ReraGenieLog inGet a buyer report

Home / Browse projects / Kolhapur, Maharashtra / THE LANDMARK

Registered No litigation declared Others project

THE LANDMARK

By SWARAJYA ASSOCIATES

RG-MH-56757 · RERA P53000055024 · Last updated on MahaRERA portal: 8 Feb 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
6 of 11Construction stages donefurthest along: Staircases, 60%
0Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

THE LANDMARK is a Others project by SWARAJYA ASSOCIATES in Kolhapur, Maharashtra, registered with MahaRERA as P53000055024 on 26 Feb 2024. Possession is promised by 31 Dec 2026.

At a glance

Project

  • NameTHE LANDMARK
  • TypeOthers
  • Location
    • AKHILESH PARK
    • KAGAL
    • Kagal (M Cl)
    • Kolhapur
    • 416216
  • Pincode416216
  • RERA no.P53000055024
  • ReraGenie IDRG-MH-56757

Builder

  • NameSWARAJYA ASSOCIATES
  • Entity typePartnership
  • PartnersAMRITA MARUTI PATIL, ANURADHA MARUTI PATIL

Key dates

this monthRegisteredFeb 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Feb 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
THE LANDMARKNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 60%.

THE LANDMARK: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area504 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
SANJEEVANI SAYAJI PALKARKagal (M Cl)Kolhapur
ANURADHA MARUTI PATILBamaniKolhapur
AMRITA MARUTI PATILBamaniKolhapur

Approvals and building plan

Permissible FSI1065.03
Proposed, not sanctioned1,065 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchS1 GROUND FLOOR VIJAY ARCADE DATTAJIRAO INGALE NAGAR KAGAL 416216

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJINKYA SAYAJI PALKAR
EngineerBHALCHANDRA S PALKAR
Chartered AccountantSPOC AND ASSOCIATES
PartnerRole in project
SWARAJYA ASSOCIATES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf8 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf8 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed (27).pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf22 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf18 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) (11).pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Form 3.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Apr 2024
Other - TechnicalFile: Architect certificate New.pdf21 Feb 2024
Other - TechnicalFile: engineer certificate New.pdf21 Feb 2024
Other - TechnicalFile: Plinth Checking remark.pdf20 Feb 2024
Building plan approvalFile: New Sanction Plan Scan.pdf19 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: New Sanction Plan Scan.pdf19 Jan 2024
Proforma of Agreement for saleFile: Agreement to Sell as per RERA Act - Final.pdf19 Jan 2024
Other - LegalFile: Power of Attorney.pdf19 Jan 2024
Details of encumbrances concerned to FinanceFile: Encumbrances Concerned to Finance.pdf29 Dec 2023
Details of encumbrances concerned to FinanceFile: Encumbrances Concerned to Legal.pdf29 Dec 2023
Details of encumbrances concerned to LegalFile: Encumbrances Concerned to Finance.pdf29 Dec 2023
Details of encumbrances concerned to LegalFile: Encumbrances Concerned to Legal.pdf29 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: Plinth Checking remark.pdf29 Dec 2023
Declaration about Commencement CertificateFile: Declaration about CC.pdf29 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Declaration.pdf29 Dec 2023
Deviation Report with respect to Allotment letterFile: No Deviation - Allotment Letter.pdf29 Dec 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation - Agreement to Sell.pdf29 Dec 2023
Layout approvalFile: Layout Plan_compressed.pdf28 Dec 2023
PAN CardFile: Pan Card.pdf28 Dec 2023
Copy of the legal title reportFile: Legal Title and Search Report.pdf28 Dec 2023
Copy of Layout Approval (in case of layout)File: Layout Plan_compressed.pdf28 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf28 Dec 2023
Declaration in FORM BFile: Form B Declaration - Promoter.pdf28 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf28 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate.pdf28 Dec 2023
CERSAI detailsFile: CERSAI Declaration.pdf28 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf28 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf28 Dec 2023
Proforma of Allotment letterFile: Allottment Letter - New.pdf28 Dec 2023

How this compares with Kolhapur

17%of Kolhapur projects moved their completion datethis one has not
25%of Kolhapur registrations have lapsed or been cancelledthis one is on the register

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep THE LANDMARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KAGAL880+ in Kolhapur

Builder: SWARAJYA ASSOCIATES

SWARAJYA ASSOCIATES has 1 registration on MahaRERA, including THE LANDMARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if THE LANDMARK is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE LANDMARK?

The registered promoter entity is SWARAJYA ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE LANDMARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for THE LANDMARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE LANDMARK?

The professionals named in the filing: Architect: AJINKYA SAYAJI PALKAR; Engineer: BHALCHANDRA S PALKAR; Chartered Accountant: SPOC AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE LANDMARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE LANDMARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE LANDMARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.