Registered Litigation declared Others project

SUBURBIA ESTATE PHASE 1

By SSG REALTY AND INFRA LLP

RG-MH-07703 · RERA P52100002391 · Last updated on MahaRERA portal: 9 Apr 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 93 complaints at MahaRERA
  • Completion date moved by 90 months
  • 3 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2027Possession promisedmoved 90 months from the original
23 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 90%
166 of 430Units unsoldnot recorded sold or booked
93Complaints at MahaRERAon this registration
Jump to the 151 documents Report an error

SUBURBIA ESTATE PHASE 1 is a Others project by SSG REALTY AND INFRA LLP in Pune, Maharashtra, registered with MahaRERA as P52100002391 on 31 Jul 2017. Possession is promised by 22 Feb 2027. The completion date has moved by 90 months from the original filing. 264 of the 430 units on this registration are recorded sold or booked, and 23 of 44 construction stages are filed complete. 93 complaints are on record with the regulator.

At a glance

Project

  • NameSUBURBIA ESTATE PHASE 1
  • TypeOthers
  • Location
    • -
    • Loni-kand
    • Haveli
    • Pune
    • 412216
  • Pincode412216
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002391
  • ReraGenie IDRG-MH-07703

Builder

  • NameSSG REALTY AND INFRA LLP
  • Entity typeOthers
  • Named personsPRANAY PRAKASH SHINGI, SUSHIL EKNATH GHULE, SAURABH EKNATH GHULE, VINAY PRAKASH SHINGI
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJul 2017First promiseAug 2019Revised toFeb 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Jul 2017
  • Promised completion22 Feb 2027
  • Revised completionRevised to 22 Feb 2027 (originally 10 Aug 2019)
  • Buildings4 building records
  • Documents filed151 files

Current status

61%264 of 430 units booked
54.1%Work done, per cost certificate

Figures as on 9 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA14121430143
BUILDING BNA141296096
BUILDING CNA141296096
BUILDING DNA141295095

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 9 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

23 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 90%.

BUILDING A73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING B74%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING C67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING D73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes25%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed382

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots382
Closed/Covered309
Open Space73
BuildingClosed/CoveredOpen SpaceTotal
BUILDING A10225127
BUILDING B691685
BUILDING C691685
BUILDING D691685

Land and ownership14

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,208 sq m
Land owned byThe promoter, with other names on the file
Named landowners14
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Feb 2026
LandownerVillageDistrict
BHASKAR SHANKAR JAGTAPLoni-kandPune
MANISHA SHAMKANT JAGTAPLoni-kandPune
RAVIKANT BHASKAR JAGTAPLoni-kandPune
PRAKASH SHANKAR JAGTAPLoni-kandPune
MURLIDHAR SHANKAR JAGTAPLoni-kandPune
SHOBHA MURLIDHAR JAGTAPLoni-kandPune
PRASHANT MURLIDHAR JAGTAPLoni-kandPune
ASHWINI PRASHANT JAGTAPLoni-kandPune
CHANDRAKANT SHANKAR JAGTAPLoni-kandPune
SURYAKANT CHANDRAKANT JAGTAPLoni-kandPune
NISHIKANT CHANDRAKANT JAGTAPLoni-kandPune
NALINI RAJENDRA SHITOLELoni-kandPune
SUJATA AMAR SHILIMKARLoni-kandPune
SUSHMA VITTHAL SHITOLELoni-kandPune

Approvals and building plan

Sanctioning authorityPUNE METROPOLITAN REGIONAL DEVELOPMENT AUTHORITY, PUNE
Permissible FSI22217.55
Proposed, not sanctioned22,218 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSIGNATURE BUILDING, BHANDARKAR ROAD, PUNE-04
Estimated costRs 66.58 cr
Cost incurredRs 36.00 cr
Work done54.07%
BuildingWingEstimatedIncurred
BUILDING ANARs 15.00 crRs 10.50 cr
BUILDING BNARs 15.00 crRs 10.50 cr
BUILDING CNARs 15.00 crRs 6.75 cr
BUILDING DNARs 15.00 crRs 6.75 cr
-NARs 6.58 crRs 1.50 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGOHAD ARCHITECTS
EngineerHANSAL PARIKH & ASSOCIATES
EngineerVISHWANATH BALASAHEB PANDHARE
EngineerINFINITY CONSULTANTS
EngineerRAJKUMAR SITARAM JAGTAP
Chartered AccountantZAMBAD AND CO
Chartered AccountantVIPIN KHOBRAGADE AND CO
Chartered AccountantNIKHIL BHUTADA
PartnerRole in project
SSG REALTY AND INFRA LLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100001494Aug 2019 → Aug 2020

