SWASTIK HEIGHTS WING - A
RG-MH-28974 · RERA P51700027365 · Last updated on MahaRERA portal: 2 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 9 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SWASTIK HEIGHTS WING - A is a Residential / Group Housing project by SWASTIK DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700027365 on 6 Dec 2020. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 9 months from the original filing. 104 of the 124 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameSWASTIK HEIGHTS WING - A
- TypeResidential / Group Housing
- Location
- EDEN PARK
- INDRALOK PHASE - 7
- BHAYANDER EAST
- Mira-Bhayandar (M Corp.)
- Thane
- 401105
- Pincode401105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700027365
- ReraGenie IDRG-MH-28974
Builder
- NameSWASTIK DEVELOPERS
- Entity typePartnership
- GSTIN27AEDFS7958A1ZU
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersNAGENDRA DWIVEDI, RITESH CHAURASIA, DEEPAK KISHANLAL JAIN
- Other registrations14 more →
- Completed2 of 15
- No longer live6 lapsed, de-registered or revoked
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on6 Dec 2020
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 30 Jun 2025)
- Buildings1 building record
- Documents filed68 files
Current status
Figures as on 2 Jun 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SWASTIK HEIGHTS WING - A | NA | 30 | 29 | 110 | 14 | 124 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
SWASTIK HEIGHTS WING - A: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 2 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed57
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ADARSH CONSULTANT |
| Engineer | TEJ'S CONSULTANTS |
| Engineer | DILIP MANUBHAI SHARMA |
| Chartered Accountant | ABHISHEK SURANA AND CO |
| Chartered Accountant | ABHISHEK SURANA & CO. |
| Chartered Accountant | P.R.KOTADIYA & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SWASTIK DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have completed construction work however waiting for OC and Society Handover for the same we required extension.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12501979 | Ravikant Ramprakash Upadhyay | SWASTIK DEVELOPERS | 17/06/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: form 1 31 03 2025.pdf | 2 Jun 2025 |
| Form 2File: form 2 31 03 2025.pdf | 2 Jun 2025 |
| Form 3File: FORM 3 SWASTIL 31032025.pdf | 2 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: 16 DISCLOSER 31032025.pdf | 2 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: 16 31032025.pdf | 2 Jun 2025 |
| Form 2A (FY 2021-2022)File: 2A M 2022.pdf | 2 Jun 2025 |
| Form 2A (FY 2022-2023)File: 2A M 2023.pdf | 2 Jun 2025 |
| Form 2A (FY 2023-2024)File: 2A M 2024.pdf | 2 Jun 2025 |
| Form 2A (FY 2024-2025)File: 2A M 2025.pdf | 2 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: 1 DISCLOSER 30062021.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 1 30062021.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 2 DISCLOSER 30092021.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 2 30092021.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 3 DISCLOSER 31122021.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 3 31122021.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 4 DISCLOSER 31032022.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 4 31032022.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 5 DISCLOSER 30062022.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 5 30062022.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 6 DISCLOSER 30092022.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 6 30092022.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 7 DISCLOSER 31122022.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 7 31122022.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 8 DISCLOSER 31032023.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 8 31032023.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 9 DISCLOSER 30062023.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 9 30062023.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 10 DISCLOSER 30092023.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 10 30092023.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 11 DISCLOSER 31122023.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 11 31122023.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 12 DISCLOSER 31032024.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 12 31032024.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 13 DISCLOSER 30062024.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 13 30062024.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 14 DISCLOSER 30092024.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 14 30092024.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 15 DISCLOSER 31122024.pdf | 31 May 2025 |
| Self-declaration of Quarterly ProgressFile: 15 31122024.pdf | 31 May 2025 |
| Form 5 (FY 2022-2023)File: Form 5 2023 Swastik.pdf | 31 May 2025 |
| Form 5 (FY 2023-2024)File: Form 5 2024 Swastik.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 12 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 12 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SWASTIK FORM 3_11zon.pdf | 12 Oct 2022 |
| Layout approvalFile: LAYOUT PLAN NEW.pdf | 23 Feb 2022 |
| Building plan approvalFile: FLOOR PLAN 1 NEW.pdf | 23 Feb 2022 |
| Building plan approvalFile: FLOOR PLAN 2 NEW.pdf | 23 Feb 2022 |
| Copy of the legal title reportFile: Swastk title new.pdf | 23 Feb 2022 |
| Details of encumbrancesFile: Swastik Encum New.pdf | 23 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN NEW.pdf | 23 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: FLOOR PLAN 1 NEW.pdf | 23 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: FLOOR PLAN 2 NEW.pdf | 23 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Swastik New CC.pdf | 23 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Swastik Form 1 New.pdf | 23 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Swastik Form 2 New.pdf | 23 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC DATED 20-06-20.pdf | 3 Dec 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Agreement and CC SWASTIK.pdf | 3 Dec 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Swastik.pdf | 1 Dec 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Swastik.pdf | 1 Dec 2020 |
| Layout approvalFile: LAYOUT PLAN SWASTIK.pdf | 28 Nov 2020 |
| Building plan approvalFile: BUILDING PLAN.pdf | 28 Nov 2020 |
| Copy of the legal title reportFile: TITLE SEARCH SWASTIK_compressed.pdf | 28 Nov 2020 |
| Details of encumbrancesFile: ENCUMBRANC.pdf | 28 Nov 2020 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN SWASTIK.pdf | 28 Nov 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN.pdf | 28 Nov 2020 |
| Declaration in FORM BFile: FORM B SWASTIK_compressed.pdf | 28 Nov 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SWASTIK.pdf | 28 Nov 2020 |
| Proforma of Allotment letterFile: RERA-AGR- SWASTIK HEIGHTS - 24112020.pdf | 28 Nov 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 14 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 68 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SWASTIK HEIGHTS WING - A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BHAYANDER EAST7,600+ in Thane
Filed coordinates, straight-line distance. 208 registered projects within 2 km.
VIHANG LUXURIA
REYANSHP REALTY LLP
ESQUIRE
JP INFRA&SALASAR BUILDCON LLP
ANJANI BLISS
ANJANI KUMAR COMPANY PRIVATE LIMITED
SHREE BALAJI EMPIRE
SHUBHAM HOUSING
SMIT VISTA
SMIT MEGASTRUCTURES
INDRA NEEL
SONAM SPARK INFRA PRIVATE LIMITED
See every Thane project, with the district possession charts
Builder: SWASTIK DEVELOPERS
SWASTIK DEVELOPERS has 15 registrations on MahaRERA, including INDRAPRASTH COMPLEX and SIGNATURE BUSINESS PARK. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that SWASTIK HEIGHTS WING - A shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SWASTIK HEIGHTS WING - A is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SWASTIK HEIGHTS WING - A?
The registered promoter entity is SWASTIK DEVELOPERS, a partnership as per the filing. Its GSTIN 27AEDFS7958A1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SWASTIK HEIGHTS WING - A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SWASTIK HEIGHTS WING - A?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SWASTIK HEIGHTS WING - A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SWASTIK HEIGHTS WING - A?
The professionals named in the filing: Architect: ADARSH CONSULTANT; Engineer: TEJ'S CONSULTANTS; Engineer: DILIP MANUBHAI SHARMA; Chartered Accountant: ABHISHEK SURANA AND CO; Chartered Accountant: ABHISHEK SURANA & CO.; Chartered Accountant: P.R.KOTADIYA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SWASTIK HEIGHTS WING - A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback