THE GOLDEN HERITAGE
RG-MH-13961 · RERA P49700029921 · Last updated on MahaRERA portal: 27 Apr 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 16 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nandurbar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
THE GOLDEN HERITAGE is a Residential / Group Housing project by THE GOLDEN HERITAGE in Nandurbar, Maharashtra, registered with MahaRERA as P49700029921 on 15 Jul 2021. The registration is recorded completed; possession was promised by 15 Jul 2026. The completion date has moved by 16 months from the original filing. 71 of the 102 units on this registration are recorded sold or booked, and 1130 of 1375 construction stages are filed complete.
At a glance
Project
- NameTHE GOLDEN HERITAGE
- TypeResidential / Group Housing
- Location
- HOL TURFE HAVELI
- NANDURBAR
- Hol T. Haveli
- 425412
- Pincode425412
- MapView location on Google Maps (as filed on RERA)
- RERA no.P49700029921
- ReraGenie IDRG-MH-13961
Builder
- NameTHE GOLDEN HERITAGE
- Entity typePartnership
- PartnersANAND HASTIMAL JAIN, AJAY HASTIMAL JAIN
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on15 Jul 2021
- Promised completion15 Jul 2026
- Revised completionRevised to 15 Jul 2026 (originally 31 Mar 2025)
- Buildings125 building records
- Documents filed123 files
Current status
Figures as on 27 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| THE GOLDEN HERITAGE ROW HOUSE 3 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 4 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 5 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 6 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 7 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 8 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 9 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 10 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 11 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 12 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 13 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 14 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 15 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 16 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 17 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 18 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 19 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 20 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 21 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 22 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 23 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 24 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 25 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 26 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 27 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 28 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 29 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 30 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 31 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 32 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 33 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 34 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 35 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 36 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 51 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 52 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 53 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 54 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 55 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 56 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 57 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 58 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 59 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 60 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 61 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 62 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 63 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 64 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 65 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 66 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 67 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 68 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 69 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE70 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 71 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 72 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 73 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 74 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 75 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 76 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 77 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 78 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 79 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 80 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 81 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 82 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 83 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 84 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 85 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 86 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 87 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 88 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 89 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 90 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 91 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 92 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 93 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 96 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 97 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 98 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 99 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 100 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 101 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 102 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 103 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 104 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 105 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 106 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 107 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 108 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 109 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 110 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 111 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 112 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 113 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 114 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 115 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 116 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 117 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 118 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 119 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 120 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 121 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 122 | NA | 2 | 1 | 1 | 0 | 1 |
| THE GOLDEN HERITAGE ROW HOUSE 125 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 126 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 127 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 128 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 129 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 130 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 131 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 132 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 133 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 134 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 135 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 136 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 137 | NA | 3 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 138 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 139 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 140 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 141 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 142 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 143 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 144 | NA | 2 | 1 | 0 | 0 | 0 |
| THE GOLDEN HERITAGE ROW HOUSE 145 | NA | 2 | 1 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 27 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 125 buildings; the table lists the first 20.
1130 of 1375 construction stages are filed complete across 125 buildings. The stage furthest along is Staircases, at 80%.
