Home / Browse projects / Pune, Maharashtra / THE SAGA
THE SAGA
RG-MH-22617 · RERA P52100035028 · Last updated on MahaRERA portal: 27 Nov 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- Completion date moved by 30 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
THE SAGA is a Residential / Group Housing project by NEST SASWAD REALTY LLP in Pune, Maharashtra, registered with MahaRERA as P52100035028 on 29 Apr 2022. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 30 months from the original filing. 13 of the 13 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.
At a glance
Project
- NameTHE SAGA
- TypeResidential / Group Housing
- Location
- BHEL CHOWK
- PRADHIKARAN NIGDI
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 411044
- Pincode411044
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100035028
- ReraGenie IDRG-MH-22617
Builder
- NameNEST SASWAD REALTY LLP
- Entity typePartnership
- Other registrations1 more →
- Past their filed date1
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Apr 2022
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 24 Mar 2024)
- Buildings1 building record
- Documents filed55 files
Current status
Figures as on 27 Nov 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| THE SAGA | NA | 15 | 13 | 13 | 0 | 13 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 80%.
THE SAGA: 30% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 47% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 15% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed40
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SUDHASH ZUMBERLAL BEDMUTHA | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANDEEP DANGE |
| Engineer | PROTECH CONSULTANTS |
| Engineer | Gensys Technologies Pvt Ltd |
| Engineer | Prakash Ajinath Jawale |
| Engineer | Laxmikant Bhagwantrao Jadhav |
| Chartered Accountant | SHAH KHANDELWAL JAIN & ASSOCIATES |
| Chartered Accountant | Jain Doshi and Associates |
| Chartered Accountant | Akshay Jain & Company |
| Partner | Role in project |
|---|---|
| NEST SASWAD REALTY LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to technical and financial issues, there is a delay in completing the project and obtaining the completion certificate in the given time. Hence we request to grant us an extension.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30/0/to complete the project and fulfil all regulatory requirements
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Apr 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Apr 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed55
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 September 2025 Signed.pdf | 27 Nov 2025 |
| Form 2File: Form 2 Sept 2025.pdf | 27 Nov 2025 |
| Form 3File: Form 3 Sep 2025 Signed.pdf | 27 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Cicular 29.pdf | 27 Nov 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Saga Mar 25.pdf | 17 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Saga Mar 25 (1).pdf | 17 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Saga Dec 24 C.pdf | 15 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Saga Dec 24.pdf | 15 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Jun 24.pdf | 18 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sep 24.pdf | 18 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Cert Jun 24.pdf | 18 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 24.pdf | 18 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert Jun 24.pdf | 18 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep 24.pdf | 18 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Saga Mar 24.pdf | 18 Dec 2024 |
| Declaration in FORM BFile: Form B.pdf | 17 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Ar Saga Mar 24.pdf | 22 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Er Saga Mar 24.pdf | 22 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Saga Mar 24.pdf | 22 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory.pdf | 28 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 22-23 Quality Assurance Saga.pdf | 23 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Ar.pdf | 14 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng.pdf | 14 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA.pdf | 14 Feb 2024 |
| Details of encumbrancesFile: Encumbraces for Saga.pdf | 18 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 23 Saga.pdf | 13 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sep 23 Saga.pdf | 13 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 23 Saga.pdf | 13 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep 23 Saga.pdf | 13 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 23 Saga.pdf | 13 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 23 Saga.pdf | 13 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: The Saga RERA Audit Report_FY 2022-23 Compress.pdf | 4 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer’s Certificate_31-03-2023 The SAGA-.pdf | 7 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 The Saga Signed.pdf | 7 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate.pdf | 17 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate.pdf | 17 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cer Sep 22.pdf | 17 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cer Dec 22.pdf | 17 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cer Sep 22.pdf | 17 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cer Dec 22.pdf | 17 Mar 2023 |
| Details of encumbrancesFile: Encumbraces for Saga.pdf | 4 Jan 2023 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 28 Apr 2022 |
| Proforma of Allotment letterFile: DRAFT AGREEMENT.pdf | 28 Apr 2022 |
| Details of encumbrancesFile: Encumbrances for Saga.pdf | 18 Apr 2022 |
| Building plan approvalFile: PLAN.pdf | 16 Apr 2022 |
| Layout approvalFile: PLAN (1).pdf | 16 Apr 2022 |
| Copy of the legal title reportFile: Search Report in RERA.pdf | 16 Apr 2022 |
| Copy of Layout Approval (in case of layout)File: PLAN (1).pdf | 16 Apr 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN.pdf | 16 Apr 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT CC.pdf | 5 Apr 2022 |
| Declaration in FORM BFile: Declaration in FORM B.pdf | 5 Apr 2022 |
| CERSAI detailsFile: CERSAI - THE SAGA.pdf | 5 Apr 2022 |
| PAN CardFile: Nest PAN Card.pdf | 31 Mar 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 31 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SAGA CA Certificate_compressed_compressed-compressed.pdf | 24 Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 55 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep THE SAGA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PRADHIKARAN NIGDI13,700+ in Pune
Filed coordinates, straight-line distance. 80 registered projects within 2 km.
VISION VANESSA
P4 GROUP
VISION PLUS
URBAN SPACESS VERACO REALTORS
ELEGANT RESIDENCY PHASE II
ARIHANT VASTUSHILP PROPCON PRIVATE LIMITED
CITY ONE PANACHE
SHREE SAI KEYSTONE
Shuban Enclave
Sahyadri Devcon
NITAARA TOWER
M/s ABC & Mittal Realty
Builder: NEST SASWAD REALTY LLP
NEST SASWAD REALTY LLP has 2 registrations on MahaRERA, including AASHIRWAD HOMES and THE SAGA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if THE SAGA is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of THE SAGA?
The registered promoter entity is NEST SASWAD REALTY LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in THE SAGA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for THE SAGA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at THE SAGA?
The professionals named in the filing: Architect: SANDEEP DANGE; Engineer: PROTECH CONSULTANTS; Engineer: Gensys Technologies Pvt Ltd; Engineer: Prakash Ajinath Jawale; Engineer: Laxmikant Bhagwantrao Jadhav; Chartered Accountant: SHAH KHANDELWAL JAIN & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in THE SAGA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.