Red flags

  • 4 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 3 completed earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
4Complaints at MahaRERAon this registration
Jump to the 132 documents Report an error

TEN X HABITAT Raymond Realty Tower D is a Residential / Group Housing project by Raymond Limited in Thane, Maharashtra, registered with MahaRERA as P51700020881 on 15 May 2019. The registration is recorded completed; possession was promised by 30 Sep 2025. 4 complaints are on record with the regulator.

At a glance

Project

  • NameTEN X HABITAT Raymond Realty Tower D
  • TypeResidential / Group Housing
  • Location
    • Pokhran Road
    • J K Gram
    • Chavindra
    • Thane
    • 400606
  • Pincode400606
  • RERA no.P51700020881
  • ReraGenie IDRG-MH-03332

Builder

  • NameRaymond Limited
  • Entity typeCompany
  • DirectorHarmohan Harminder Sahni
  • Other registrations14 more →
  • Completed9 of 15
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects24 →

Key dates

this monthRegisteredMay 2019PromisedSep 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 May 2019
  • Promised completion30 Sep 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed132 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower DNA440000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Tower D: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes30%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes30%
Street LightingYes30%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area990 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI15036.89
Proposed, not sanctioned14,360 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFort, Mumbai - 400001

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Raymond Limited-

Litigation declared11

CaseCourtStatus
27/2022Maharashtra Revenue Tribunal Mumbai against RLPending for argument
158/2012Bombay High Court against RLPending
13/2016Bombay High Court against RLPending
57/2016Bombay High Court against RLPending
71/2017Bombay High Court against RLPending
997/2019Civil Judge Senior Division Thane against RLFor evidence of plaintiff
34/2020District Court Thane against RLArgument of order dt eleven feb two thousand twenty in sr no seven above
315/2020Civil Judge Senior Division Thane against RLPending for argument on injunction application
583/2021High Court Bombay against RLfor argument
10027/2021Sub Division Office Thaneclosed for order
51/2021District Consumer Dispute Redressal ComissionPending

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000375053Raymond LimitedMr.Faizan Ashraf Khan 2.Mr.Mohd Nawaz Ashraf Khan31/03/2023
CC006000000375042Raymond Limited1.Mrs Zarina Ashraf Khan 2.Mr.Mohammed Zeeshan Ashraf Khan31/03/2023
CC006000000429602Jagdish Sanjeeva ShettyRaymond Limited11/03/2024
CC12502503Raymond LimitedMRS ZARINA NOOR AHMED SURVE21/07/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 May 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 May 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 May 2024