THE GOLDEN HERITAGE ROW HOUSE 3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 5100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 6100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 7100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 8100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 9100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 10100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 11100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 12100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 13100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 14100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 15100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 16100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 17100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 18100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 19100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 20100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 21100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
THE GOLDEN HERITAGE ROW HOUSE 220%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| THE GOLDEN HERITAGE ROW HOUSE 3 | NA | Rs 17.00 cr | Rs 16.88 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DHANANJAY NARENDRA JOSHI |
| Architect | D.N. Joshi Architect |
| Engineer | Anil Sanjay Mali |
| Engineer | Samarth Vastu Engineers |
| Engineer | Nitin Indarchand Jain |
| Chartered Accountant | VARDHAMAN SBHANDARI |
| Chartered Accountant | RSPH & Associates |
| Chartered Accountant | CA Pratik D Jain & Associates |
| Partner | Role in project |
|---|---|
| THE GOLDEN HERITAGE | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter3. We have obtained occupancy certificate for the project from Urban Planning and Pricing Department, Nandurbar dated 13/06/2025. The copy of the same is attached herewith. 4. Our project is completed. We have to remove Row Houses on Plot No.22, 109, and 125 to 145 which are not related to the project “The Golden Heritage” as at present we do not intend to market, construct, or sell the said Row Houses. Accordingly, the same are required to be corrected and updated on the MahaRERA portal. 5. Since the project completion date was 31.03.2025, RERA portal is not allowing to file correction applic
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Jun 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jun 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 16 Jun 2025
Documents filed123
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form-1 - Sept 25.pdf | 27 Apr 2026 |
| Withdrawal Update Form 1File: AR - Dec 25_11zon.pdf | 27 Apr 2026 |
| Withdrawal Update Form 1File: AR - Dec 25_11zon.pdf | 27 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Sept 25.pdf | 27 Apr 2026 |
| Withdrawal Update Form 2File: ER - Dec 25 .pdf | 27 Apr 2026 |
| Withdrawal Update Form 2File: ER - Dec 25 .pdf | 27 Apr 2026 |
| Withdrawal Update Form 3File: CA - Sept 25.pdf | 27 Apr 2026 |
| Withdrawal Update Form 3File: CA - DEC 25.pdf | 27 Apr 2026 |
| Withdrawal Update Form 3File: CA - DEC 25.pdf | 27 Apr 2026 |
| Withdrawal Update Form 1File: AR June 25 Compressed.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: ER june 25.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: CA Certificate-June 25 Final.pdf | 24 Apr 2026 |
| Form 2A (FY 2021-2022)File: Form 2A March 22.pdf | 27 Jan 2026 |
| Form 2A (FY 2022-2023)File: Form 2A March 23.pdf | 27 Jan 2026 |
| Form 5 (FY 2024-2025)File: RERA Audit report 24-25 final.pdf | 5 Nov 2025 |
| Form 2A (FY 2024-2025)File: Form 2A.pdf | 30 Oct 2025 |
| Form 2A (FY 2023-2024)File: Form 2A March 24.pdf | 30 Oct 2025 |
| Form 1File: AR certificate Dec 24.pdf | 16 Oct 2025 |
| Form 2File: ER certificate Dec 24.pdf | 16 Oct 2025 |
| Form 3File: CA Certificate Dec 24.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Dec 24.pdf | 16 Oct 2025 |
| Form 1File: AR Mar 25.pdf | 16 Oct 2025 |
| Form 2File: ER cert Mar 25.pdf | 16 Oct 2025 |
| Form 3File: CA Cert Mar 25.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Mar 25.pdf | 16 Oct 2025 |
| Form 1File: AR SEP 24 (1).pdf | 16 Oct 2025 |
| Form 2File: ER SEP 24.pdf | 16 Oct 2025 |
| Form 3File: CA SEP 24.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure SEP 24.pdf | 16 Oct 2025 |
| Form 1File: AR June 24.pdf | 16 Oct 2025 |
| Form 2File: ER June 24.pdf | 16 Oct 2025 |
| Form 3File: CA June 24.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure June 24.pdf | 16 Oct 2025 |
| Form 1File: AR March 24.pdf | 16 Oct 2025 |
| Form 2File: ER March 24.pdf | 16 Oct 2025 |
| Form 3File: CA March 24.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure March 24.pdf | 16 Oct 2025 |
| Form 5 (FY 2023-2024)File: Form 5 (23-24).pdf | 15 Oct 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Updated OC Certificate.pdf | 16 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 30 Apr 2025 |
| Other - TechnicalFile: Form 2A.pdf | 30 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - Dec 24.pdf | 4 Apr 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 27 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR cert_compressed-2.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR cert_compressed-8.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR cert_compressed-7.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR cert_compressed-6.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR cert_compressed-5.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR cert_compressed-4.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR cert_compressed-3.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR cert_compressed-1.pdf | 7 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA cert_compressed.pdf | 7 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER certificate.pdf | 7 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Golden Heritage form 5.pdf | 4 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR SEP 24-91-129_compressed.pdf | 26 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR SEP 24-46-90_compressed.pdf | 26 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR SEP 24-1-45_compressed.pdf | 26 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA SEP 24 Sign copy.pdf | 26 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER SEP 24.pdf | 26 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Document 3.pdf | 28 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: archtict certificate june2024_0001_compressed_compressed_compressed_compressed - converted | 20 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIJUNE2024_0001.pdf | 20 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate June 2024 - Signed.pdf | 20 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 19 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ilovepdf_merged - converted - converted-4 - converted-2.pdf | 13 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 13 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Golden Heritage - converted (1).pdf | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate-1-45.pdf | 23 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate-46-90.pdf | 23 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate-91-128.pdf | 23 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 23 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate - converted.pdf | 23 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: disclousure book inventory_0001.pdf | 22 Apr 2024 |
| Other - TechnicalFile: Form 2A.pdf | 22 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate_march 23.pdf | 18 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate June 23-1.pdf | 18 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate Sept 23-2.pdf | 18 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Cert March 23.pdf | 18 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er cert June 23.pdf | 18 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Cert sept 23.pdf | 18 Nov 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 123 filed documents as one ZIP, foldered, with a manifest
Keep THE GOLDEN HERITAGE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NANDURBAR17 in Nandurbar
C B Market
Katariya Land Developers & Builders LLP
Ashtavinayak Residency
Yogesh Pramodshankar Desai
BHANUDHAN PLAZA
SHAH ENTERPRISES
Chhoriya Residency Nandurbar Phase-3
Chhoriya and Kela Developers
Chhoriya Residency Nandurbar Phase - 2
Chhoriya and Kela Developers
Chhoriya Residency Nandurbar Phase -4
Chhoriya and Kela Developers
See every Nandurbar project, with the district possession charts
Builder: THE GOLDEN HERITAGE
THE GOLDEN HERITAGE has 1 registration on MahaRERA, including THE GOLDEN HERITAGE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nandurbar district page.
Frequently asked questions
What are my rights if THE GOLDEN HERITAGE is delayed beyond 15 Jul 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of THE GOLDEN HERITAGE?
The registered promoter entity is THE GOLDEN HERITAGE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in THE GOLDEN HERITAGE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for THE GOLDEN HERITAGE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at THE GOLDEN HERITAGE?
The professionals named in the filing: Architect: DHANANJAY NARENDRA JOSHI; Architect: D.N. Joshi Architect; Engineer: Anil Sanjay Mali; Engineer: Samarth Vastu Engineers; Engineer: Nitin Indarchand Jain; Chartered Accountant: VARDHAMAN SBHANDARI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in THE GOLDEN HERITAGE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback