Home / Browse projects / Palghar, Maharashtra / SUKHKARTA

Registered No litigation declared Residential / Group Housing project

SUKHKARTA

By SUKHKARTA DEVELOPERS

RG-MH-66797 · RERA P99000007883 · Last updated on MahaRERA portal: 6 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 69 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 69 months from the original
25 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 5%
32 of 93Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

SUKHKARTA is a Residential / Group Housing project by SUKHKARTA DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000007883 on 18 Aug 2017. Possession is promised by 31 Mar 2027. The completion date has moved by 69 months from the original filing. 61 of the 93 units on this registration are recorded sold or booked, and 25 of 33 construction stages are filed complete.

At a glance

Project

  • NameSUKHKARTA
  • TypeResidential / Group Housing
  • Location
    • samelpada
    • nallasopara west
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401203
  • Pincode401203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000007883
  • ReraGenie IDRG-MH-66797

Builder

  • NameSUKHKARTA DEVELOPERS
  • Entity typePartnership
  • GSTIN27ACOFS4451P1ZA
  • PartnersYashika Yatin Dhage, ANKIT RAJESH DHAGE, SHAURYA YATIN DHAGE, RAJESH KAMLAKAR DHAGE
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseJun 2021Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Aug 2017
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Jun 2021)
  • Buildings3 building records
  • Documents filed60 files

Current status

66%61 of 93 units booked
75.6%Work done, per cost certificate

Figures as on 6 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA3337643
WING BNA6525025
WING CNA5525025

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

25 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 5%.

WING A46%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3
BuildingClosed/CoveredTotal
WING A11
WING B11
WING C11

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,750 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Mar 2026

Approvals and building plan

Sanctioning authorityVASAI VIRAR CITY MUNICIPAL CORPORATION
Permissible FSI1750.0
Proposed, not sanctioned1,750 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFRENY ARCADE SAMEL PADA NALASOPARA WEST TAL VASAI DIST PALGHAR PIN401203
Estimated costRs 11.65 cr
Cost incurredRs 8.81 cr
Work done75.61%
BuildingWingEstimatedIncurred
WING ANARs 5.85 crRs 3.80 cr
WING BNARs 3.16 crRs 3.16 cr
-NARs 1.59 crRs 79.35 lakh
WING CNARs 1.05 crRs 1.05 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHIMESH GUPTA AND ASSOCIATES
EngineerSHILPLEKHA ASSOCIATES
Chartered AccountantDEEP THAKKAR
PartnerRole in project
SUKHKARTA DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000010590Jun 2021 → Jun 2022

Reason as filed by the promoterThe project was delayed as revised CC received late from the competent authority.

EXT99000013890Jun 2021 → Mar 2026

Reason as filed by the promoterIncrease in FSI.

