Home / Browse projects / Pune, Maharashtra / Tara Mondesire
Tara Mondesire
RG-MH-24625 · RERA P52100011353 · Last updated on MahaRERA portal: 17 Mar 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 12 months past the filed date
- Completion date moved by 82 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Tara Mondesire is a Others project by Nilesh Shivjee Singh in Pune, Maharashtra, registered with MahaRERA as P52100011353 on 31 Aug 2017. Possession was promised by 31 Oct 2025 and is now 12 months past that date. The completion date has moved by 82 months from the original filing.
At a glance
Project
- NameTara Mondesire
- TypeOthers
- Location
- Pune-Solapur Highway
- Uruli Kanchan-Dalim Road
- Uruli Kanchan
- Haveli
- Pune
- 412202
- Pincode412202
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100011353
- ReraGenie IDRG-MH-24625
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Aug 2017
- Promised completion31 Oct 2025
- Revised completionRevised to 31 Oct 2025 (originally 31 Dec 2018)
- Buildings5 building records
- Documents filed149 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 6 | 0 | 0 | 0 | 0 |
| Wing B | NA | 6 | 0 | 0 | 0 | 0 |
| Wing C | NA | 6 | 0 | 0 | 0 | 0 |
| Wing D | NA | 6 | 0 | 0 | 0 | 0 |
| Amenity Building | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 17 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
50 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 0%.
Wing A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Amenity Building91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 17 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed61
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Wing A | 10 | 5 | 15 |
| Wing B | 16 | 4 | 20 |
| Wing C | 1 | 5 | 6 |
| Wing D | 1 | 4 | 5 |
| Amenity Building | 10 | 5 | 15 |
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Pramod Haribhau Kanchan and other | Pune (M Corp.) | Pune |
| Ganesh Haribhau Kanchan | Pune (M Corp.) | Pune |
| Santosh Haribhau Kanchan | Pune (M Corp.) | Pune |
| Kishor Haribhau Kanchan | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sumitesh Zinjurde |
| Engineer | Sagar Salunke |
| Chartered Accountant | K P Joshi & Associates |
| Chartered Accountant | Chandrashekher Sarda |
| Chartered Accountant | JSVL and Co |
| Partner | Role in project |
|---|---|
| Nilesh Shivjee Singh | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO FINANCIAL ISSUES
Reason as filed by the promoterFinance problems
Reason as filed by the promoterFUND PROBLEM
Reason as filed by the promoterThe extension is majorly due to significant Material shortages, which severely have impacted the construction timeline, delaying important stages of project. However, the work of Wing A to Wing D is completed and we are preparing to apply for OC. Wing E is cancelled and Work of Amenity building is in process. Hence, additional time is required to address the delays, requesting you to grant us the same.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed149
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 149 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: 17-3-25 Sold booked inventory.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: Q3 24-25 Form 3_compressed.pdf | 12 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Q3 24-25 Sold booked inventory_compressed (1).pdf | 12 Mar 2025 |
| CERSAI detailsFile: Declaration of CERSAI.pdf | 12 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_c.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q3 24-25 Form 2.pdf | 19 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Q3 24-25 Sold booked inventory_compressed.pdf | 19 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: Details of Encumbrances - Finance and legal.pdf | 17 Feb 2025 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 17 Feb 2025 |
| Declaration in FORM BFile: Form B.pdf | 17 Feb 2025 |
| Deviation Report with respect to Allotment letterFile: Deviation report of allotment letter (2).pdf | 17 Feb 2025 |
| Details of encumbrances concerned to LegalFile: Details of Encumbrances - Finance and legal.pdf | 17 Feb 2025 |
| Deviation Report with respect to model copy of AgreementFile: Deviation report AFS_c.pdf | 17 Feb 2025 |
| Deviation Report with respect to model copy of AgreementFile: Deviation report AFS_c.pdf | 17 Feb 2025 |
| Proforma of Agreement for saleFile: Tara Mondesire AFS.pdf | 17 Feb 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about separate bank account.pdf | 28 Jan 2025 |
| CERSAI detailsFile: Declaration of CERSAI.pdf | 27 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2a 2022-23.pdf | 27 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23 signed.pdf | 27 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2a 2023-24.pdf | 27 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24 signed.pdf | 27 Jan 2025 |
| Building plan approvalFile: MD-2-6.pdf | 19 Nov 2024 |
| Building plan approvalFile: MD-3-6.pdf | 19 Nov 2024 |
| Building plan approvalFile: MD-4-6.pdf | 19 Nov 2024 |
| Building plan approvalFile: MD-5-6.pdf | 19 Nov 2024 |
| Building plan approvalFile: MD-6-6.pdf | 19 Nov 2024 |
| Building plan approvalFile: 1-2 c.pdf | 19 Nov 2024 |
| Building plan approvalFile: 2-2c.pdf | 19 Nov 2024 |
| Building plan approvalFile: MD-2-6.pdf | 19 Nov 2024 |
| Building plan approvalFile: MD-3-6.pdf | 19 Nov 2024 |
| Building plan approvalFile: MD-4-6.pdf | 19 Nov 2024 |
| Building plan approvalFile: MD-5-6.pdf | 19 Nov 2024 |
| Building plan approvalFile: MD-6-6.pdf | 19 Nov 2024 |
| Building plan approvalFile: 1-2 c.pdf | 19 Nov 2024 |
| Building plan approvalFile: 2-2c.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: MD-2-6.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: MD-3-6.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: MD-4-6.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: MD-5-6.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: MD-6-6.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: 1-2 c.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: 2-2c.pdf | 19 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q2 24-25.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 Q2 24-25_compressed.pdf | 19 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q1 24-25_compressed.pdf | 19 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q1 24-25.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 Q1 24-25_compressed.pdf | 19 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q2 24-25_compressed.pdf | 19 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory (2).pdf | 19 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q2 24-25_compressed.pdf | 19 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q1 24-25_compressed.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 Q2 24-25_compressed.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 Q1 24-25_compressed.pdf | 19 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q2 24-25.pdf | 19 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q1 24-25.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: MD-2-6.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: MD-3-6.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: MD-4-6.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: MD-5-6.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: MD-6-6.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: 1-2 c.pdf | 19 Nov 2024 |
| Building Plan Approval (IOD)File: 2-2c.pdf | 19 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory (2).pdf | 19 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q2 23-24c.pdf | 29 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q4 23-24c.pdf | 29 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q3 23-24.pdf | 29 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q1 23-24.pdf | 29 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q4 22-23.pdf | 29 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q3 22-23.pdf | 29 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q2 22-23.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3Q2 Tara Mondesire FY 22-23c.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: RERA Form 3 Shivtara Q4 FY 23-24c.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: RERA Form 3 Shivtara Q3 FY 23-24c.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: RERA Form 3 Shivtara Q2 FY 23-24c.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: RERA Form 3 Shivtara Q1 FY 23-24c.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3Q4 Tara Mondesire FY 22-23c.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3Q3 Tara Mondesire FY 22-23c.pdf | 29 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q3 22-23.pdf | 29 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q4 23-24.pdf | 29 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q3 23-24.pdf | 29 Oct 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Tara Tarang | S No 1146 Opp Raisoni College Dhomkhel Road Wagholi | 52 | Completed | Mar 2014 | Late, Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 149 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Tara Mondesire on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Uruli Kanchan-Dalim Road13,700+ in Pune
Filed coordinates, straight-line distance. 14 registered projects within 2 km.
Green Fantasy Phase-I
Shree Mangalmurti Associates Phase-I
24 KOREGAON GREENS
OBEROI INFRA CONSULTANT LLP
Chintamani Paradise
01/04/2017
Emerald City
Suresh kanchan & other 5
KANCHAN CITY
MR. SANJAY ABASAHEB KANCHAN AND OTHER - 1
GOKUL VILLA
GOKUL VILLA
Builder: Nilesh Shivjee Singh
Nilesh Shivjee Singh has 4 registrations on MahaRERA, including Tara Alicia and Tara Mondesire. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Tara Mondesire shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Tara Mondesire is delayed beyond 31 Oct 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Tara Mondesire?
The registered promoter entity is Nilesh Shivjee Singh, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Tara Mondesire?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Tara Mondesire?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Tara Mondesire?
The professionals named in the filing: Architect: Sumitesh Zinjurde; Engineer: Sagar Salunke; Chartered Accountant: K P Joshi & Associates; Chartered Accountant: Chandrashekher Sarda; Chartered Accountant: JSVL and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Tara Mondesire?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback