ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / SWASTIK RESIDENCY

Registered No litigation declared Mixed project

SWASTIK RESIDENCY

By SUGANDHI SWASTIK BUILDERS & DEVELOPERS

RG-MH-25475 · RERA P99000005439 · Last updated on MahaRERA portal: 4 Mar 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
6 of 33Construction stages doneacross 4 buildings; furthest along: Slabs of Super Structure, 50%
96 of 96Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 100 documents Report an error

SWASTIK RESIDENCY is a Mixed project by SUGANDHI SWASTIK BUILDERS & DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000005439 on 11 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 0 of the 96 units on this registration are recorded sold or booked, and 6 of 33 construction stages are filed complete.

At a glance

Project

  • NameSWASTIK RESIDENCY
  • TypeMixed
  • Location
    • Boisar Chillar Road
    • Betegaon
    • Palghar
    • 401501
  • Pincode401501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000005439
  • ReraGenie IDRG-MH-25475

Builder

  • NameSUGANDHI SWASTIK BUILDERS & DEVELOPERS
  • Entity typePartnership
  • GSTIN27ACLFS8495G1ZC
  • PartnerRAJESH MORESHWAR NAIK

Key dates

this monthRegisteredAug 2017First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2024)
  • Buildings3 building records
  • Documents filed100 files

Current status

0%0 of 96 units booked

Figures as on 4 Mar 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1NA4496096
BUILDING NO 2NA80000
BUILDING NO 3NA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 4 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 33 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

BUILDING NO 152%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
BUILDING NO 252%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
BUILDING NO 37%
ActivityProgress
Excavation25%
Basement (if any)25%
Podiums (if any)0%
Plinth25%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 4 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes45%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes2%
Street LightingYes1%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes1%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed55

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots55
Open Space55
BuildingOpen SpaceTotal
BUILDING NO 199
BUILDING NO 22323
BUILDING NO 32323

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,898 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Jul 2026
LandownerVillageDistrict
VIRENDRA KANADIAMumbai CityMumbai City
EHSANULLAH SALAMULLAH CHAUDHARYKurlaMumbai Suburban
NAVINCHANDRA HATHICHAND KANADIAKurlaMumbai Suburban

Approvals and building plan

Permissible FSI19891.74
Proposed, not sanctioned6,250 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAGASHI ROAD VIRAR WEST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYASH MILIND NANSI
EngineerGANESH RAGHUNATH AWHAD
Chartered AccountantD N FORGOES & CO
PartnerRole in project
SUGANDHI SWASTIK BUILDERS & DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000027754Dec 2024 → Dec 2026

Reason as filed by the promoterImpact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these materi

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed100

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ DEC 24 SWASTIK RESIDENCY.pdf4 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ DEC 24 SWASTIK RESIDENCY.pdf4 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ DEC 24 SWASTIK RESIDENCY.pdf4 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ DEC 24 SWASTIK RESIDENCY.pdf4 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ MARCH 24.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ JUNE 24.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ SEP 24.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ DEC 24.pdf3 Mar 2025
CERSAI detailsFile: CERSAI.pdf6 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: INDIDS.pdf6 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: SECURED.pdf6 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: SECURED.pdf6 Feb 2025
Declaration in FORM BFile: 6 FORM B.pdf5 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold June 24_compressed.pdf30 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold March 24_compressed.pdf30 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate- sugandhi swastik Dec 2024.pdf29 Jan 2025
Certificates of CA (Form 3)File: Form 3 - Sugandhi Swastik Dec 2024 - Building 1-5.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5, Audit Report (FY 2017-18) - Sugandhi Swastik.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate- sugandhi swastik Dec 2024.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5, Audit Report (FY 2018-19) - Sugandhi Swastik.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5, Audit Report (FY 2019-20) - Sugandhi Swastik.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5, Audit Report (FY 2020-21) - Sugandhi Swastik.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Dec 2024.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5, Audit Report (FY 2021-22) - Sugandhi Swastik.pdf29 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Form 5, Audit Report (FY 2017-18) - Sugandhi Swastik.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5, Audit Report (FY 2022-23) - Sugandhi Swastik.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5, Audit Report (FY 2023-24) - Sugandhi Swastik.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Sept 24.pdf28 Jan 2025
Proforma of Agreement for saleFile: 1 Proforma of AFS.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf27 Dec 2024
Certificates of CA (Form 3)File: Form - 3.pdf27 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - Quality Certificate - Sugandhi Swastik - 2020.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Certificate - Sugandhi Swastik - 2021.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Quality Certificate - Sugandhi Swastik - 2022.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Quality Certificate - Sugandhi Swastik - 2023.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Quality Certificate - Sugandhi Swastik - 2024.pdf27 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf9 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf9 Oct 2024
Certificates of CA (Form 3)File: Form 3.pdf9 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf9 Oct 2024
Certificates of CA (Form 3)File: Form 3.pdf9 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf9 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1.pdf13 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2.pdf13 Aug 2024
Certificates of CA (Form 3)File: Form -3.pdf13 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate - June 23.pdf17 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate - Sep 23.pdf17 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate - Dec 23.pdf17 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate 23.pdf30 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate 23.pdf25 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificates June -23.pdf25 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificates Sept -23.pdf25 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificates Dec -23.pdf25 Jan 2024
Certificates of CA (Form 3)File: Form 3 - CA Certificate 23_compressed.pdf25 Jan 2024
Certificates of CA (Form 3)File: Form 3 - CA Certificate - June 23_compressed.pdf25 Jan 2024
Certificates of CA (Form 3)File: Form 3 - CA Certificate - Sept 23_compressed.pdf25 Jan 2024
Certificates of CA (Form 3)File: Form 3 - CA Certificate - Dec 23_compressed.pdf25 Jan 2024
Details of encumbrances concerned to FinanceFile: Legal Encumbrances.pdf29 Mar 2023
Details of encumbrances concerned to LegalFile: Legal Encumbrances.pdf29 Mar 2023
Declaration about Commencement CertificateFile: Declaration About CC.pdf29 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate.pdf29 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate.pdf29 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate.pdf29 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate.pdf29 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate.pdf29 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate 18.pdf29 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate 19.pdf29 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate 20.pdf29 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate 21.pdf29 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate 22.pdf29 Mar 2023
Disclosure of sold/ booked inventoryFile: Discolsure of sold_compressed.pdf29 Mar 2023
CERSAI detailsFile: Affidavit Cum Declaration.pdf29 Mar 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate 18_compressed.pdf29 Mar 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate 19_compressed.pdf29 Mar 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate 20_compressed.pdf29 Mar 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate 21_compressed.pdf29 Mar 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate 22_compressed.pdf29 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate bank account.pdf29 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation.pdf29 Mar 2023

How this compares with Palghar

0%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 24 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SWASTIK RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Betegaon3,200+ in Palghar

2 kmSWASTIK RESIDENCYCompleted 14Lapsed / revoked 15Other 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 71 registered projects within 2 km.

Builder: SUGANDHI SWASTIK BUILDERS & DEVELOPERS

SUGANDHI SWASTIK BUILDERS & DEVELOPERS has 1 registration on MahaRERA, including SWASTIK RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if SWASTIK RESIDENCY is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SWASTIK RESIDENCY?

The registered promoter entity is SUGANDHI SWASTIK BUILDERS & DEVELOPERS, a partnership as per the filing. Its GSTIN 27ACLFS8495G1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SWASTIK RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SWASTIK RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SWASTIK RESIDENCY?

The professionals named in the filing: Architect: YASH MILIND NANSI; Engineer: GANESH RAGHUNATH AWHAD; Chartered Accountant: D N FORGOES & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWASTIK RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWASTIK RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWASTIK RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.