SUMAN VATIKA
By SUNIL VISHWAMBARNATH TIWARI
RG-MH-00903 · RERA P50500012082 · Last updated on MahaRERA portal: 15 Jun 2019
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 52 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 42 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SUMAN VATIKA is a Residential / Group Housing project by SUNIL VISHWAMBARNATH TIWARI in Nagpur, Maharashtra, registered with MahaRERA as P50500012082 on 1 Sep 2017. Possession was promised by 30 Jun 2022 and is now 52 months past that date. The completion date has moved by 42 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameSUMAN VATIKA
- TypeResidential / Group Housing
- Location
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440026
- Pincode440026
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500012082
- ReraGenie IDRG-MH-00903
Builder
- NameSUNIL VISHWAMBARNATH TIWARI
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Sep 2017
- Promised completion30 Jun 2022
- Revised completionRevised to 30 Jun 2022 (originally 30 Dec 2018)
- Buildings1 building record
- Documents filed14 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SUMAN VATIKA APPARTMENT | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Jun 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 50%.
SUMAN VATIKA APPARTMENT: 54% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 45% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 15 Jun 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 30% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MRS SHWETA DESHPANDE |
| Architect | SHWETA DESHPANDE |
| Engineer | MR AASHISH SONI |
| Chartered Accountant | Amit Gudadhe |
| Partner | Role in project |
|---|---|
| SUNIL VISHWAMBARNATH TIWARI | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs we have being struggling since last few months as my earning have dropped drastically due to heavy recession witnessed by global economy being into reality sector. I had tried my best to keep the wheel moving but was totally helpless in last few months which resulted in bankers recovery action initiated and work was stopped by them. Due to which existing customers moved to court and work was totally stopped. Now the things are in control and construction work is speadly moving on and will be completed on or before 30/12/2019
Reason as filed by the promoterAs our project was financed by Religare Finvest Ltd. and due to there management decision finance company was not giving NOC for further construction and sale. Unless NOC is not received from bank we can not sell or construct. After order of DRT we have received permission for construction. Court Commissioner is appointed by DRT and every month work progress report is submitted by the commissioner and now project is moving properly. From the month of march due to pendamic Covid -19 work is stop due to non availability of material and labour. Work is completed about 85% and will be completed on
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC004000000010066 | Kanwar Sain | Panchvati Builderp | 15/06/2018 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed14
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 5)File: 00.pdf | 15 Jun 2019 |
| Layout approvalFile: LAYOUT MAP.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: AKHIV PATRIKA.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LAYOUT MAP.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: FORM B.pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Proforma allotment letter.pdf | 30 Jul 2017 |
| Building plan approvalFile: Sanction Map.pdf | 29 Jul 2017 |
| PAN CardFile: pancard tiwari sir.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: PNB project approved letter.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Sanction Map.pdf | 29 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Building Permit.pdf | 29 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 14 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SUMAN VATIKA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nagpur (M Corp.)2,800+ in Nagpur
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
Swapnapurtee - A Project by NMC
SANDEEP DWELLERS PVT. LTD.
KARAN KOTHARI BUSINESS PARK SHOPPING VILLAGE
KARAN KOTHARI BUSINESS PARK PRIVATE LIMITE
HBA PARK PHASE-I
HBA CONSTRUCTION COMPANY PVT.LTD
OAK SHANTINIKETAN
OAK Constructions
RAI CREST
RAI UDYOG UNITY MEDISCIENCE PRIVATE LIMITE
BHIL CITY 3
MOHAN BAPURAO MAKDE
See every Nagpur project, with the district possession charts
Builder: SUNIL VISHWAMBARNATH TIWARI
SUNIL VISHWAMBARNATH TIWARI has 1 registration on MahaRERA, including SUMAN VATIKA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What does it mean that SUMAN VATIKA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SUMAN VATIKA is delayed beyond 30 Jun 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SUMAN VATIKA?
The registered promoter entity is SUNIL VISHWAMBARNATH TIWARI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SUMAN VATIKA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SUMAN VATIKA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SUMAN VATIKA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SUMAN VATIKA?
The professionals named in the filing: Architect: MRS SHWETA DESHPANDE; Architect: SHWETA DESHPANDE; Engineer: MR AASHISH SONI; Chartered Accountant: Amit Gudadhe. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUMAN VATIKA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.