ReraGenieLog inGet a buyer report

Home / Browse projects / Kolhapur, Maharashtra / THE SKYLARK

Registration lapsed No litigation declared Others project

THE SKYLARK

By Sanjay Pandurang Gaikwad

RG-MH-70132 · RERA P53000052120 · Last updated on MahaRERA portal: 19 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
8 of 11Construction stages donefurthest along: Basement (if any), 0%
9 of 11Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

THE SKYLARK is a Others project by Sanjay Pandurang Gaikwad in Kolhapur, Maharashtra, registered with MahaRERA as P53000052120 on 24 Jul 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 2 of the 11 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameTHE SKYLARK
  • TypeOthers
  • Location
    • Laxmanrao Mohite Colony
    • Kadamwadi Road
    • 511 E Ward New Tarabai Park
    • Kolhapur (M Corp.)
    • Karvir
    • Kolhapur
    • 416003
  • Pincode416003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53000052120
  • ReraGenie IDRG-MH-70132

Builder

  • NameSanjay Pandurang Gaikwad
  • Entity typeIndividual

Key dates

10 months past promisethis monthRegisteredJul 2023First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Jul 2023
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed88 files

Current status

18%2 of 11 units booked
99.1%Work done, per cost certificate

Figures as on 19 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The SkylarkNA558311

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

The Skylark: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 19 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes15%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Open Space20

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area476 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityKolhapur Municipal Corporation
Permissible FSI841.88
Proposed, not sanctioned842 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVasant Plaza Rajarampuri Kolhapuri
Estimated costRs 1.72 cr
Cost incurredRs 1.70 cr
Work done99.1%
BuildingWingEstimatedIncurred
The SkylarkNARs 1.60 crRs 1.59 cr
-NARs 11.67 lakhRs 11.67 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanrachna Consultants
EngineerPRATIK RAJARAM PATIL Rajaram Patil
Chartered AccountantJ P Chougule and Companny through Partner CA Amit Madanrao Shinde
PartnerRole in project
Sanjay Pandurang Gaikwad-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53000027386Dec 2024 → Dec 2025

