Completed No litigation declared Residential / Group Housing project

The Trees Residential Phase 2

By Godrej Properties Limited

RG-MH-02436 · RERA P51800000161 · Last updated on MahaRERA portal: 3 Oct 2020

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
50 of 55Construction stages doneacross 5 buildings; furthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

The Trees Residential Phase 2 is a Residential / Group Housing project by Godrej Properties Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000161 on 5 Jul 2017. The registration is recorded completed; possession was promised by 30 Jun 2022. 1 complaint is on record with the regulator.

At a glance

Project

  • NameThe Trees Residential Phase 2
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400079
  • Pincode400079
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000161
  • ReraGenie IDRG-MH-02436

Builder

  • NameGodrej Properties Limited
  • Entity typeCompany
  • Other registrations27 more →
  • Completed5 of 28
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects35 →

Key dates

this monthRegisteredJul 2017PromisedJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Jul 2017
  • Promised completion30 Jun 2022
  • Revised completionNone
  • Buildings5 building records
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KNA210000
LNA210000
MNA150000
NNA210000
ONA210000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 3 Oct 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

50 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 0%.

K91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
L91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
M91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
N91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
O91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Oct 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed505

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots505
Closed/Covered411
Open Space94
BuildingClosed/CoveredOpen SpaceTotal
K701686
L611475
M721688
N10825133
O10023123

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,815 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI23548.0
Proposed, not sanctioned23,548 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchManekji Wadia Bldg Ground Floor Nanik Motwani Marg Fort Mumbai 400001

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKapadia Associates Design LLP
ArchitectSpacage Consultants
EngineerSterling Engineering Consultancy Services Pvt Ltd
PartnerRole in project
Godrej Properties Limited-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000141048SANDEEP VICHAREGODREJ PROPERTIES LTD08/12/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Jun 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Jun 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jun 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Oct 2019

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Phase 2 - 2018-19.pdf3 Oct 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5- Phase 2- Mar'20.pdf3 Oct 2020
Proforma of Allotment letterFile: AFS - OC - Phase 2.pdf28 Apr 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Shops in Phase I, II and Club House.pdf22 Oct 2019
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf22 Oct 2019
Certificates of CA (Form 5)File: FY 18-19 Trees- Phase 2.pdf30 Sep 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OCCUPANCY CERTIFICATE.pdf30 Sep 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: PHASE 2 CERTIFICATE.pdf16 Jul 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: PHASE 2 CERTIFICATE.pdf13 Feb 2019
Certificates of CA (Form 5)File: GPL_TREES_2.pdf30 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: Resi Full CC - GPL.pdf3 Sep 2018
Proforma of Allotment letterFile: PHASE 2 - AFS.pdf15 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Re- AC - PHASE 2.pdf26 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SE -PHASE 2.pdf26 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SC -PHASE 2.pdf26 Apr 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: STATUS -SOCIETY FORMATION - PHASE 2-26032018.pdf30 Mar 2018
PAN CardFile: GPL pancard.pdf23 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: Further CC - 2 2 2018.pdf23 Feb 2018
OtherFile: PRC - GPL JAN 2018.pdf1 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 2.pdf31 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase 2.pdf31 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SC - PHASE 2.pdf11 Dec 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 2.pdf7 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE - PHASE 2.pdf5 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE - PHASE 2.pdf5 Oct 2017
Declaration in FORM BFile: PHASE 2.pdf29 Jun 2017
Proforma of Allotment letterFile: PROFORMA - AL AFS - Phase 1 and 2 29062017 RANJIT.pdf29 Jun 2017
Certificates of CA (Form 3)File: PHASE 2 FORM 3 CA CERTIFICATE.pdf27 Jun 2017
Layout approvalFile: Amended Layout Letter with plan.pdf13 Jun 2017
Building plan approvalFile: IOD letter 01042017.pdf13 Jun 2017
Copy of Layout Approval (in case of layout)File: Amended Layout Letter with plan.pdf13 Jun 2017
Building Plan Approval (IOD)File: IOD letter 01042017.pdf13 Jun 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 2.pdf13 Jun 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase 2.pdf13 Jun 2017
PAN CardFile: PAN - GVPIL.pdf9 Jun 2017
Copy of the legal title reportFile: Land Title Report -25052016.pdf9 Jun 2017
Details of encumbrancesFile: Non Encumbrance Certificate.pdf9 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Full CC and Plinth Origins.pdf9 Jun 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
GODREJ ONEGodrej One Pirojshanagar Off Eastern Express Highway Vikhroli East Mumbai 400079 Maharashtra India39CompletedDec 2013Late, Aug 2014

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Trees Residential Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmThe Trees Residential PhCompleted 26Lapsed / revoked 15Other 58Dot size: filed unitsN

Filed coordinates, straight-line distance. 99 registered projects within 2 km.

Builder: Godrej Properties Limited

Godrej Properties Limited has 28 registrations on MahaRERA, including The Trees, Residential Phase 1 and Godrej Anandam. Its filings disclose 35 earlier MahaRERA projects: declares 28 of 30 past projects completed on time. Litigation is declared on 7 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if The Trees Residential Phase 2 is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Trees Residential Phase 2?

The registered promoter entity is Godrej Properties Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Trees Residential Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against The Trees Residential Phase 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for The Trees Residential Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Trees Residential Phase 2?

The professionals named in the filing: Architect: Kapadia Associates Design LLP; Architect: Spacage Consultants; Engineer: Sterling Engineering Consultancy Services Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Trees Residential Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Trees Residential Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Trees Residential Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.