ReraGenieLog inGet a buyer report

Home / Browse projects / Sindhudurg, Maharashtra / Sulabha Plaza

Registered No litigation declared Mixed project

Sulabha Plaza

By Laxmi Developers

RG-MH-74439 · RERA PM1310002501961 · Last updated on MahaRERA portal: 30 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 13 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
2 of 8Construction stages donefurthest along: Slabs of Super Structure, 67%
21 of 23Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 12 documents Report an error

Sulabha Plaza is a Mixed project by Laxmi Developers in Sindhudurg, Maharashtra, registered with MahaRERA as PM1310002501961 on 31 Dec 2025. Possession is promised by 31 Dec 2028. 2 of the 23 units on this registration are recorded sold or booked, and 2 of 8 construction stages are filed complete.

At a glance

Project

  • NameSulabha Plaza
  • TypeMixed
  • Location
    • Kelbai Mandir Road
    • Kudal
    • Kudal (CT)
    • Sindhudurg
    • 416520
  • Pincode416520
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PM1310002501961
  • ReraGenie IDRG-MH-74439

Builder

  • NameLaxmi Developers
  • Entity typePartnership
  • PartnersMohan Vasudev Hundare, Umesh Shashikant Dabholkar
  • Other registrations13 more →
  • Completed5 of 14
  • No longer live6 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredDec 2025PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Dec 2025
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed12 files

Current status

9%2 of 23 units booked
22.6%Work done, per cost certificate

Figures as on 30 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sulabha PlazaNA6620323

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 8 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 67%.

Sulabha Plaza: 33% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed27

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots27
Stilt / Ground27

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area611 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Nov 2025
LandownerVillageDistrict
Gangaram Shankar AnavkarKudal (CT)Sindhudurg

Approvals and building plan

Permissible FSI1342.13
Proposed, not sanctioned1,342 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPRATHAM APARTMENT, NEAR KUDAL HIGH SCHOOL, KUDAL, DIST SINDHUDURG - 416520.
Estimated costRs 3.05 cr
Cost incurredRs 69.06 lakh
Work done22.64%
BuildingWingEstimatedIncurred
Sulabha PlazaNARs 2.51 crRs 69.06 lakh
-NARs 53.92 lakh-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRupesh Narayan Tawate
EngineerRupesh Narayan Tawate
Chartered AccountantSagar Gajanan Teli
PartnerRole in project
Laxmi Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalNot on the file

    The planning authority's approval of how the plots and buildings sit on the land.

  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Nov 2025
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed12

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architects Certificate Mar26.pdf30 May 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Mar26.pdf30 May 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate Mar26.pdf30 May 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Mar26.pdf30 May 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Mar26.pdf30 May 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Mar26.pdf30 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Mar26.pdf30 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Mar26.pdf30 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Mar26.pdf30 May 2026
Declaration and undertaking (Annexure A)File: Annexure A Declaration.pdf19 Dec 2025
Building plan approval or NA orderFile: 10 NA Order.pdf15 Nov 2025
Building plan approvalFile: Sanction Plan.pdf15 Nov 2025

How this compares with Sindhudurg

9%of this project is bookeddistrict median 15%
21%of Sindhudurg projects moved their completion datethis one has not
30%of Sindhudurg registrations have lapsed or been cancelledthis one is on the register

Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.

Keep Sulabha Plaza on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kudal530+ in Sindhudurg

2 kmSulabha PlazaCompleted 6Lapsed / revoked 5Other 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 31 registered projects within 2 km.

Builder: Laxmi Developers

LAXMI DEVELOPERS has 14 registrations on MahaRERA, including LAXMI VISHNUPURAM and KUTUMB. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Sindhudurg district page.

Frequently asked questions

What are my rights if Sulabha Plaza is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sulabha Plaza?

The registered promoter entity is Laxmi Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sulabha Plaza?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sulabha Plaza?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sulabha Plaza?

The professionals named in the filing: Architect: Rupesh Narayan Tawate; Engineer: Rupesh Narayan Tawate; Chartered Accountant: Sagar Gajanan Teli. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sulabha Plaza?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sulabha Plaza. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sulabha Plaza to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.