Documents filed132

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 132 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrancesFile: release of loan.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Annexure 2-TENX Habitat Tower D.pdf7 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC TOWER D.pdf7 May 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Tower D.pdf7 May 2024
Disclosure of sold/ booked inventoryFile: Habitat Tower D.pdf23 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tower D.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 Ten X Habitat Tower D.pdf18 Apr 2024
Form 2AFile: TOWER D FORM2A.pdf18 Apr 2024
CERSAI detailsFile: CERSAI TOWER D.pdf18 Apr 2024
Certificates of CA (Form 3)File: Form 3Tower D Habitat.pdf18 Apr 2024
Form 2AFile: Ten X Habitat TOWER D.pdf15 Apr 2024
Disclosure of sold/ booked inventoryFile: TEN X HABITAT TOWER -D_240123_123745.pdf23 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tower D.pdf18 Jan 2024
CERSAI detailsFile: CERSAI_Search_Report_200293543298_For_Asset_Based_Search_15_01_2024_16_24_37_351.pdf16 Jan 2024
CERSAI detailsFile: CERSAI_Search_Report_200293543993_For_Asset_Based_Search_15_01_2024_16_28_52_682.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ten X Habitat Tower D_240109_174210.pdf12 Jan 2024
Certificates of CA (Form 3)File: tower d_240112_161849.pdf12 Jan 2024
Certificates of CA (Form 3)File: Form 3 Tower D revised.pdf20 Nov 2023
Disclosure of sold/ booked inventoryFile: TOWER D.pdf31 Oct 2023
Certificates of CA (Form 3)File: Form 3 Tower D.pdf31 Oct 2023
CERSAI detailsFile: 1.pdf27 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tower D.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Tower D.pdf26 Oct 2023
Form 2AFile: tower d.pdf26 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: TOWER D D.pdf30 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: TOWER D D.pdf30 Sep 2023
Disclosure of sold/ booked inventoryFile: TOWER D.pdf25 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tower D .pdf18 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tower - D.pdf18 Jul 2023
Form 2AFile: Form 2A Tower D.pdf18 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200274181216_For_Asset_Based_Search_13_07_2023_12_48_17_371.pdf18 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200274181361_For_Asset_Based_Search_13_07_2023_12_49_06_325.pdf18 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200274181414_For_Asset_Based_Search_13_07_2023_12_49_24_768.pdf18 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200274181414_For_Asset_Based_Search_13_07_2023_12_49_24_768.pdf18 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200274181465_For_Asset_Based_Search_13_07_2023_12_49_44_403.pdf18 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200274181616_For_Asset_Based_Search_13_07_2023_12_50_33_549.pdf18 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200274181709_For_Asset_Based_Search_13_07_2023_12_50_56_216.pdf18 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200274181959_For_Asset_Based_Search_13_07_2023_12_51_35_363.pdf18 Jul 2023
Certificates of CA (Form 3)File: Form 3 Tower D.pdf18 Jul 2023
Form 2AFile: Tower D Form 2A.pdf30 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tower D.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tower D.pdf17 Apr 2023
Certificates of CA (Form 3)File: Form 3 Tower D.pdf17 Apr 2023
Disclosure of sold/ booked inventoryFile: sold unsold.pdf10 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019 2020.pdf29 Mar 2023
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf23 Feb 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf20 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tower D.pdf18 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 RERA - TowerD -10 01 23.pdf18 Jan 2023
Form 2AFile: FORM 2A.pdf18 Jan 2023
Certificates of CA (Form 3)File: Form 3 Tower D .pdf18 Jan 2023
Form 2AFile: Form2A.pdf10 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1.pdf7 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf7 Oct 2022
Certificates of CA (Form 3)File: Form 3.pdf7 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Tower D.pdf30 Sep 2022
Details of encumbrancesFile: Declaration.pdf25 Jul 2022
Form 2AFile: FORM 2A-D.pdf12 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tower D_.pdf8 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tower D.pdf8 Jul 2022
Certificates of CA (Form 3)File: Form 3 Tower D.pdf8 Jul 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Decleration Tower D.pdf8 Apr 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Tower D.pdf8 Apr 2022
OtherFile: TOWER D.pdf8 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tower D 24 03 22.pdf7 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 RERA - Tower D -2022 03 24.pdf7 Apr 2022
Form 2AFile: Tower D.pdf7 Apr 2022
Certificates of CA (Form 3)File: Form 3 RERA Tower D 310322 signed.pdf7 Apr 2022
Copy of the legal title reportFile: Title Report Maharera.pdf31 Jan 2022
Disclosure of sold/ booked inventoryFile: Tower D.pdf23 Dec 2021
Status of ConveyanceFile: Tower D.pdf23 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower D - Dec.pdf22 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Tower D.PDF22 Dec 2021
CERSAI detailsFile: CERSAI REPORT DEC 2021.pdf22 Dec 2021
Certificates of CA (Form 3)File: Tower D.pdf22 Dec 2021
CERSAI detailsFile: CERSAI REPORT DEC 2021.pdf15 Dec 2021
OtherFile: Tower D.pdf4 Oct 2021
Disclosure of sold/ booked inventoryFile: TOWER D.pdf30 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Tower D.pdf30 Sep 2021
OtherFile: CERSAI Report.pdf30 Sep 2021

Promoter's earlier projects7

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise4 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
The Address by GS Tower EP51700077861Thane, Thane144Nov 2024OngoingMar 2030Not due yet
The Address by GS Tower EP51700077861Thane, Thane144Nov 2024OngoingMar 2030Not due yet
The Address by GS Tower EP51700077861Thane, Thane144Nov 2024OngoingMar 2030Not due yet
INVICTUS BY GSP51700052012Village Panchpakhadi, Thane102Jul 2023OngoingOct 2028Not due yet
TEN X HABITAT Raymond Realty Tower CJ K Gram Pokhran Road Thane 400606244-CompletedMar 2024Mar 2024
TEN X HABITAT Raymond Realty Tower A and BJ K Gram Pokhran Road Thane 400606638-CompletedMar 2024Mar 2024
Raymond Realty Premium IJ K Gram Pokhran Road Thane 40060675-CompletedMar 2024Mar 2024

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TEN X HABITAT Raymond Realty Tower D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near J K Gram7,600+ in Thane

Builder: Raymond Limited

Raymond Limited has 15 registrations on MahaRERA, including TEN X HABITAT Raymond Realty | Tower A & B and TEN X HABITAT Raymond Realty Tower C. Its filings disclose 24 earlier MahaRERA projects: declares 19 of 19 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if TEN X HABITAT Raymond Realty Tower D is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TEN X HABITAT Raymond Realty Tower D?

The registered promoter entity is Raymond Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TEN X HABITAT Raymond Realty Tower D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against TEN X HABITAT Raymond Realty Tower D?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for TEN X HABITAT Raymond Realty Tower D?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in TEN X HABITAT Raymond Realty Tower D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TEN X HABITAT Raymond Realty Tower D. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TEN X HABITAT Raymond Realty Tower D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.