Home / Browse projects / Nagpur, Maharashtra / SUKHKARTA NAGARI

Registered No litigation declared Residential / Group Housing project

SUKHKARTA NAGARI

By DR SATISH CHIDDARWAR

RG-MH-15472 · RERA P50500048800 · Last updated on MahaRERA portal: 9 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Jul 2032Possession promisedno revision filed
128 of 935Construction stages doneacross 85 buildings; furthest along: Sanitary Fittings within the flats /..., 80%
285 of 371Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 139 documents Report an error

SUKHKARTA NAGARI is a Residential / Group Housing project by DR SATISH CHIDDARWAR in Nagpur, Maharashtra, registered with MahaRERA as P50500048800 on 17 Jan 2023. Possession is promised by 31 Jul 2032. 86 of the 371 units on this registration are recorded sold or booked, and 128 of 935 construction stages are filed complete.

At a glance

Project

  • NameSUKHKARTA NAGARI
  • TypeResidential / Group Housing
  • Location
    • KHASRA NO.88/1
    • MOUZA KANHOLI
    • HINGNA
    • NAGPUR
    • KANHOLI
    • Hingna
    • Nagpur
    • 441108
  • Pincode441108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500048800
  • ReraGenie IDRG-MH-15472

Builder

  • NameDR SATISH CHIDDARWAR
  • Entity typeIndividual

Key dates

this monthRegisteredJan 2023PromisedJul 2032

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Jan 2023
  • Promised completion31 Jul 2032
  • Revised completionNone
  • Buildings85 building records
  • Documents filed139 files

Current status

23%86 of 371 units booked

Figures as on 9 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B-21NA10101
B-22NA10101
B-23NA10101
B-24NA10101
B-25NA10101
B-26NA10101
B-27NA10101
B-28NA10101
B-29NA10101
B-30NA10101
B-31NA10101
B-32NA10101
B-33NA10101
B-34NA10101
B-35NA10101
B-36NA10101
B-37NA10101
B-38NA10101
B-39NA10101
B-40NA10101
B-41NA10101
B-42NA10101
B-43NA10101
B-44NA10101
B-45NA10101
B-46NA10101
B-47NA10101
B-48NA10101
B-49NA10101
B-50NA10101
B-51NA10101
B-52NA10101
B-53NA10101
B-54NA10101
B-55NA10101
B-56NA10101
B-57NA10101
B-58NA10101
B-59NA10101
BUILDING 1NA3012012
BUILDING 2NA3012012
BUILDING 3NA3012012
BUILDING 4NA3012012
BUILDING 5NA3012012
BUILDING 6NA3012012
BUILDING 7NA3012012
BUILDING 8NA3012012
BUILDING 9NA3012012
BUILDING 10NA3012012
BUILDING 11NA3012012
BUILDING 12NA3012012
BUILDING 13NA3012012
BUILDING 14NA3012012
BUILDING 15NA3012012
BUILDING 16NA3012012
BUILDING 17NA3012012
BUILDING 18NA3012012
BUILDING 19NA3012012
BUILDING 20NA3012012
BUILDING 21NA3012012
BUILDING 22NA3012012
BUILDING 23NA3012012
BUILDING 24NA3012012
BUILDING 25NA3012012
BUILDING 26NA3012012
B-1NA10101
B-2NA10101
B-3NA10101
B-4NA10101
B-5NA10101
B-6NA10101
B-7NA10101
B-8NA10101
B-9NA10101
B-10NA10101
B-11NA10101
B-12NA10101
B-13NA10101
B-14NA10101
B-15NA10101
B-16NA10101
B-17NA10101
B-18NA10101
B-19NA10101
B-20NA10101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 9 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 85 buildings; the table lists the first 20.

128 of 935 construction stages are filed complete across 85 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 80%.

B-2121%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-2221%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-2321%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-2421%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-2521%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-2621%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-2721%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-2821%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-2921%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-3021%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-3121%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-3221%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-3321%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-3421%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-3521%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-3621%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-3721%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-3821%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-3915%
ActivityProgress
Excavation100%
Basement (if any)30%
Podiums (if any)0%
Plinth30%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-4015%
ActivityProgress
Excavation100%
Basement (if any)30%
Podiums (if any)0%
Plinth30%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed565

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots565
Open Space565
BuildingOpen SpaceTotal
B-2111
B-2211
B-2311
B-2411
B-2511
B-2611
B-2711
B-2811
B-2911
B-3011
B-3111
B-3211
B-3311
B-3411
B-3511
B-3611
B-3711
B-3811
B-3922
B-4022
B-4122
B-4222
B-4322
B-4422
B-4522
B-4622
B-4722
B-4822
B-4922
B-5022
B-5122
B-5222
B-5322
B-5422
B-5522
B-5622
B-5722
B-5822
B-5922
BUILDING 11919
BUILDING 21919
BUILDING 31919
BUILDING 41818
BUILDING 51818
BUILDING 61818
BUILDING 71818
BUILDING 81818
BUILDING 91717
BUILDING 101818
BUILDING 111818
BUILDING 121818
BUILDING 131818
BUILDING 141818
BUILDING 151818
BUILDING 161818
BUILDING 171818
BUILDING 181818
BUILDING 191818
BUILDING 201818
BUILDING 211818
BUILDING 221818
BUILDING 231818
BUILDING 241919
BUILDING 252020
BUILDING 262020
B-111
B-211
B-311
B-422
B-522
B-622
B-722
B-822
B-911
B-1011
B-1111
B-1211
B-1311
B-1422
B-1522
B-1622
B-1722
B-1822
B-1911
B-2011

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area20,300 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Sep 2024

Approvals and building plan

Sanctioning authorityMAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY
Permissible FSI15684.63
Proposed, not sanctioned15,685 sq m
Buildings approved85
Buildings sanctioned85

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK, UP CHAT HOUSE, KARLA ROAD, PUSAD, DIST YAVATMAL

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectALOK LUNIA
EngineerRAMDAS WAGH
EngineerABHISHEK M REVATKAR
EngineerAkshay Bawane
Chartered AccountantCA NITYAPRAKASH LANJEWAR
Chartered AccountantCA Rakesh Daswani
Chartered AccountantAdhish Agrawal
PartnerRole in project
DR SATISH CHIDDARWAR-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jul 2032

