Home / Browse projects / Satara, Maharashtra / The green woods

Registered No litigation declared Others project

The green woods

By Vedant Infra

RG-MH-12171 · RERA P52700004436 · Last updated on MahaRERA portal: 19 Jul 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 33 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 33 months from the original
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 80%
0Complaints at MahaRERAon this registration
Jump to the 113 documents Report an error

The green woods is a Others project by Vedant Infra in Satara, Maharashtra, registered with MahaRERA as P52700004436 on 9 Aug 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 33 months from the original filing.

At a glance

Project

  • NameThe green woods
  • TypeOthers
  • Location
    • Godoli (CT)
    • Satara
    • 415001
  • Pincode415001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700004436
  • ReraGenie IDRG-MH-12171

Builder

  • NameVedant Infra
  • Entity typePartnership
  • PartnersChetan Pralhad Sawant, Pratibha pravin jadhav, Shubhangi adhikrao mane
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredAug 2017First promiseMar 2026Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2017
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 30 Mar 2026)
  • Buildings2 building records
  • Documents filed113 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WINGNA70000
A WINGNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

B WING67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
A WING31%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes60%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes10%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3
BuildingClosed/CoveredTotal
B WING22
A WING11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,032 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1327.58
Proposed, not sanctioned1,228 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 27 SHRI GANESH HOUSING SOCIETY SHAUNAGAR GODOLI

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Vedant Infra-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700025510Mar 2026 → Dec 2028

Reason as filed by the promoterDue to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2028 to complete the project

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed113

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 113 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch form Mar 25.pdf19 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Form Jun 25.pdf19 Jul 2025
Certificates of CA (Form 3)File: FORM NO 3 Mar 25.pdf19 Jul 2025
Certificates of CA (Form 3)File: Revised FORM NO 3_June 25.pdf19 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2__Engineers_Certificate Mar 25.pdf19 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2__Engineers_Certificate Jun 25.pdf19 Jul 2025
Form 1File: Arch form Mar 25.pdf19 Jul 2025
Form 2File: Form_2__Engineers_Certificate Mar 25.pdf19 Jul 2025
Form 3File: FORM NO 3 Mar 25.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold invertery Mar 25.pdf19 Jul 2025
Form 1File: Arch Form Jun 25.pdf19 Jul 2025
Form 2File: Form_2__Engineers_Certificate Jun 25.pdf19 Jul 2025
Form 3File: Revised FORM NO 3_June 25.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold unsold invertery Jun 25.pdf19 Jul 2025
Declaration in FORM BFile: Form B.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch_certificate_-_Vedant_infa_Dec 24.pdf29 Jan 2025
Certificates of CA (Form 3)File: Form-3-Vedant_Infra_Dec 24.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vedant_infra_Engineer_certificate_Dec 24.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no -1- Sep 24.pdf21 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no -1- Jun 24.pdf21 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no - 1 Mar 24.pdf21 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no - 1 Mar 23.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form no 3 - Mar 23.pdf21 Jan 2025
Certificates of CA (Form 3)File: form no 3 - Sep 24_compressed.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form no 3 - Jun 24_compressed.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form no - 3 Mar 24.pdf21 Jan 2025
Other - LegalFile: Consent Format C.pdf21 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no 1 MAR 23.pdf19 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no 1 Sep 24.pdf19 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no 1 Jun 24.pdf19 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no 1 Mar 24.pdf19 Dec 2024
Certificates of CA (Form 3)File: Form no 1 Sep 24.pdf19 Dec 2024
Certificates of CA (Form 3)File: Form no 1 Jun 24.pdf19 Dec 2024
Certificates of CA (Form 3)File: Form no 1 Mar 24.pdf19 Dec 2024
Certificates of CA (Form 3)File: Form no 1 MAR 23.pdf19 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2__Engineers_Certificate Sep 24.pdf19 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2__Engineers_Certificate Jun 24.pdf19 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2__Engineers_Certificate Mar 23.pdf19 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2__Engineers_Certificate Mar 24.pdf19 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Mar 23.pdf19 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Mar 24.pdf19 Dec 2024
Other - LegalFile: Consent of Customers.pdf12 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf12 Dec 2024
Declaration about Commencement CertificateFile: Declaration about CC.pdf12 Dec 2024
Other - TechnicalFile: Sold Unsold Inventory.pdf12 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest of Partners.pdf12 Dec 2024
Building plan approvalFile: scan0155.pdf6 Dec 2024
Building plan approvalFile: scan0156_compressed.pdf6 Dec 2024
Building plan approvalFile: scan0157_compressed.pdf6 Dec 2024
Details of encumbrances concerned to FinanceFile: Legal Encumbrance.pdf6 Dec 2024
Details of encumbrancesFile: Financial Encumbarnce.pdf6 Dec 2024
Proforma of Allotment letterFile: Allotment Letter.pdf6 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: Vedant Revised Order.pdf6 Dec 2024
Building Plan Approval (IOD)File: scan0155.pdf6 Dec 2024
Building Plan Approval (IOD)File: scan0156_compressed.pdf6 Dec 2024
Building Plan Approval (IOD)File: scan0157_compressed.pdf6 Dec 2024
CERSAI detailsFile: CERSAI_Search_Report_200330509673_For_Asset_Based_Search_06_12_2024_19_19_44_520.pdf6 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: ANNEX A.pdf6 Dec 2024
Deviation Report with respect to Allotment letterFile: Deviation Declaration.pdf6 Dec 2024
Details of encumbrances concerned to LegalFile: Legal Encumbrance.pdf6 Dec 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Declaration.pdf6 Dec 2024
Proforma of Agreement for saleFile: ATS_Green_woods.pdf6 Dec 2024
Certificates of CA (Form 3)File: FORM NO 3_New_23-24Q4.pdf29 Nov 2024
Certificates of CA (Form 3)File: FORM NO 3_New_23-24Q3_compressed.pdf29 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5_New_23-24.pdf5 Nov 2024
Certificates of CA (Form 3)File: Form 3 Jun 22_compressed.pdf3 Nov 2023
Certificates of CA (Form 3)File: Form 3 Sep 22_compressed.pdf3 Nov 2023
Certificates of CA (Form 3)File: Form 3 Dec 22_compressed.pdf3 Nov 2023
Certificates of CA (Form 3)File: Form 3 Mar 23_compressed.pdf3 Nov 2023
Certificates of CA (Form 3)File: Form 3 Jun 23_compressed.pdf3 Nov 2023
Certificates of CA (Form 3)File: Form 3 Sep 23.pdf3 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf3 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Mar18.pdf9 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Mar19.pdf9 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Mar20.pdf9 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Mar21.pdf9 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Dec21.pdf9 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Mar22.pdf9 Feb 2023
Certificates of CA (Form 3)File: Form 3 17-18.pdf7 Feb 2023
Certificates of CA (Form 3)File: Form 3 18-19.pdf7 Feb 2023

How this compares with Satara

16%of Satara projects moved their completion datethis one moved by 33 months
35%of Satara registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep The green woods on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Godoli (CT)1,100+ in Satara

Builder: Vedant Infra

Vedant Infra has 2 registrations on MahaRERA, including The green woods and VEDANTIKA PRIDE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if The green woods is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The green woods?

The registered promoter entity is Vedant Infra, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The green woods?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for The green woods?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in The green woods?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The green woods. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The green woods to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.