EA09042620588Jun 2021 → Mar 2027

Reason as filed by the promoterReason for Delay is due to Increase in FSI and revision of CC for Awing in 2024. Also the Work of Wing C and Wing B is completed 100% and Part OC is already Taken for both the wing. Attaching herewith the Revised CC Copy for your reference below. Kindly allow us time till the month of Dec-26.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect certificate Mar-26.pdf6 May 2026
Withdrawal Update Form 2File: Form 2 Engineer Mar-26.pdf6 May 2026
Withdrawal Update Form 3File: Form 3 - Sukhkarata Developers Mar-26.pdf6 May 2026
Form 5 (FY 2024-2025)File: Form 5 24-25 Sukhkarta RERA.pdf6 May 2026
Form 2A (FY 2024-2025)File: Fom-2A 2024-25 signed.pdf5 May 2026
Form 2A (FY 2025-2026)File: Fom-2A 2025-26 Signed.pdf5 May 2026
Commencement certificateFile: Sukhkarta Updated CC Latest 2024_compressed.pdf8 Apr 2026
Form 1File: Archirtect Certificate.pdf8 Apr 2026
Form 2File: Form 2 Sep24.pdf8 Apr 2026
Form 3File: Form 3 Sukhkarta Sep-24.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: Form 3 Sukhkarta Sep-24.pdf8 Apr 2026
Form 1File: Form-1 Q3 FY24-25.pdf8 Apr 2026
Form 2File: Form-2 Q3 FY 24-25 1.pdf8 Apr 2026
Form 3File: FORM 3 SUKHARATA Dec-24.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: FORM 3 SUKHARATA Dec-24.pdf8 Apr 2026
Form 1File: Form - 1.pdf8 Apr 2026
Form 2File: Form - 2.pdf8 Apr 2026
Form 3File: Form 3 - Sukhkarata Developers Mar-25.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: Form 3 - Sukhkarata Developers Mar-25.pdf8 Apr 2026
Withdrawal Update Form 1File: Combined2.pdf8 Apr 2026
Withdrawal Update Form 1File: FORM 1 June 25.pdf8 Apr 2026
Withdrawal Update Form 1File: FORM 1 June 25.pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 rera 2026.pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 Apr-June 25.pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 Sep25.pdf8 Apr 2026
Withdrawal Update Form 3File: CA-CERT-.pdf8 Apr 2026
Withdrawal Update Form 3File: Form 3 - Sukhkarata Developers June-25.pdf8 Apr 2026
Withdrawal Update Form 3File: Form 3 - Sukhkarata Developers Sep-25.pdf8 Apr 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archirtect Certificate.pdf23 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Q3 FY24-25.pdf23 Jan 2025
Certificates of CA (Form 3)File: Form 3 Sukhkarta Sep-24.pdf23 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: fORM 2.pdf23 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Q3 FY 24-25 1.pdf23 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sep24.pdf23 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Sukhkarta Form 5 Signed.pdf31 May 2023
Commencement Certificates / NA Order for plotted developmentFile: sukhkarta updated CC_compressed.pdf16 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Quality Assurance Certificate.pdf27 Oct 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY (BUILDING WISE) latest.pdf27 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 17-18.pdf27 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf27 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf27 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf27 Oct 2021
Declaration about Commencement CertificateFile: CC declaration.pdf31 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Quality Assurance Certificate.pdf31 Jul 2021
Building plan approvalFile: Combined.pdf31 Jul 2017
Layout approvalFile: Blue Piint.pdf31 Jul 2017
PAN CardFile: Pan Card.pdf31 Jul 2017
Copy of the legal title reportFile: Combined.pdf31 Jul 2017
Copy of the legal title reportFile: Combined2.pdf31 Jul 2017
Details of encumbrancesFile: Ecambarance.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Blue Piint.pdf31 Jul 2017
Building Plan Approval (IOD)File: Combined.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Combined.pdf31 Jul 2017
Declaration in FORM BFile: Form B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Combined1.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Combined2.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Combined.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA-CERT-.pdf31 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Draft (1).pdf31 Jul 2017
Proforma of Allotment letterFile: Adrrement.pdf31 Jul 2017

How this compares with Palghar

66%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 69 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUKHKARTA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near nallasopara west3,200+ in Palghar

2 kmSUKHKARTACompleted 35Lapsed / revoked 25Other 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 128 registered projects within 2 km.

Builder: SUKHKARTA DEVELOPERS

SUKHKARTA DEVELOPERS has 2 registrations on MahaRERA, including SUKHKARTA and Shivalay. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if SUKHKARTA is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUKHKARTA?

The registered promoter entity is SUKHKARTA DEVELOPERS, a partnership as per the filing. Its GSTIN 27ACOFS4451P1ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUKHKARTA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SUKHKARTA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUKHKARTA?

The professionals named in the filing: Architect: HIMESH GUPTA AND ASSOCIATES; Engineer: SHILPLEKHA ASSOCIATES; Chartered Accountant: DEEP THAKKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUKHKARTA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUKHKARTA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUKHKARTA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.