The Altimus
RG-MH-88676 · RERA PM1180002501362 · Last updated on MahaRERA portal: 16 Nov 2026
Why this is marked a redevelopment: this filing shows 16 flats filed as rehab units, MahaRERA's column for homes returned to existing occupants or owners. MahaRERA has no redevelopment field, so this is ReraGenie's reading of the filing. Redevelopment across Mumbai Suburban.
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- No extension sought by the promoter; the date moved only under MahaRERA's automatic 4-month extension
- No encumbrance on the project land
- Separate project account declared
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
The Altimus is a Mixed project by Sosar Corporation LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as PM1180002501362 on 31 Oct 2025. Possession is promised by 30 Jan 2030. The completion date has moved by 4 months under MahaRERA's automatic 4-month extension for the West Asia conflict, which the promoter did not apply for. 14 of the 34 units on this registration are recorded sold or booked, and 2 of 10 construction stages are filed complete.
At a glance
Project
- NameThe Altimus
- TypeMixed
- Location
- FP No. 576 Khar West in H/W Ward
- Khar West in H/W Ward
- Others
- CTSO Bandra
- Mumbai Suburban
- 400052
- Pincode400052
- MapView location on Google Maps (as filed on RERA)
- RERA no.PM1180002501362
- ReraGenie IDRG-MH-88676
Builder
- NameSosar Corporation LLP
- Entity typeLimited Liability Partnership
- LLPINACB-6119
- Designated PartnersPravinkumar Basantilal Chordia, Arvinkumar Kewalchand Marlecha
- PartnersDarsh Prakash Shah, M/s. J Bhogilal Construction LLP, M/s. Sosar Enterprises LLP
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Oct 2025
- Promised completion30 Jan 2030
- Revised completionRevised to 30 Jan 2030 (originally 30 Sep 2029)
- Buildings1 building record
- Documents filed29 files
Current status
Figures as on 16 Nov 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Proposed Redevelopment Building | NA | 16 | 16 | 27 | 7 | 34 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Nov 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 10 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 13%.
Proposed Redevelopment Building: 21% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 13% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 16 Nov 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 0% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | 0% |
| Water conservation /Rain water harvesting | No | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | 0% |
| Electrical meter room, sub-station, receiving station | No | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed54
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Kamal Kunj Co Operative Housing Society LTD | Others | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Proposed Redevelopment Building | NA | Rs 8.32 cr | Rs 3.28 cr |
| - | NA | Rs 5.55 cr | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rasik P Hingoo Associates |
| Engineer | Tosif H Inamdar |
| Engineer | Saadiq M Patel |
| Chartered Accountant | WINNER & CO. Chartered Accountant |
| Chartered Accountant | Jain Jain & Associates Chartered Accountants |
| Partner | Role in project |
|---|---|
| Sosar Corporation LLP | - |
Extensions1
A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.
Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportNot on the file
A lawyer's report on who owns the land and what is registered against it.
- Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Oct 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Oct 2025 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jan 2030
Documents filed29
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 as on date 30-09-2026 for The Altimus.pdf | 16 Nov 2026 |
| Withdrawal Update Form 1File: Form 1 as on date 30-09-2026 for The Altimus.pdf | 16 Nov 2026 |
| Withdrawal Update Form 2File: FORM 2- SOSAR CORPORATION LLP.pdf | 16 Nov 2026 |
| Withdrawal Update Form 2File: FORM 2- SOSAR CORPORATION LLP.pdf | 16 Nov 2026 |
| Withdrawal Update Form 3File: The Altimus Form 3 141026 Final (1).pdf | 16 Nov 2026 |
| Withdrawal Update Form 3File: The Altimus Form 3 141026 Final (1).pdf | 16 Nov 2026 |
| Form 5 (FY 2025-2026)File: Form 5 Corp LLP_261105_130107.pdf | 5 Nov 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A Corporation llp 2025-2026 (The Altimus).pdf | 23 Oct 2026 |
| Withdrawal Update Form 1File: Form 1 as on date 30-09-2026 for The Altimus.pdf | 15 Oct 2026 |
| Withdrawal Update Form 2File: FORM 2- SOSAR CORPORATION LLP.pdf | 15 Oct 2026 |
| Withdrawal Update Form 3File: The Altimus Form 3 141026 Final (1).pdf | 15 Oct 2026 |
| Withdrawal Update Form 1File: Form 1_dtd 30-06-2026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 2File: Form 2_dtd 30-06-2026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 3File: The Altimus Final Form 3.pdf | 23 Jul 2026 |
| Withdrawal Update Form 1File: Form-1 as on March 2026.pdf | 15 May 2026 |
| Withdrawal Update Form 2File: Form-2 as on March 2026.pdf | 15 May 2026 |
| Withdrawal Update Form 3File: Form -3 Altimus_Q4.pdf | 15 May 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 as on December 2025.pdf | 2 Feb 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 as on December 2025.pdf | 2 Feb 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 as on December 2025.pdf | 2 Feb 2026 |
| Layout approvalFile: Plan page 1.pdf | 8 Oct 2025 |
| Building plan approvalFile: Plan page 1.pdf | 8 Oct 2025 |
| Building plan approvalFile: Plan Page 2.pdf | 8 Oct 2025 |
| Building plan approvalFile: Plan Page 3.pdf | 8 Oct 2025 |
| Building plan approvalFile: Plan Page 4.pdf | 8 Oct 2025 |
| Building plan approvalFile: Plan Page 5.pdf | 8 Oct 2025 |
| Building plan approvalFile: Plan page 6.pdf | 8 Oct 2025 |
| Building plan approvalFile: Plan Page 7.pdf | 8 Oct 2025 |
| Declaration and undertaking (Annexure A)File: Plot Declaration Order 50.pdf | 7 Oct 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,900+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 29 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep The Altimus on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Khar West in H/W Ward6,900+ in Mumbai Suburban
Filed coordinates, straight-line distance. 319 registered projects within 2 km.
Purva Parkhill
Puravankara Limited
Rustomjee Crescent
KEYVIHAR REALTORS PRIVATE LIMITED
Nebula Empress
M/s Shiv Sai developer
Joy Legend Wing B
Bhavin Jayant Soni
PLATINUM OCEANIC
PLATINUMCORP LIFESCAPES LLP
Venue 52
Wadhwa Dreamscapes Private limited
See every Mumbai Suburban project, with the district possession charts
Builder: Sosar Corporation LLP
Sosar Corporation LLP has 1 registration on MahaRERA, including The Altimus. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if The Altimus is delayed beyond 30 Jan 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of The Altimus?
The registered promoter entity is Sosar Corporation LLP, a limited liability partnership as per the filing. Its LLPIN ACB-6119 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in The Altimus?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for The Altimus?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at The Altimus?
The professionals named in the filing: Architect: Rasik P Hingoo Associates; Engineer: Tosif H Inamdar; Engineer: Saadiq M Patel; Chartered Accountant: WINNER & CO. Chartered Accountant; Chartered Accountant: Jain Jain & Associates Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in The Altimus?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback