Registered No litigation declared Residential / Group Housing project

Tathastu Homes

By Shri Bhagyalaxmi Infracon

RG-MH-39346 · RERA P52100046818 · Last updated on MahaRERA portal: 27 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2029Possession promisedmoved 48 months from the original
8 of 11Construction stages donefurthest along: Installation of Lifts, 95%
44 of 80Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 84 documents Report an error

Tathastu Homes is a Residential / Group Housing project by Shri Bhagyalaxmi Infracon in Pune, Maharashtra, registered with MahaRERA as P52100046818 on 10 Sep 2022. Possession is promised by 1 Jun 2029. The completion date has moved by 48 months from the original filing. 36 of the 80 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameTathastu Homes
  • TypeResidential / Group Housing
  • Location
    • Gat No 135 Gat No 136
    • Chakan
    • Nanekarwadi (CT)
    • Khed
    • Pune
    • 410501
  • Pincode410501
  • RERA no.P52100046818
  • ReraGenie IDRG-MH-39346

Builder

  • NameShri Bhagyalaxmi Infracon
  • Entity typePartnership
  • PartnersSandeep Balkrishna Rajarshi, Ramdas Damodar Phuge

Key dates

this monthRegisteredSep 2022First promiseJun 2025Revised toJun 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Sep 2022
  • Promised completion1 Jun 2029
  • Revised completionRevised to 1 Jun 2029 (originally 1 Jun 2025)
  • Buildings1 building record
  • Documents filed84 files

Current status

45%36 of 80 units booked
56.4%Work done, per cost certificate

Figures as on 27 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tathastu HomesNA5580080

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

Tathastu Homes: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 27 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes75%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes60%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed80

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots80
Closed/Covered50
Open Space30

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,200 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 May 2025
LandownerVillageDistrict
Sakharam Baban MandaleChakan (CT)Pune
Bhikoba Sakharam DhadageChakan (CT)Pune
Vijay Vitthal GaikwadChakan (CT)Pune
Bharat Shankar HulawaleChakan (CT)Pune
Vilas Harakchand BotharaChakan (CT)Pune

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI3122.34
Proposed, not sanctioned3,122 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHINJAWADI PUNE
Estimated costRs 7.85 cr
Cost incurredRs 4.43 cr
Work done56.4%
BuildingWingEstimatedIncurred
Tathastu HomesNARs 7.18 crRs 4.12 cr
-NARs 66.72 lakhRs 30.32 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDESIGN PLACE
EngineerSANDEEP B RAJARSHI
Chartered AccountantR G BHILARE & CO
Chartered AccountantV R V K & Associates
Chartered AccountantAmruta Shinde & Associates
PartnerRole in project
Shri Bhagyalaxmi Infracon-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA19052501174Jun 2025 → Jun 2026

Reason as filed by the promoterDue to strike of material, labour and some financial crunches and also we required an additional time for obtaining NOC/Permissions from various Corporation departments like Water Supply, Garden Department, Drainage Department, Vermiculture Department and Road Department.

EA29052621162Jun 2025 → Jun 2029

Reason as filed by the promoterThe Promoter is now proposing to commence and undertake the construction and development work of Building C Wing of the said project, and therefore extension of the project registration is required for completion of the said remaining development work and obtaining necessary approvals.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 1 Jun 2029

Documents filed84

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf27 Aug 2026
Withdrawal Update Form 2File: FORM 2 ENGINEERCERT.pdf27 Aug 2026
Withdrawal Update Form 3File: FORM 3.pdf27 Aug 2026
Form 2A (FY 2025-2026)File: FORM 2A (2).pdf19 Aug 2026
Withdrawal Update Form 1File: Form 1_Architecture Certificate.pdf7 Apr 2026
Withdrawal Update Form 2File: FORM 2 ENGINEER.pdf7 Apr 2026
Withdrawal Update Form 3File: FORM 3-Shri Bhagyalaxmi Infracon.pdf7 Apr 2026
Withdrawal Update Form 1File: Form 1_Architecture Certificate.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM 2 ENGINEER.pdf20 Jan 2026
Withdrawal Update Form 3File: FORM 3-Shri Bhagyalaxmi Infracon.pdf20 Jan 2026
Withdrawal Update Form 1File: FORM-1RERA CERTIFICATE 06-10-25.pdf30 Oct 2025
Withdrawal Update Form 2File: FORM 2 ENGINEER.pdf30 Oct 2025
Withdrawal Update Form 3File: FORM-3-SEPT-25.pdf30 Oct 2025
Withdrawal Update Form 1File: Arch-Rera certificate 21-07-2025.pdf31 Jul 2025
Withdrawal Update Form 1File: Arch-Rera certificate 21-07-2025.pdf31 Jul 2025
Withdrawal Update Form 2File: FORM 2 ENGG.pdf31 Jul 2025
Withdrawal Update Form 2File: FORM 2 ENGG.pdf31 Jul 2025
Withdrawal Update Form 3File: form-3-signed-march-25.pdf31 Jul 2025
Withdrawal Update Form 3File: FORM 3.pdf31 Jul 2025
Form 1File: Form-1-rera certificate.pdf27 Jun 2025
Form 2File: FORM 2 ENGINEER.pdf27 Jun 2025
Form 3File: form-3-signed-march-25.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: -Disclosure of Sold and Unsold Inventory.pdf27 Jun 2025
Self-declaration of Quarterly ProgressFile: Self-Declaration for Quarterly Progress.pdf27 Jun 2025
OthersFile: Disclosure of Sold and Unsold Inventory.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-rera certificate 15-04-25_compressed.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form-3-signed-march-25_compressed.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: -Disclosure of Sold and Unsold Inventory.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA CERTIFICATE - 31-01-25.pdf3 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 RERA-sign-311224_compressed.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA CERTIFICATE - 24-07-24 (1).pdf17 Dec 2024
Disclosure of sold/ booked inventoryFile: SHREEBHAGYALAXMI-Disclosure of Sold and Unsold Inventory FINAL.pdf17 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory30-09-24.pdf17 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5.pdf17 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Shribhgyalaxmi.pdf15 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 May 2024
Disclosure of sold/ booked inventoryFile: SHREEBHAGYALAXMI-Disclosure of Sold and Unsold Inventory FINAL.pdf27 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Shri Bhagyalaxmi Infracon_11zon.pdf27 Apr 2024
Proforma of Agreement for saleFile: 1 Proforma of Allotment letter.pdf27 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 22-23-Shri BhagyalaxmiFORM 2A- Quality Assurance Certificate b.pdf20 Feb 2024
Disclosure of sold/ booked inventoryFile: SBI Disclosure of sold unsold inventory-Q-3-2023-24.pdf20 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Bhagyalaxmi_compressed.pdf19 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3-SHRI-BHAGYALAXMI_compressed.pdf19 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-rera certificate 04-10-2023.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: SHREEBHAGYALAXMI-Disclosure of Sold and Unsold Inventory FINAL.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-shribhagyalaxmi_compressed.pdf20 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DOI Ram sir.pdf20 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Projects-Sandeep.pdf20 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DOI Shinde sir.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-5-shribhagyalaxmi.pdf20 Oct 2023
Layout approvalFile: Map-02-02.pdf25 Sep 2023
Copy of Layout Approval (in case of layout)File: Map-02-02.pdf25 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf9 Mar 2023
Disclosure of sold/ booked inventoryFile: Disclousre of Sold Unsold.pdf9 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account details and declaration.pdf9 Mar 2023
Proforma of Allotment letterFile: Performa Allotment Letter Format.pdf1 Sep 2022
Proforma of Allotment letterFile: Draft Agreement.pdf23 Aug 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report.pdf23 Aug 2022
Details of encumbrances concerned to LegalFile: Encrumbarance Certificate.pdf4 Jul 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: CHEQUE PHOTO SHRI BHAGYALAXMI INFRACON.pdf4 Jul 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration.pdf4 Jul 2022
Deviation Report with respect to Allotment letterFile: Deviation Report.pdf4 Jul 2022
Declaration in FORM BFile: FORM-B_compressed.pdf20 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA-CERTIFICATE_compressed.pdf20 Jun 2022
Copy of the legal title reportFile: Search and Title Report.pdf11 Jun 2022
CERSAI detailsFile: CERSAI_Search_Report_200239508282_For_Debtor_Based_Search_11_06_2022_15_06_00_780.pdf11 Jun 2022
CERSAI detailsFile: CERSAI_Search_Report_200239508508_For_Asset_Based_Search_11_06_2022_15_15_21_886.pdf11 Jun 2022
CERSAI detailsFile: CERSAI_Search_Report_200239508534_For_Asset_Based_Search_11_06_2022_15_16_12_216.pdf11 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA-Form 3_compressed.pdf11 Jun 2022
Layout approvalFile: Plan Layout.pdf3 Jun 2022
Building plan approvalFile: Plan Layout.pdf3 Jun 2022
Building plan approvalFile: NA ORDER.PDF3 Jun 2022
PAN CardFile: pancard letter.pdf3 Jun 2022
Copy of the legal title reportFile: Copy of legal title report_compressed.pdf3 Jun 2022
Details of encumbrancesFile: Encrumbarance Certificate.pdf3 Jun 2022
Copy of Layout Approval (in case of layout)File: Plan Layout.pdf3 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan Layout.pdf3 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER.PDF3 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.PDF3 Jun 2022
Declaration about Commencement CertificateFile: Declaration about commencment certificate.pdf3 Jun 2022

How this compares with Pune

45%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 48 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Tathastu Homes on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chakan13,700+ in Pune

Builder: Shri Bhagyalaxmi Infracon

Shri Bhagyalaxmi Infracon has 1 registration on MahaRERA, including Tathastu Homes. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Tathastu Homes is delayed beyond 1 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Tathastu Homes?

The registered promoter entity is Shri Bhagyalaxmi Infracon, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Tathastu Homes?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Tathastu Homes?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Tathastu Homes?

The professionals named in the filing: Architect: DESIGN PLACE; Engineer: SANDEEP B RAJARSHI; Chartered Accountant: R G BHILARE & CO; Chartered Accountant: V R V K & Associates; Chartered Accountant: Amruta Shinde & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Tathastu Homes?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Tathastu Homes. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Tathastu Homes to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.