Documents filed139

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 139 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form-1 MAR 26 Sukhakarta Developers.pdf9 May 2026
Form 2File: FORM 2 mar 26 sukhkarta developers.pdf9 May 2026
Form 3File: Form 3CA Mar 26 Final Sukhkarta Developers.pdf9 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Mar 2026 new Sukhkarta Developers.pdf9 May 2026
Form 1File: SN Form 1 Dec 2025.pdf21 Jan 2026
Form 2File: SN Form 2 Dec 2025.pdf21 Jan 2026
Form 3File: SN Form 3 Dec 2025.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: SN Disclosure Dec 2025.pdf21 Jan 2026
Form 1File: Sukhkarta Form 1 Sep 2025.pdf28 Oct 2025
Form 2File: Sukhkarta Form 2 Sep 2025.pdf28 Oct 2025
Form 3File: Sukhkarta Form 3CA Sep 2025.pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sukhkarta Disclosure Sep 2025.pdf28 Oct 2025
Form 1File: Sukhkarta Form 1 Sep 2025.pdf28 Oct 2025
Form 2File: Sukhkarta Form 2 Sep 2025.pdf28 Oct 2025
Form 3File: Sukhkarta Form 3CA Sep 2025.pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sukhkarta Disclosure Sep 2025.pdf28 Oct 2025
Form 5 (FY 2024-2025)File: Sukhkarta Nagari Form 5 Mar 2025.pdf11 Aug 2025
Form 1File: 10) FORM 1 30-06-2025.pdf26 Jul 2025
Form 2File: 10) FORM 2 30-06-2025.pdf26 Jul 2025
Form 3File: 10) FORM 3 30-06-2025.pdf26 Jul 2025
Disclosure of Sold and Booked InventoryFile: 10) DISCLOSURE 30-06-2025.pdf26 Jul 2025
Form 2A (FY 2022-2023)File: Form 2A 31-03-2023.pdf23 Jul 2025
Form 2A (FY 2023-2024)File: Form 2A 31-03-2024.pdf23 Jul 2025
Form 2A (FY 2024-2025)File: Form 2A 31-03-2025.pdf23 Jul 2025
Form 2A (FY 2025-2026)File: Form 2A 31-03-2026.pdf23 Jul 2025
Form 1File: 1) FORM 1 31-03-2023.pdf16 Jul 2025
Form 2File: 1) FORM 2 31-03-2023.pdf16 Jul 2025
Form 3File: 1) FORM 3 31-03-2023.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 1) DISCOLSURE 31-03-2023.pdf16 Jul 2025
Form 1File: 2) FORM 1 30-06-2023.pdf16 Jul 2025
Form 2File: 2) FORM 2 30-06-2023.pdf16 Jul 2025
Form 3File: 2) FORM 3 30-06-2023.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2) DISCLOSURE 30-06-2023.pdf16 Jul 2025
Form 1File: 3) FORM 1 30-09-2023.pdf16 Jul 2025
Form 2File: 3) FORM 2 30-09-2023.pdf16 Jul 2025
Form 3File: 3) FORM 3 30-09-2023.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 3) DISCLOSURE 30-09-2023.pdf16 Jul 2025
Form 1File: 4) FORM 1 30-12-2023.pdf16 Jul 2025
Form 2File: 4) FORM 2 31-12-2023.pdf16 Jul 2025
Form 3File: 4) FORM 3 31-12-2023.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 4) DISCLOSURE 31-12-2023.pdf16 Jul 2025
Form 1File: 5) FORM 1 31-03-2024.pdf16 Jul 2025
Form 2File: 5) FORM 2 31-03-2024.pdf16 Jul 2025
Form 3File: 5) FORM 3 31-03-2024.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 5) DISCOLSURE 31-03-2024.pdf16 Jul 2025
Form 1File: 6) FORM 1 30-06-2024.pdf16 Jul 2025
Form 2File: 6) FORM 2 30-06-2024.pdf16 Jul 2025
Form 3File: 6) FORM 3 30-06-2024.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 6) DISCLOSURE 30-06-2024.pdf16 Jul 2025
Form 1File: 7) FORM 1 30-09-2024.pdf16 Jul 2025
Form 2File: 7) FORM 2 30-09-2024.pdf16 Jul 2025
Form 3File: 7) FORM 3 30-09-2024.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 7) DISCLOSURE 30-09-2024.pdf16 Jul 2025
Form 1File: 8) FORM 1 30-12-2024.pdf16 Jul 2025
Form 2File: 8) FORM 2 31-12-2024.pdf16 Jul 2025
Form 3File: 8) FORM 3 31-12-2024.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 8) DISCLOSURE 31-12-2024.pdf16 Jul 2025
Form 1File: 9) FORM 1 31-03-2025.pdf16 Jul 2025
Form 2File: 9) FORM 2 31-03-2025.pdf16 Jul 2025
Form 3File: 9) FORM 3 31-03-2025.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: 9) DISCLOSURE 31-03-2025.pdf16 Jul 2025
Form 5 (FY 2022-2023)File: FORM 5 31-03-2023.pdf16 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 March 25.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 March 25.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA March 25.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SUKHAKARTA ENGINEER CERTIFICATE FORM2.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architech Dec 24.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3CA DEC 2024.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sukhkarta Form 1 Sep 2024.pdf24 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sukhkarta Form 2 Sep 2024.pdf24 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Sukhkarta FORM 2A March 2024.pdf24 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SUKHKARTA FORM 3 CA SEP 24.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Sukhkarta Form 5 MAR 24.pdf9 Oct 2024
Form 5 (FY 2023-2024)File: Sukhkarta Form 5 MAR 24.pdf4 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sukhkarta Form 1 Jun 2024.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sukhkarta Form 2 Jun 2024.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sukhkarta Form 3 CA Jun 2024.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA MAR 24 SUKHKARTA DEVLOPER.pdf1 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate 4th Qtr.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert Qtr 4 MARCH 24.pdf20 Apr 2024

How this compares with Nagpur

23%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUKHKARTA NAGARI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANHOLI2,800+ in Nagpur

2 kmSUKHKARTA NAGARICompleted 42Lapsed / revoked 19Other 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 112 registered projects within 2 km.

Builder: DR SATISH CHIDDARWAR

DR SATISH CHIDDARWAR has 1 registration on MahaRERA, including SUKHKARTA NAGARI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if SUKHKARTA NAGARI is delayed beyond 31 Jul 2032?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUKHKARTA NAGARI?

The registered promoter entity is DR SATISH CHIDDARWAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUKHKARTA NAGARI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SUKHKARTA NAGARI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUKHKARTA NAGARI?

The professionals named in the filing: Architect: ALOK LUNIA; Engineer: RAMDAS WAGH; Engineer: ABHISHEK M REVATKAR; Engineer: Akshay Bawane; Chartered Accountant: CA NITYAPRAKASH LANJEWAR; Chartered Accountant: CA Rakesh Daswani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUKHKARTA NAGARI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUKHKARTA NAGARI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUKHKARTA NAGARI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.