Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
SUNPURE HOMES is a Residential/Group Housing project by M K INFRAHOLDINGS PRIVATE LIMITED in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/171017/000557 on 17 Oct 2017. Possession is promised by 30 Apr 2021. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameSUNPURE HOMES
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- RERA no.PRM/KA/RERA/1268/378/PR/171017/000557
- ReraGenie IDRG-KA-00986
Builder
- NameM K INFRAHOLDINGS PRIVATE LIMITED
- Entity typeCompany
- CINU70102KA2011PTC058444
- Authorized SignatoryMOHAMMED IMRAN KHAN
- DirectorMOHAMMED IMRAN KHAN
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on17 Oct 2017
- Promised completion30 Apr 2021
- Revised completionRevised to 30 Apr 2021 (originally 31 Jul 2020)
- Buildings1 building record
- Documents filed45 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SUNPURE HOMES | - | - | - | 26 | 0 | 26 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | Yes | - |
| Power Backup | No | Not applicable |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | No | Not applicable |
| Staircases and Lift lobbies, corridor,lobbies, corridor | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed45
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/171017/000557 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: MKIH-MOA.pdf | - |
| Approved Layout Plan | - |
| Approved Building Plan | - |
| Approved Layout Plan | - |
| Sale Deed | - |
| Agreement of Sale | - |
| Com-Land Documents-Belvadi | - |
| Approved Section of Building | - |
| Area Development Plan | - |
| Sale Deed | - |
| sunpure-e-brochure-ver1 | - |
| NOC | - |
| Description | - |
| EC | - |
| Khata | - |
| Conversion certificate | - |
| CESCOM | - |
| Balance Sheet 2015 - 2016File: BS 2015-16.pdf | - |
| Balance Sheet 2014 - 2015File: BS 2014-15.pdf | - |
| Balance Sheet 2013 - 2014File: BS 2013-14.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: PL 2015-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: PL 2014-15.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: pl 201-14.pdf | - |
| Director's Report 2015 - 2016File: compressed_DIRECTORS REPORT M K INFRA 2014-15.pdf | - |
| Director's Report 2014 - 2015File: compressed_Audit Report 2015-16.pdf | - |
| Director's Report 2013 - 2014File: 2013-14 Director.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash Flow.pdf | - |
| Cash Flow Statement 2014 - 2015File: Cash Flow.pdf | - |
| Auditor's Report 2015 - 2016File: compressed_Audit Report 2015-16.pdf | - |
| Auditor's Report 2014 - 2015File: Infra Audit Report 14-15.pdf | - |
| Auditor's Report 2013 - 2014File: 2013-14 Auditor.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: itr 2015-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: itr 2014-15.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITV 2013-14.pdf | - |
| Affidavit | - |
| Prospectus/BrochureFile: sunpure-e-brochure-ver1.pdf | - |
| Advertisement Copy 1File: sunpure-e-brochure-ver1.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1268_378_PR_171017_000557 (2).xlsx | - |
| Occupancy CertificateFile: CR of all villas.pdf | - |
| Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Deed of Declaration Association Formation compre.pdf | - |
| Details of undivided share of land handed over to the association of allotteesFile: Deed of Declaration Association Formation compre.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Architect Certificate Form 5 for completion.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: CA Certificate Form 4CC for completion.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Completion Affidavit SPH.pdf | - |
| fORM 6File: Engineer Certificate From 6 for completion.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep SUNPURE HOMES on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: M K INFRAHOLDINGS PRIVATE LIMITED
M K INFRAHOLDINGS PRIVATE LIMITED has 1 registration on RERA Karnataka, including SUNPURE HOMES. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if SUNPURE HOMES is delayed beyond 30 Apr 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SUNPURE HOMES?
The registered promoter entity is M K INFRAHOLDINGS PRIVATE LIMITED, a company as per the filing. Its CIN U70102KA2011PTC058444 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SUNPURE HOMES?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in SUNPURE HOMES?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback