
Cost incurredRs 23.35 cr
Work done23.02%
BuildingWingEstimatedIncurred
WING ANARs 24.08 crRs 5.76 cr
Wing BNARs 24.08 crRs 5.76 cr
Wing CNARs 24.08 crRs 5.76 cr
Wing DNARs 24.08 crRs 5.76 cr
-NARs 5.07 crRs 29.57 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANISH SHAH
EngineerFRAMES
Chartered AccountantNEHALI & CO
PartnerRole in project
SAHAKAR BUILDERS & DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed110

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate Vibe.PDF18 May 2026
Withdrawal Update Form 1File: Architect Certificate Sign Vibe.PDF18 May 2026
Withdrawal Update Form 2File: Engineer Certificate Vibe.PDF18 May 2026
Withdrawal Update Form 2File: Engineer Certificate Sign Vibe.PDF18 May 2026
Withdrawal Update Form 3File: Signed Copy - The Vibe CA Certificate 31-12-25.PDF18 May 2026
Withdrawal Update Form 3File: CA Certificate - The Vibe Mar-26.PDF18 May 2026
Withdrawal Update Form 1File: Architect Certificate Vibe.PDF16 May 2026
Withdrawal Update Form 2File: Engineer Certificate Vibe.PDF16 May 2026
Withdrawal Update Form 3File: CA Certificate Vibe.PDF16 May 2026
Withdrawal Update Form 1File: Architect Certificate Vibe.PDF12 May 2026
Withdrawal Update Form 2File: Engineer Certificate Sign Vibe.PDF12 May 2026
Withdrawal Update Form 3File: form 3.pdf12 May 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Singed Architect Certificate The Vibe.PDF14 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Singed Engineer Certificate The Vibe.PDF14 Apr 2025
Layout approvalFile: Amended Approved Drawing_1-4.pdf26 Mar 2025
Layout approvalFile: Amended Approved Drawing_5-8.pdf26 Mar 2025
Layout approvalFile: Amended Approved Drawing_9-12.pdf26 Mar 2025
Layout approvalFile: Amended Approved Drawing_13-16.pdf26 Mar 2025
Layout approvalFile: Amended Approved Drawing_17-end.pdf26 Mar 2025
Building plan approvalFile: Amended Plan Approval Letter.pdf26 Mar 2025
Copy of Layout Approval (in case of layout)File: Amended Approved Drawing_1-4.pdf26 Mar 2025
Copy of Layout Approval (in case of layout)File: Amended Approved Drawing_5-8.pdf26 Mar 2025
Copy of Layout Approval (in case of layout)File: Amended Approved Drawing_9-12.pdf26 Mar 2025
Copy of Layout Approval (in case of layout)File: Amended Approved Drawing_13-16.pdf26 Mar 2025
Copy of Layout Approval (in case of layout)File: Amended Approved Drawing_17-end.pdf26 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Amended Plan Approval Letter.pdf26 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventary.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.PDF9 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.PDF9 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf30 Dec 2024
Proforma of Agreement for saleFile: AGREEMENT FOR SALE - RESIDENTIAL - THE VIBE - FINAL.pdf30 Dec 2024
Proforma of Agreement for saleFile: AGREEMENT FOR SALE - COMMERCIAL - THE VIBE - FINAL.pdf30 Dec 2024
Other - TechnicalFile: ANNEURE A.pdf7 May 2024
Other - TechnicalFile: ANNEURE A.pdf7 May 2024
Other - TechnicalFile: ANNEURE A.pdf7 May 2024
Layout approvalFile: APPROVED IOD PLANS_14-end.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_10-13.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_6-9.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_1.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_14-end.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_10-13.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_6-9.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_1.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_14-end.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_10-13.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_6-9.pdf4 May 2024
Layout approvalFile: APPROVED IOD PLANS_1.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_1.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_6-9.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_10-13.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_14-end.pdf4 May 2024
Proforma of Allotment letterFile: Sahakar - ALLOTMENT LETTER FINAL (2).pdf4 May 2024
Declaration in FORM BFile: Form B (19).PDF4 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf4 May 2024
Commencement Certificates / NA Order for plotted developmentFile: First CC.pdf4 May 2024
Declaration about Commencement CertificateFile: CC Declaration.PDF4 May 2024
Deviation Report with respect to Allotment letterFile: Deviation Report - The Vibe.PDF4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_1.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_6-9.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_10-13.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_14-end.pdf4 May 2024
Proforma of Allotment letterFile: Sahakar - ALLOTMENT LETTER FINAL (2).pdf4 May 2024
Declaration in FORM BFile: Form B (19).PDF4 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf4 May 2024
Commencement Certificates / NA Order for plotted developmentFile: First CC.pdf4 May 2024
Declaration about Commencement CertificateFile: CC Declaration.PDF4 May 2024
Deviation Report with respect to Allotment letterFile: Deviation Report - The Vibe.PDF4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_1.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_6-9.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_10-13.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: APPROVED IOD PLANS_14-end.pdf4 May 2024
Proforma of Allotment letterFile: Sahakar - ALLOTMENT LETTER FINAL (2).pdf4 May 2024
Declaration in FORM BFile: Form B (19).PDF4 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf4 May 2024
Commencement Certificates / NA Order for plotted developmentFile: First CC.pdf4 May 2024
Declaration about Commencement CertificateFile: CC Declaration.PDF4 May 2024
Deviation Report with respect to Allotment letterFile: Deviation Report - The Vibe.PDF4 May 2024
Details of encumbrances concerned to FinanceFile: NO ENCUNBRANCE.pdf30 Apr 2024
CERSAI detailsFile: CERSAI.pdf30 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow30 Apr 2024

How this compares with Mumbai Suburban

21%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE VIBE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANDIVALI6,700+ in Mumbai Suburban

Builder: SAHAKAR BUILDERS & DEVELOPERS

SAHAKAR BUILDERS & DEVELOPERS has 6 registrations on MahaRERA, including Sahakar Revanta and VOGUE77. Its filings disclose 4 earlier MahaRERA projects, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if THE VIBE is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE VIBE?

The registered promoter entity is SAHAKAR BUILDERS & DEVELOPERS, a partnership as per the filing. Its GSTIN 27ACJFS1180N1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE VIBE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for THE VIBE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE VIBE?

The professionals named in the filing: Architect: MANISH SHAH; Engineer: FRAMES; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE VIBE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE VIBE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE VIBE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.