ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Sudesh

Completed No litigation declared Residential / Group Housing project

Sudesh

By Ankur Premises Developers LLP

RG-MH-91524 · RERA P51800014138 · Last updated on MahaRERA portal: 18 Jan 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Feb 2021Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

Sudesh is a Residential / Group Housing project by Ankur Premises Developers LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800014138 on 9 Nov 2017. The registration is recorded completed; possession was promised by 24 Feb 2021.

At a glance

Project

  • NameSudesh
  • TypeResidential / Group Housing
  • Location
    • Andheri
    • Mumbai Suburban
    • 400054
  • Pincode400054
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800014138
  • ReraGenie IDRG-MH-91524

Builder

  • NameAnkur Premises Developers LLP
  • Entity typePartnership
  • PartnersAnkur Parikh, Jayshree Haren Parikh, Haren Natwarlal Parikh
  • Other registrations3 more →
  • Completed3 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredNov 2017PromisedFeb 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Nov 2017
  • Promised completion24 Feb 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sudesh ApartmentsNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

Sudesh Apartments: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 18 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes15%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered1
Open Space9

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area553 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1641.51
Proposed, not sanctioned1,642 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLinking Road Santacruz West

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKayam Design Consultants
EngineerUday Chande
PartnerRole in project
Ankur Premises Developers LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Nov 2020

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Sudesh Form 4.pdf18 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC sudesh.pdf12 Nov 2020
Status of Formation of Legal Entity (Society/Co Op etc.)File: Annexure E- PR Card Sudesh.pdf12 Nov 2020
Status of ConveyanceFile: Declaration-compressed 2.pdf12 Nov 2020
Status of ConveyanceFile: Declaration-compressed 3.pdf12 Nov 2020
Status of ConveyanceFile: Declaration-compressed 4.pdf12 Nov 2020
OtherFile: Sudesh DA 1-3.pdf12 Nov 2020
OtherFile: Sudesh DA -4-7.pdf12 Nov 2020
OtherFile: Sudesh DA 8-10.pdf12 Nov 2020
OtherFile: Sudesh DA 1-11-1.pdf12 Nov 2020
OtherFile: Sudesh DA 1-11-20-2.pdf12 Nov 2020
OtherFile: Sudesh DA 1-11-20-3.pdf12 Nov 2020
OtherFile: Sudesh DA 3-1-10.pdf12 Nov 2020
OtherFile: Sudesh DA 3-11-20.pdf12 Nov 2020
OtherFile: Sudesh DA 3-21-30.pdf12 Nov 2020
OtherFile: POA.pdf12 Nov 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate.pdf17 Apr 2020
Commencement Certificates / NA Order for plotted developmentFile: Full CC Sudesh.pdf7 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf23 Feb 2019
Status of ConveyanceFile: PR Card.pdf13 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sudesh RERA Certificate Architect.pdf10 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Sudesh 2.pdf10 Oct 2018
Certificates of CA (Form 5)File: Form 5 CA certificate Sudesh.pdf10 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf31 Aug 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Sudesh.pdf23 Mar 2018
Proforma of Allotment letterFile: Sudesh- RERA Agreement.pdf6 Nov 2017
Declaration in FORM BFile: FORM B Sudesh.pdf3 Oct 2017
Certificates of CA (Form 3)File: CA certificate Sudesh RERA.pdf27 Sep 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sudesh Architect Certificate.pdf6 Sep 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate RERA Sudesh.pdf6 Sep 2017
Building plan approvalFile: 2023763_IOD_signed.pdf28 Aug 2017
Layout approvalFile: CTS Plan (1).pdf28 Aug 2017
PAN CardFile: PAN CARD APDLLP.pdf28 Aug 2017
Copy of the legal title reportFile: Title Certificate Sudesh.pdf28 Aug 2017
Details of encumbrancesFile: Sudesh Encumbrances.pdf28 Aug 2017
Copy of Layout Approval (in case of layout)File: CTS Plan (1).pdf28 Aug 2017
Building Plan Approval (IOD)File: 2023763_IOD_signed.pdf28 Aug 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
PREMSAGARP51800004056santacruz west, Mumbai Suburban16Aug 2017OngoingJul 2025Registered original: Jun 2021Not delivered
Sudesh Condominium17th Road Santacruz West Mumbai 400 05411-CompletedAug 2020Late, Sep 2020
New Ratnadeep CHSLPhirozshah Mehta Road Santacruz West Mumbai 5411-CompletedMar 2020Late, Mar 2020
RISHIRAJPODDAR ROAD SANTACRUZ WEST MUMBAI 40005432-CompletedJul 2013Mar 2013

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sudesh on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri6,700+ in Mumbai Suburban

2 kmSudeshCompleted 117Lapsed / revoked 66Other 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 305 registered projects within 2 km.

Builder: Ankur Premises Developers LLP

Ankur Premises Developers LLP has 4 registrations on MahaRERA, including PREMSAGAR and Ratnadeep. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Sudesh is delayed beyond 24 Feb 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sudesh?

The registered promoter entity is Ankur Premises Developers LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sudesh?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sudesh?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sudesh?

The professionals named in the filing: Architect: Kayam Design Consultants; Engineer: Uday Chande. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sudesh?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sudesh. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sudesh to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.