Reason as filed by the promoterMy construction of real estate project is 95% complete. The remaining work of the project I required more 2 to 3 months. After that I can applied for completion certificate to Kolhapur Municipal Corporation. hence I applied for 1 year extension to MahaRERA Authority. I would greatly appreciate and request MAHARERA authority to grant me further extension of One year for completing the project and thereby submitting the Completion Certificate along with Form 4 as soon as the Kolhapur Municipal Corporation issues us the Completion certificate and Occupancy certificate for our project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_11zon (1).pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1_11zon (2).pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2_11zon (1).pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2_11zon (2).pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3_11zon (2).pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3_11zon (3).pdf19 Feb 2026
Form 1File: Form 1.pdf5 Aug 2025
Form 2File: Form 2.pdf5 Aug 2025
Form 3File: Form 3.pdf5 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory.pdf5 Aug 2025
Form 1File: Form 1.pdf10 Jun 2025
Form 2File: Form 2.pdf10 Jun 2025
Form 3File: Form 3.pdf10 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory.pdf10 Jun 2025
Self-declaration of Quarterly ProgressFile: Doc1.pdf10 Jun 2025
Declaration in FORM BFile: Form B.pdf30 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: MahaRERA Form 5 - CA Audit Report FY 2023-2024.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 CA Certificate on Project Cost and Fund withdrawal (Form 3).pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 Engineer’s Certificate on Cost Incurred on Project (Form 2) .pdf23 Jan 2025
Other - LegalFile: Agreement To Sell - Index-2_Hariprasad Dattatray Kulkarni_Flat No 201.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: 7 Disclosure of sold booked inventory.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf27 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 CA Certificate on Project Cost and Fund withdrawal (Form 3).pdf27 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 Engineer’s Certificate on Cost Incurred on Project (Form 2) .pdf27 Oct 2024
Disclosure of sold/ booked inventoryFile: 6 Disclosure of sold booked inventory.pdf27 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: 5 Disclosure of sold booked inventory.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 CA Certificate on Project Cost and Fund withdrawal (Form 3).pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1_Architects_Certificate (1).pdf30 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_Structural Engineer’s Certificate (1).pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory (1).pdf30 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_Chartered Accountant's Certificate (1).pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1_Architects_Certificate.pdf23 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf23 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf23 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3.pdf23 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf20 Oct 2023
Building plan approvalFile: Commencement Certificate -SAnjay Gaikwad.pdf22 Jul 2023
Building plan approvalFile: Old Plan-Sanjay Gaikwad.pdf22 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: Commencement Certificate -SAnjay Gaikwad.pdf22 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: Old Plan-Sanjay Gaikwad.pdf22 Jul 2023
Deviation Report with respect to model copy of AgreementFile: No DEviation in Agreement -Gaikwad_0001.pdf17 Jul 2023
Other - TechnicalFile: No DEviation in Agreement -Gaikwad_0001.pdf10 Jul 2023
Other - TechnicalFile: No DEviation in Allotment -Gaikwad.pdf10 Jul 2023
Building plan approvalFile: Letter from KMC-Tushar Gaikwad.pdf8 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: Letter from KMC-Tushar Gaikwad.pdf8 Jul 2023
Details of encumbrances concerned to FinanceFile: Finance -Gaikwad05232023.pdf23 May 2023
Details of encumbrances concerned to LegalFile: Finance -Gaikwad05232023.pdf23 May 2023
CERSAI detailsFile: Declaration about cersai Report05232023.pdf23 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A-Gaikwad05232023.pdf23 May 2023
Declaration about Commencement CertificateFile: Format D -New Sanjay Gaikwad04272023.pdf27 Apr 2023
Proforma of Agreement for saleFile: fINAL Agreement upload.pdf27 Apr 2023
Other - LegalFile: Index Before Registration.pdf27 Apr 2023
Other - TechnicalFile: Highlighted Corporation Drawing_The Skylark_Updated_16032023 (1).pdf12 Apr 2023
Other - TechnicalFile: Self Declaration04122023.pdf12 Apr 2023
Layout approvalFile: Highlighted Layout Plan -Gaikwad_11zon.pdf28 Feb 2023
Copy of Layout Approval (in case of layout)File: Highlighted Layout Plan -Gaikwad_11zon.pdf28 Feb 2023
Building plan approvalFile: Plan_11zon (5).pdf27 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan_11zon (5).pdf27 Feb 2023
CERSAI detailsFile: CERSAI_Search_Report_Gaikwad.pdf17 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Final Annexture A -Gaikwad.pdf17 Feb 2023
Copy of the legal title reportFile: Legal Title Report02102023.pdf10 Feb 2023
Declaration about Commencement CertificateFile: DEclaration about sold unit-Gaikwad02092023.pdf10 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DEclaration about sold unit-Gaikwad02092023.pdf10 Feb 2023
Layout approvalFile: layout.pdf9 Feb 2023
Building plan approvalFile: Plan_11zon (5).pdf9 Feb 2023
PAN CardFile: PAN_Sanjay Pandurang Gaikwad.pdf9 Feb 2023
Details of encumbrances concerned to FinanceFile: Legal-Gaikwad02092023.pdf9 Feb 2023
Details of encumbrances concerned to LegalFile: Legal-Gaikwad02092023.pdf9 Feb 2023
Copy of Layout Approval (in case of layout)File: layout.pdf9 Feb 2023

How this compares with Kolhapur

18%of this project is bookeddistrict median 19%
17%of Kolhapur projects moved their completion datethis one moved by 12 months
25%of Kolhapur registrations have lapsed or been cancelledthis one is among them

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep THE SKYLARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near 511 E Ward New Tarabai Park880+ in Kolhapur

2 kmTHE SKYLARKCompleted 38Lapsed / revoked 17Other 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 101 registered projects within 2 km.

Builder: Sanjay Pandurang Gaikwad

Sanjay Pandurang Gaikwad has 1 registration on MahaRERA, including THE SKYLARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What does it mean that THE SKYLARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if THE SKYLARK is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE SKYLARK?

The registered promoter entity is Sanjay Pandurang Gaikwad, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE SKYLARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for THE SKYLARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE SKYLARK?

The professionals named in the filing: Architect: Sanrachna Consultants; Engineer: PRATIK RAJARAM PATIL Rajaram Patil; Chartered Accountant: J P Chougule and Companny through Partner CA Amit Madanrao Shinde. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE SKYLARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE SKYLARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE SKYLARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.