Reason as filed by the promoterTo Chairman, Maharashtra Real Estate Regulatory Authority 10th August, 2019, Bandra, Mumbai. Subject: Application for Extension for Project Completion Date. Respected Sir/Ma’am, I, Pranay Shingi, Designated Partner in SSG Realty and Infra LLP, and promoter of Suburbia Estate Phase 1 having RERA registration No P52100002391, hereby apply for revision in project completion date. The erstwhile project completion date was 10th August, 2019, however the same seems to be unachievable due to reasons beyond our control such as: • Insufficient Cash Flow and shortage of Funds due to default in payments

EXT52100010059Aug 2019 → Apr 2023

Reason as filed by the promoterTHE CONSTRUCTION WORK OF THE PROJECT IS 90% COMPLETED. ONLY FEW WORK IS PENDING DUE TO FORCE MAJEURE CIRCUMSTANCES. HENCE THE EXTENSION IS SOUGHT ONLY FOR 10 MONTHS TO COMPLETE THE PROJECT.

EA18022619897Aug 2019 → Feb 2027

Reason as filed by the promoter1. CONSTRUCTION OF THE SAID PROJECT IS 75% COMPLETED. WE NEED EXTENSION TO COMPLETE THE REMAINING CONSTRUCTION. 2. Extension applied till 22/02/2028 with 24.07% consent 3. Completion within 14 months already recorded & approved by HC (Order dt. 22/12/2025) 4. Present application is in compliance with HC order and RERA provisions

Litigation declared1

CaseCourtStatus
949/2016CIVIL COURT SENIOR DIVISIONAWAITING SUMMONS

Complaints filed with MahaRERA93

Case no.ComplainantRespondentFiled
CC005000000054004Prakash JohareS.S.G Realty and Infra LLP02/02/2020
CC005000000064417Sachin ParhadS.S.G Realty and Infra LLP21/07/2020
CC005000000064647Nitesh KumarS S G Reality23/09/2020
CC005000000064673Ravi Soman and Pooja SomanM/s SSG Reality and Infra LLP28/09/2020
CC005000000064731Amit and Seema DevrukhakarM/s SSG Reality and Infra LLP10/10/2020
CC005000000064732Amit and Seema DevrukkhkarM/s SSG Reality and Infra LLP10/10/2020
CC005000000075207Shilpa Rani BansalM/s SSG Reality and Infra LLP13/02/2021
CC005000000053979Sanjay TyagiSSG REALTY AND INFRA LLP [PAN ACHFS 4446 F]16/09/2021
CC005000000054028Amit JogiM/s. S.S.G. REALTY AND INFRA LLP20/03/2022
CC005000000054077Vartika Gokhale BhatiaABISKY RITKRITI PROJECTS01/03/2020
CC005000000064335Mr. Sopan Muktaram Jagtap and Mrs. Sheetal Sopan JagtapM/s S S G Realty and Infra LLP through its Partner Abhijeet Shende, Pranay Shingi and Saurabh Ghule01/07/2020
CC005000000064342Mr. Ramesh Vitthal Sirashayad and Mr. Prakash Vitthal ShirashayadM/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule01/07/2020
CC005000000064350Mr. Ashok Bhausaheb Mhase and Mrs. Sunanda Ashok MhaseM/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule02/07/2020
CC005000000064353Mr. Arindam Mondal and Mrs. Anita MondalM/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule03/07/2020
CC005000000064356Mr. Gaurav KatiyarM/s. S S G Realty and Infra LLP through its Partners Abhijeet Shende, Pranay Shingi, Saurabh Ghule03/07/2020
CC005000000064370Mr. Raghvendra Singh and Mrs. Shanti SinghM/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule04/07/2020
CC005000000064369Mr. Shishir Dash and Mrs. Sibani MohapatroM/s. S S G Realty & Infra LLP Through its Partner Abhijeet Shende, Pranay Shingi and Saurabh Ghule04/07/2020
CC005000000064375Mr. Rohit PanditaM/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule07/07/2020
CC005000000064376Mr. Rahul PanditaM/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule07/07/2020
CC005000000064389Mr. Dhanraj Premraj Wanve & Mrs. Vaishali Dhanraj WanveM/s S.S.G Realty & infra LLP through its partners Abhijeet Shende, Pranay Shingi & Saurabh Ghule11/07/2020
CC005000000064397Mr. Rishikesh Shrikrishna Kabara and Mrs. Bharati Shrikrishna KabaraM/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule13/07/2020
CC005000000064454Mr. Manish Amin and Mrs. Mital Manish AminM/s S S G Realty and Infra LLP through its Partners Abhijeet Shende, Pranay shingi & Saurabh Ghule30/07/2020
CC005000000064457Mrs. Renuka Bajpai and Mr. Anant Kumar MishraM/s. S S G Realty & Infra LLP Through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule29/07/2020
CC005000000064451Mr. Niwruttee Pandurang Hage and Mrs. Snehal Niwruttee HageM/s. S S G Realty and Infra LLP through its Partners Abhijeet Shende, Pranay Shingi & Saurabh Ghule28/07/2020
CC005000000064493Mr. Niteen Keshri and Mrs. Shweta KeshriM/s S S G Realty and Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule13/08/2020
CC005000000064518Mrs. Sapna Nandkishor Daga and Mr. Nandkishor Chaturbhuj DagaM/s S.S.G.Realty & Infra LLP through its partners Abhijeet Shende, Pranay Shingi & Saurabh Ghule18/08/2020
CC005000000064801Mrs. Rekha Sachin Supekar and Mr. Sachin Vijay SupekarM/s S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi & Saurabh Ghule04/11/2020
CC005000000064831Balasaheb Kisan RaskarSSG REALITY AND INFRA LLP18/11/2020
CC005000000085612SSG REALTY AND INFRA LLPSHAKILA KAZI29/06/2021
CC005000000085613SSG REALTY AND INFRA LLPRAJENDRA PARHAD29/06/2021
CC005000000085614SSG REALTY AND INFRA LLPUTTANKA HAZARIKA29/06/2021
CC005000000085616SSG REALTY AND INFRA LLPVIKAS SRIVASTAVA29/06/2021
CC005000000085617SSG REALTY AND INFRA LLPSUMAN GUPTA29/06/2021
CC005000000085618SSG REALTY AND INFRA LLPRAVIRAJ MANGALAM29/06/2021
CC005000000096022SSG Realty and Infra LLPMR. PRAKASH BHIKAJI JOHARE19/09/2021
CC005000000096023SSG Realty and Infra LLPAMIT SRIVASTAV19/09/2021
CC005000000096024SSG Realty and Infra LLPVIJAY MANGESHKAR19/09/2021
CC005000000096025SSG Realty and Infra LLPVARTIKA GOKHALE BHATIA19/09/2021
CC005000000096026SSG Realty and Infra LLPRAJENDRA BALKRISHNA PARHAD19/09/2021
CC005000000096027SSG Realty and Infra LLPNITESH KUMAR19/09/2021
CC005000000085621Rakesh Narendra DhoptePRANAY SHINGI15/01/2022
CC005000000106619TABASSUM SHAIKHABISKY-RITKRITI PROJECTS20/02/2022
CC005000000095894Rahul Sumant BhadraDirectors of Abisky Ritkriti Projects, Suburbia, Lonikand, MahaRera Registration No. P5210000239106/05/2022
CC005000000095906Mrs. Akshada ShrivastavM/s. S.S.G. Realty and Infra LLP Through its Partners Abhijeet Shende, Pranay Shingi, Saurabh Ghule19/08/2021
CC005000000095911Mr. Uttanka HazarikaM/s. S. S. G. Realty and Infra LLP through its partner Pranay Shingi, Sushil Ghule, Saurabh Ghule21/08/2021
CC005000000095963Gagan Pandey and Munni Priya PandeyPRANAY PRAKASH SHINGI AND SAURABH EKNATH GHULE16/09/2021
CC005000000096006Mr. Pinkesh Vasantlal (alias Vasantbhai) AchhodwalaS S G Realty and Infra LLP thro its Partner Pranay Shingi,Sushil Ghule, Saurabh Ghule, Vinay Shingi16/09/2021
CC005000000096067Vivek VidhyasagarPranay Shingi09/11/2021
CC005000000096070Shweta SaranPranay Shingvi11/11/2021
CC005000000096243Raviraj MangalamPranay Shingi20/11/2021
CC005000000096236Nikhil NaiduPranay Shingi23/11/2021
CC005000000106455SHUVASHANKAR DUTTAPRANAY SHINGI06/01/2022
CC005000000106458MANISHA JAINMANISHA JAIN06/01/2022
CC005000000106486Mr. Vikas ShrivastavaS.S.G. Realty & Infra LLP Thr Part. a.Pranay Shingi b.Sushil Ghule c.Saurabh Ghule d.Vinay Shingi13/01/2022
CC005000000106545Mr. Umesh Dayaram YadavS S G Realty and Infra LLP thro its Partner Pranay Shingi,Sushil Ghule, Saurabh Ghule, Vinay Shingi25/01/2022
CC005000000106541Mr. Omkar Bhalchandra AmbulkarS.S.G.Realty&Infra LLP Thr.its Partner a.Pranay Shingi b.Sushil Ghule c.Saurabh Ghule d.Vinay Shingi25/01/2022
CC005000000106789Purushottam M. JogiM/s. S.S.G. REALTY AND INFRA LLP20/03/2022
CC005000000053917Niranjan GhatpandeSSG Realty and Infra12/01/2020
CC005000000106831Salahuddin ChoudhariM/s. S. S. G. Realty and Infra LLP a. Pranay Shingi b. Sushil Ghule c. Saurabh Ghule d. Vinay Shingi16/04/2022
CC005000000054033Vijay MangeshkarM/s s s g Realty12/02/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 22 Feb 2027

Documents filed151

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 151 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: ARCHITECT CERTIFICATE_0001 (2).pdf9 Apr 2026
Form 2File: 01-01-2025 Engineer Certificate_0001.pdf9 Apr 2026
Form 3File: CA CERTIFICATE_000.pdf9 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0002_.pdf9 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE_0001_.pdf9 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE_0001 (2).pdf9 Apr 2026
Withdrawal Update Form 2File: 01-07-2025 Engineer Certificate_0001.pdf9 Apr 2026
Withdrawal Update Form 2File: FORM 2 - Engineer Certificate _0001.pdf9 Apr 2026
Withdrawal Update Form 3File: CA_06-2025 (2).pdf9 Apr 2026
Withdrawal Update Form 3File: CA_09-2025_.pdf9 Apr 2026
Form 1File: ARCHITECT CERTIFICATE.pdf8 Apr 2026
Form 2File: 01-07-2023 Engineer Certificate_0001.pdf8 Apr 2026
Form 3File: CA_06-2023.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf8 Apr 2026
Form 1File: ARCHITECT CERTIFICATE.pdf8 Apr 2026
Form 2File: 01-10-2023 Engineer Certificate_0001.pdf8 Apr 2026
Form 3File: CA_09-2023 (2).pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf8 Apr 2026
Form 1File: ARCHITECT CERTIFICATE.pdf8 Apr 2026
Form 2File: 01-01-2024 Engineer Certificate_0001.pdf8 Apr 2026
Form 3File: CA_12-2023 (2).pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf8 Apr 2026
Form 1File: ARCHITECT CERTIFICATE.pdf8 Apr 2026
Form 2File: 01-04-2024 Engineer Certificate_0001.pdf8 Apr 2026
Form 3File: CA CERTIFICATE_0001 (2).pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf8 Apr 2026
Form 1File: ARCHITECT CERTIFICATE_0001 (2).pdf8 Apr 2026
Form 2File: 01-07-2024 Engineer Certificate_0001.pdf8 Apr 2026
Form 3File: CA CERTIFICATE_0001 (2).pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf8 Apr 2026
Form 1File: ARCHITECT CERTIFICATE_0001 (2).pdf8 Apr 2026
Form 2File: 01-10-2024 Engineer Certificate_0001.pdf8 Apr 2026
Form 3File: CA CERTIFICATE_0001 (2).pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf8 Apr 2026
Form 1File: ARCHITECT CERTIFICATE.pdf26 Mar 2026
Form 2File: ENGINEER CERTIFICATE 01-07-2021.pdf26 Mar 2026
Form 3File: CA CERTIFICATE 30-06-2021.pdf26 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf26 Mar 2026
Form 1File: ARCHITECT CERTIFICATE_0001.pdf26 Mar 2026
Form 2File: ENGINEER CERTIFICATE 01-10-2021.pdf26 Mar 2026
Form 3File: CA CERTIFICATE 30-09-2021.pdf26 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001.pdf26 Mar 2026
Form 1File: ARCHITECT CERTIFICATE_0001.pdf26 Mar 2026
Form 2File: ENGINEER CERTIFICATE 01-01-2022_0001.pdf26 Mar 2026
Form 3File: CA CERTIFICATE 30-12-2021.pdf26 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf26 Mar 2026
Form 1File: ARCHITECT CERTIFICATE.pdf26 Mar 2026
Form 2File: EG_12-2022.pdf26 Mar 2026
Form 3File: CA_12-2022.pdf26 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf26 Mar 2026
Form 5 (FY 2019-2020)File: 2019-20.pdf21 Mar 2026
Form 5 (FY 2020-2021)File: 2020-21.pdf21 Mar 2026
Form 5 (FY 2021-2022)File: 2021-22.pdf21 Mar 2026
Form 5 (FY 2022-2023)File: 2022-23.pdf21 Mar 2026
Form 5 (FY 2023-2024)File: 2023-24.pdf21 Mar 2026
Form 1File: ARCHITECT CERTIFICATE.pdf20 Mar 2026
Form 2File: 01-01-2023 Engineer Certificate_0001.pdf20 Mar 2026
Form 3File: CA_03-2023.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf20 Mar 2026
Form 1File: ARCHITECT CERTIFICATE_0001.pdf20 Mar 2026
Form 2File: 01-04-2019 Engineer Certificate_0001.pdf20 Mar 2026
Form 3File: CA-CERTIFICATE-31-03-2019.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001.pdf20 Mar 2026
Form 1File: ARCHITECT CERTIFICATE_0001.pdf20 Mar 2026
Form 2File: 01-04-2020 Engineer Certificate_0001.pdf20 Mar 2026
Form 3File: CA-CERTIFICATE-31-03-2020.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001.pdf20 Mar 2026
Form 1File: ARCHITECT CERTIFICATE_0001.pdf20 Mar 2026
Form 2File: 01-04-2021 Engineer Certificate_0001.pdf20 Mar 2026
Form 3File: CA CERTIFICATE 31-03-2021.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001.pdf20 Mar 2026
Form 1File: ARCHITECT CERTIFICATE18-03-2026.pdf18 Mar 2026
Form 2File: 01-04-2022 Engineer Certificate_0001.pdf18 Mar 2026
Form 3File: CA_03-2022.pdf18 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf18 Mar 2026
Form 1File: AR_06-2022.pdf18 Mar 2026
Form 2File: 01-07-2022 Engineer Certificate.pdf18 Mar 2026
Form 3File: CA_06-2022.pdf18 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf18 Mar 2026
Form 1File: ARCHITECT CERTIFICATE.pdf18 Mar 2026

How this compares with Pune

61%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 90 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUBURBIA ESTATE PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near -13,700+ in Pune

2 kmSUBURBIA ESTATE PHASE 1Completed 3Lapsed / revoked 3Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: SSG REALTY AND INFRA LLP

SSG REALTY AND INFRA LLP has 2 registrations on MahaRERA, including SUBURBIA ESTATE PHASE 1 and SUBURBIA ESTATE PHASE 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SUBURBIA ESTATE PHASE 1 is delayed beyond 22 Feb 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUBURBIA ESTATE PHASE 1?

The registered promoter entity is SSG REALTY AND INFRA LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUBURBIA ESTATE PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SUBURBIA ESTATE PHASE 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SUBURBIA ESTATE PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUBURBIA ESTATE PHASE 1?

The professionals named in the filing: Architect: GOHAD ARCHITECTS; Engineer: HANSAL PARIKH & ASSOCIATES; Engineer: VISHWANATH BALASAHEB PANDHARE; Engineer: INFINITY CONSULTANTS; Engineer: RAJKUMAR SITARAM JAGTAP; Chartered Accountant: ZAMBAD AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUBURBIA ESTATE PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUBURBIA ESTATE PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUBURBIA ESTATE PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.