ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / SUNSHINE SQUARE

Registration lapsed No litigation declared Others project

SUNSHINE SQUARE

By VIKRAMADITYA REALTY PRIVATE LIMITED

RG-MH-59783 · RERA P52000050875 · Last updated on MahaRERA portal: 8 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
5 of 11Construction stages donefurthest along: External plumbing and external plaster, 90%
17 of 25Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

SUNSHINE SQUARE is a Others project by VIKRAMADITYA REALTY PRIVATE LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000050875 on 15 May 2023. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 18 months from the original filing. 8 of the 25 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameSUNSHINE SQUARE
  • TypeOthers
  • Location
    • PUSHPAK
    • KARANJADE
    • NAVI MUMBAI
    • Karanjade
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000050875
  • ReraGenie IDRG-MH-59783

Builder

  • NameVIKRAMADITYA REALTY PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsADITYA VIKRAM SINGH, SANDHYA ADITYA SINGH

Key dates

4 months past promisethis monthRegisteredMay 2023First promiseDec 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 May 2023
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed48 files

Current status

32%8 of 25 units booked

Figures as on 8 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SUNSHINE SQUARENA5521425

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.

SUNSHINE SQUARE: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed13

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots13
Closed/Covered13

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area400 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on31 Dec 2025
LandownerVillageDistrict
SHRI. GANGARAM GOVARYA PATILPargaonRaigarh
SHRI. NAVNATH GANGARAM PATILPargaonRaigarh

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI959.57
Proposed, not sanctioned960 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNAVI MUMBAI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectACKRUTI ARCHITECTS & INTERIOR DISGNERS
EngineerB S SUKTHANKAR & ASSOCIATES
Chartered AccountantJ B PATEL & ASSOCIATES
PartnerRole in project
VIKRAMADITYA REALTY PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA07012619341Dec 2024 → Jun 2026

Reason as filed by the promoterUnforeseen delays due to supply chain disruptions, labour shortages, or delays in the procurement of essential materials that have impacted the project timeline. These delays are beyond the control of the developer, and additional time is required to ensure that the project meets the necessary quality standards and complies with safety regulations.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: form 1.pdf8 Jan 2026
Form 2File: form 2.pdf8 Jan 2026
Form 3File: Form-3.pdf8 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf8 Jan 2026
Self-declaration of Quarterly ProgressFile: Self-Declaration for Quaterly Progress SAI SAVLI.pdf8 Jan 2026
Form 2A (FY 2023-2024)File: Form 2A 23-24 Vikramaditya.pdf8 Jan 2026
Form 5 (FY 2023-2024)File: form 5 with declaration.pdf8 Jan 2026
Declaration in FORM BFile: Form B.pdf22 Apr 2025
Other - TechnicalFile: Pert Chart.pdf22 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24 Vikramaditya.pdf7 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Dec 2023.pdf3 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 March 2024.pdf3 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 June 2024.pdf3 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Sep 2024.pdf3 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Dec 2024 lastest .pdf3 Apr 2025
Other - TechnicalFile: Annexure-A2.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sunshine Square Work Completetion.pdf28 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - New.pdf27 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept.pdf27 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf27 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf27 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration.pdf27 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration.pdf27 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure.pdf7 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure.pdf7 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Sunshine Square1.pdf28 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Sunshine Square_- sandhya.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (1).pdf12 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Sunshine Square- aditya.pdf12 Apr 2023
Declaration in FORM BFile: Form B of promoter (1).pdf23 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate bank account_1 (2 files merged).pdf22 Mar 2023
Building plan approvalFile: PLAN - SIGN_compressed.pdf27 Feb 2023
Details of encumbrances concerned to FinanceFile: SELF DECLARATION ABOUT ENCUMBARNCES to fianace.pdf27 Feb 2023
Details of encumbrances concerned to FinanceFile: TO WHOMSOREVER IT MAY CONCERN.pdf27 Feb 2023
Details of encumbrances concerned to LegalFile: SELF DECLARATION ABOUT ENCUMBARNCES to fianace.pdf27 Feb 2023
Details of encumbrances concerned to LegalFile: TO WHOMSOREVER IT MAY CONCERN.pdf27 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN - SIGN_compressed.pdf27 Feb 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT.pdf27 Feb 2023
CERSAI detailsFile: undertaking about cersai.pdf27 Feb 2023
Deviation Report with respect to Allotment letterFile: NO DEVIATION FORM MODEL.pdf27 Feb 2023
Deviation Report with respect to model copy of AgreementFile: NO DEVIATION FORM AGREEMENT.pdf27 Feb 2023
Layout approvalFile: PLAN - SIGN_compressed.pdf23 Feb 2023
PAN CardFile: Company Pan.pdf23 Feb 2023
Copy of the legal title reportFile: Title Report.pdf23 Feb 2023
Copy of Layout Approval (in case of layout)File: PLAN - SIGN_compressed.pdf23 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf23 Feb 2023
Proforma of Agreement for saleFile: Model Agreement.pdf23 Feb 2023
Proforma of Allotment letterFile: Alllotement letter.pdf23 Feb 2023

How this compares with Raigarh

32%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 18 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUNSHINE SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KARANJADE, NAVI MUMBAI5,900+ in Raigarh

2 kmSUNSHINE SQUARECompleted 126Lapsed / revoked 49Other 103Dot size: filed unitsN

Filed coordinates, straight-line distance. 278 registered projects within 2 km.

Builder: VIKRAMADITYA REALTY PRIVATE LIMITED

VIKRAMADITYA REALTY PRIVATE LIMITED has 1 registration on MahaRERA, including SUNSHINE SQUARE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that SUNSHINE SQUARE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SUNSHINE SQUARE is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUNSHINE SQUARE?

The registered promoter entity is VIKRAMADITYA REALTY PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUNSHINE SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SUNSHINE SQUARE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUNSHINE SQUARE?

The professionals named in the filing: Architect: ACKRUTI ARCHITECTS & INTERIOR DISGNERS; Engineer: B S SUKTHANKAR & ASSOCIATES; Chartered Accountant: J B PATEL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUNSHINE SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUNSHINE SQUARE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUNSHINE SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.