Home / Browse projects / Satara, Maharashtra / SWAPNDEEP

Registered No litigation declared Residential / Group Housing project

SWAPNDEEP

By APURVA CONSTRUCTION

RG-MH-26470 · RERA P52700014600 · Last updated on MahaRERA portal: 23 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 78 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Jun 2028Possession promisedmoved 78 months from the original
16 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 98%
67 of 74Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 126 documents Report an error

SWAPNDEEP is a Residential / Group Housing project by APURVA CONSTRUCTION in Satara, Maharashtra, registered with MahaRERA as P52700014600 on 15 Dec 2017. Possession is promised by 30 Jun 2028. The completion date has moved by 78 months from the original filing. 7 of the 74 units on this registration are recorded sold or booked, and 16 of 44 construction stages are filed complete.

At a glance

Project

  • NameSWAPNDEEP
  • TypeResidential / Group Housing
  • Location
    • Satara Pandarpur Highway
    • Lahsurne
    • Lhasurne
    • Koregaon
    • Satara
    • 415501
  • Pincode415501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700014600
  • ReraGenie IDRG-MH-26470

Builder

  • NameAPURVA CONSTRUCTION
  • Entity typePartnership
  • PartnerMangesh Vijay Shinde

Key dates

this monthRegisteredDec 2017First promiseDec 2021Revised toJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Dec 2017
  • Promised completion30 Jun 2028
  • Revised completionRevised to 30 Jun 2028 (originally 30 Dec 2021)
  • Buildings4 building records
  • Documents filed126 files

Current status

9%7 of 74 units booked
92.2%Work done, per cost certificate

Figures as on 23 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA55161632
WING CNA64141226
WING DNA6416016
WING BNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 98%.

WING A40%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING C84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
WING D84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
WING B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes80%

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Closed/Covered3
Open Space36
BuildingClosed/CoveredOpen SpaceTotal
WING C101
WING D13637
WING B101

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,213 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Mar 2026
LandownerVillageDistrict
DIPAK SOPANRAO GHADAGEKoregaon (CT)Satara
SANDEEP BABAN GHADAGELhasurneSatara

Approvals and building plan

Sanctioning authorityNagar Palika Satara
Permissible FSI3098.63
Proposed, not sanctioned2,649 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAbanjani Survey Number 257 Plot Number 2 Bhosale Mala G D Tapase Marg Satara 415001
Estimated costRs 7.27 cr
Cost incurredRs 6.70 cr
Work done92.16%
BuildingWingEstimatedIncurred
-NARs 2.60 crRs 2.47 cr
WING ANARs 1.56 crRs 1.00 cr
WING CNARs 1.56 crRs 1.62 cr
WING DNARs 1.56 crRs 1.62 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHOK GAIKWAD
EngineerRAMDAS JAGTAP jagtap
EngineerVIJAY H SHINDE
Chartered AccountantZoheb Nasurhusen Mulani
Chartered AccountantNikhil Vilas Raut
Chartered AccountantM K T S K & CO
PartnerRole in project
APURVA CONSTRUCTION-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700010987Dec 2021 → Jun 2025

Reason as filed by the promoterDue to Covid-19 situation and Lockdown we couldn't complete the said project. Hence, it is requested to increase registration period till 30 June 2025.

EA26092517954Dec 2021 → Jun 2028

Reason as filed by the promoterwe have complete 2 building out of three building we want this Extension time for complete building and hand over flats to allotiess

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Nov 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Nov 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Nov 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed126

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: 7 Form 2A 2023 24.pdf23 Jun 2026
Form 2A (FY 2024-2025)File: 8 Form 2A 2024 25.pdf23 Jun 2026
Form 2A (FY 2025-2026)File: 9 Form 2A 2025 26.pdf23 Jun 2026
Form 2A (FY 2021-2022)File: 5 Form 2A 2021 22.pdf22 Jun 2026
Form 2A (FY 2022-2023)File: 6 Form 2A 2022 23.pdf22 Jun 2026
Form 2A (FY 2017-2018)File: 1 Form 2A 2017 18.pdf19 Jun 2026
Form 2A (FY 2018-2019)File: 2 Form 2A 2018 19.pdf19 Jun 2026
Form 2A (FY 2019-2020)File: 3 Form 2A 2019 20.pdf19 Jun 2026
Form 2A (FY 2020-2021)File: 4 Form 2A 2020 21.pdf19 Jun 2026
Withdrawal Update Form 1File: 26. 2025-26 Q4 Withdrawal Application Form1..pdf6 Apr 2026
Withdrawal Update Form 2File: 26. 2025-26 Q4 Withdrawal Application Form2..pdf6 Apr 2026
Withdrawal Update Form 3File: Form 3 Q4 2025-26.pdf6 Apr 2026
Withdrawal Update Form 1File: Form 1 Q3 FY 2025-26.pdf19 Jan 2026
Withdrawal Update Form 2File: Form 2 Q3 FY 2025-26.pdf19 Jan 2026
Withdrawal Update Form 3File: Form 3 Q3 FY 2025-25.pdf19 Jan 2026
Withdrawal Update Form 1File: form 1.PDF30 Dec 2025
Withdrawal Update Form 2File: form 2.PDF30 Dec 2025
Withdrawal Update Form 3File: form 3.PDF30 Dec 2025
Form 1File: form 1 Architect certi 17-18.PDF16 Dec 2025
Form 2File: form 2 engineer certi 17-18.PDF16 Dec 2025
Form 3File: form3 FY17-18.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 Architect certi 17-18.PDF16 Dec 2025
Form 2File: form 2 engineer certi 17-18.PDF16 Dec 2025
Form 3File: form3 FY17-18.PDF16 Dec 2025
Form 1File: form 1 ARCHITECH CERTI 18-19.PDF16 Dec 2025
Form 2File: form 2 engineers cer18-19.PDF16 Dec 2025
Form 3File: form 3CA certificate 18-19.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 ARCHITECH CERTI 18-19.PDF16 Dec 2025
Form 2File: form 2 engineers cer18-19.PDF16 Dec 2025
Form 3File: form 3CA certificate 18-19.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 ARCHITECH CERTI 18-19.PDF16 Dec 2025
Form 2File: form 2 engineers cer18-19.PDF16 Dec 2025
Form 3File: form 3CA certificate 18-19.PDF16 Dec 2025
Form 1File: form 1 ARCHITECH CERTI 18-19.PDF16 Dec 2025
Form 2File: form 2 engineers cer18-19.PDF16 Dec 2025
Form 3File: form 3CA certificate 18-19.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 ARCHITECH CERTI 18-19.PDF16 Dec 2025
Form 2File: form 2 engineers cer18-19.PDF16 Dec 2025
Form 3File: form 3CA certificate 18-19.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 architect certi 19-20.PDF16 Dec 2025
Form 2File: form 2 engineer cer 19-20.PDF16 Dec 2025
Form 3File: form 3 CA cerificat 19-20.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 architect certi 19-20.PDF16 Dec 2025
Form 2File: form 2 engineer cer 19-20.PDF16 Dec 2025
Form 3File: form 3 CA cerificat 19-20.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 architect certi 19-20.PDF16 Dec 2025
Form 2File: form 2 engineer cer 19-20.PDF16 Dec 2025
Form 3File: form 3 CA cerificat 19-20.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 architec certificate march20 sept 20.PDF16 Dec 2025
Form 2File: form 2 engineer cerificat march 20 sept 20.PDF16 Dec 2025
Form 3File: form 3CA certificate march 20 to sept 20.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 architec certificate march20 sept 20.PDF16 Dec 2025
Form 2File: form 2 engineer cerificat march 20 sept 20.PDF16 Dec 2025
Form 3File: form 3CA certificate march 20 to sept 20.PDF16 Dec 2025
Form 1File: form 1 architec certificate march20 sept 20.PDF16 Dec 2025
Form 2File: form 2 engineers certificate20.PDF16 Dec 2025
Form 3File: form 3 CA cerificat 19-20.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 architec certificate march20 sept 20.PDF16 Dec 2025
Form 2File: form 2 engineer cerificat march 20 sept 20.PDF16 Dec 2025
Form 3File: form 3CA certificate march 20 to sept 20.PDF16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD 12-17 TO 9-21.pdf16 Dec 2025
Form 1File: form 1 architec certificate march20 sept 20.PDF16 Dec 2025
Form 2File: form 2 engineer cerificat march 20 sept 20.PDF16 Dec 2025
Form 3File: form 3CA certificate march 20 to sept 20.PDF16 Dec 2025
Form 1File: form 1 architec certificate march20 sept 20.PDF16 Dec 2025
Form 2File: form 2 engineer cerificat march 20 sept 20.PDF16 Dec 2025

How this compares with Satara

9%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one moved by 78 months
35%of Satara registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep SWAPNDEEP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Lahsurne1,100+ in Satara

Builder: APURVA CONSTRUCTION

APURVA CONSTRUCTION has 1 registration on MahaRERA, including SWAPNDEEP. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if SWAPNDEEP is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SWAPNDEEP?

The registered promoter entity is APURVA CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SWAPNDEEP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SWAPNDEEP?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SWAPNDEEP?

The professionals named in the filing: Architect: ASHOK GAIKWAD; Engineer: RAMDAS JAGTAP jagtap; Engineer: VIJAY H SHINDE; Chartered Accountant: Zoheb Nasurhusen Mulani; Chartered Accountant: Nikhil Vilas Raut; Chartered Accountant: M K T S K & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWAPNDEEP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWAPNDEEP. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWAPNDEEP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.