Home / Browse projects / Pune, Maharashtra / SUBURBIA ESTATE PHASE 1
SUBURBIA ESTATE PHASE 1
RG-MH-07703 · RERA P52100002391 · Last updated on MahaRERA portal: 9 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 1 case
- 93 complaints at MahaRERA
- Completion date moved by 90 months
- 3 extensions taken
Clear
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SUBURBIA ESTATE PHASE 1 is a Others project by SSG REALTY AND INFRA LLP in Pune, Maharashtra, registered with MahaRERA as P52100002391 on 31 Jul 2017. Possession is promised by 22 Feb 2027. The completion date has moved by 90 months from the original filing. 264 of the 430 units on this registration are recorded sold or booked, and 23 of 44 construction stages are filed complete. 93 complaints are on record with the regulator.
At a glance
Project
- NameSUBURBIA ESTATE PHASE 1
- TypeOthers
- Location
- -
- Loni-kand
- Haveli
- Pune
- 412216
- Pincode412216
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100002391
- ReraGenie IDRG-MH-07703
Builder
- NameSSG REALTY AND INFRA LLP
- Entity typeOthers
- Named personsPRANAY PRAKASH SHINGI, SUSHIL EKNATH GHULE, SAURABH EKNATH GHULE, VINAY PRAKASH SHINGI
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Jul 2017
- Promised completion22 Feb 2027
- Revised completionRevised to 22 Feb 2027 (originally 10 Aug 2019)
- Buildings4 building records
- Documents filed151 files
Current status
Figures as on 9 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING A | NA | 14 | 12 | 143 | 0 | 143 |
| BUILDING B | NA | 14 | 12 | 96 | 0 | 96 |
| BUILDING C | NA | 14 | 12 | 96 | 0 | 96 |
| BUILDING D | NA | 14 | 12 | 95 | 0 | 95 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 9 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
23 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 90%.
BUILDING A73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING B74%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING C67%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING D73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 55% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 9 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 25% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed382
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BUILDING A | 102 | 25 | 127 |
| BUILDING B | 69 | 16 | 85 |
| BUILDING C | 69 | 16 | 85 |
| BUILDING D | 69 | 16 | 85 |
Land and ownership14
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| BHASKAR SHANKAR JAGTAP | Loni-kand | Pune |
| MANISHA SHAMKANT JAGTAP | Loni-kand | Pune |
| RAVIKANT BHASKAR JAGTAP | Loni-kand | Pune |
| PRAKASH SHANKAR JAGTAP | Loni-kand | Pune |
| MURLIDHAR SHANKAR JAGTAP | Loni-kand | Pune |
| SHOBHA MURLIDHAR JAGTAP | Loni-kand | Pune |
| PRASHANT MURLIDHAR JAGTAP | Loni-kand | Pune |
| ASHWINI PRASHANT JAGTAP | Loni-kand | Pune |
| CHANDRAKANT SHANKAR JAGTAP | Loni-kand | Pune |
| SURYAKANT CHANDRAKANT JAGTAP | Loni-kand | Pune |
| NISHIKANT CHANDRAKANT JAGTAP | Loni-kand | Pune |
| NALINI RAJENDRA SHITOLE | Loni-kand | Pune |
| SUJATA AMAR SHILIMKAR | Loni-kand | Pune |
| SUSHMA VITTHAL SHITOLE | Loni-kand | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING A | NA | Rs 15.00 cr | Rs 10.50 cr |
| BUILDING B | NA | Rs 15.00 cr | Rs 10.50 cr |
| BUILDING C | NA | Rs 15.00 cr | Rs 6.75 cr |
| BUILDING D | NA | Rs 15.00 cr | Rs 6.75 cr |
| - | NA | Rs 6.58 cr | Rs 1.50 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GOHAD ARCHITECTS |
| Engineer | HANSAL PARIKH & ASSOCIATES |
| Engineer | VISHWANATH BALASAHEB PANDHARE |
| Engineer | INFINITY CONSULTANTS |
| Engineer | RAJKUMAR SITARAM JAGTAP |
| Chartered Accountant | ZAMBAD AND CO |
| Chartered Accountant | VIPIN KHOBRAGADE AND CO |
| Chartered Accountant | NIKHIL BHUTADA |
| Partner | Role in project |
|---|---|
| SSG REALTY AND INFRA LLP | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTo Chairman, Maharashtra Real Estate Regulatory Authority 10th August, 2019, Bandra, Mumbai. Subject: Application for Extension for Project Completion Date. Respected Sir/Ma’am, I, Pranay Shingi, Designated Partner in SSG Realty and Infra LLP, and promoter of Suburbia Estate Phase 1 having RERA registration No P52100002391, hereby apply for revision in project completion date. The erstwhile project completion date was 10th August, 2019, however the same seems to be unachievable due to reasons beyond our control such as: • Insufficient Cash Flow and shortage of Funds due to default in payments
Reason as filed by the promoterTHE CONSTRUCTION WORK OF THE PROJECT IS 90% COMPLETED. ONLY FEW WORK IS PENDING DUE TO FORCE MAJEURE CIRCUMSTANCES. HENCE THE EXTENSION IS SOUGHT ONLY FOR 10 MONTHS TO COMPLETE THE PROJECT.
Reason as filed by the promoter1. CONSTRUCTION OF THE SAID PROJECT IS 75% COMPLETED. WE NEED EXTENSION TO COMPLETE THE REMAINING CONSTRUCTION. 2. Extension applied till 22/02/2028 with 24.07% consent 3. Completion within 14 months already recorded & approved by HC (Order dt. 22/12/2025) 4. Present application is in compliance with HC order and RERA provisions
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 949/2016 | CIVIL COURT SENIOR DIVISION | AWAITING SUMMONS |
Complaints filed with MahaRERA93
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000054004 | Prakash Johare | S.S.G Realty and Infra LLP | 02/02/2020 |
| CC005000000064417 | Sachin Parhad | S.S.G Realty and Infra LLP | 21/07/2020 |
| CC005000000064647 | Nitesh Kumar | S S G Reality | 23/09/2020 |
| CC005000000064673 | Ravi Soman and Pooja Soman | M/s SSG Reality and Infra LLP | 28/09/2020 |
| CC005000000064731 | Amit and Seema Devrukhakar | M/s SSG Reality and Infra LLP | 10/10/2020 |
| CC005000000064732 | Amit and Seema Devrukkhkar | M/s SSG Reality and Infra LLP | 10/10/2020 |
| CC005000000075207 | Shilpa Rani Bansal | M/s SSG Reality and Infra LLP | 13/02/2021 |
| CC005000000053979 | Sanjay Tyagi | SSG REALTY AND INFRA LLP [PAN ACHFS 4446 F] | 16/09/2021 |
| CC005000000054028 | Amit Jogi | M/s. S.S.G. REALTY AND INFRA LLP | 20/03/2022 |
| CC005000000054077 | Vartika Gokhale Bhatia | ABISKY RITKRITI PROJECTS | 01/03/2020 |
| CC005000000064335 | Mr. Sopan Muktaram Jagtap and Mrs. Sheetal Sopan Jagtap | M/s S S G Realty and Infra LLP through its Partner Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 01/07/2020 |
| CC005000000064342 | Mr. Ramesh Vitthal Sirashayad and Mr. Prakash Vitthal Shirashayad | M/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 01/07/2020 |
| CC005000000064350 | Mr. Ashok Bhausaheb Mhase and Mrs. Sunanda Ashok Mhase | M/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 02/07/2020 |
| CC005000000064353 | Mr. Arindam Mondal and Mrs. Anita Mondal | M/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 03/07/2020 |
| CC005000000064356 | Mr. Gaurav Katiyar | M/s. S S G Realty and Infra LLP through its Partners Abhijeet Shende, Pranay Shingi, Saurabh Ghule | 03/07/2020 |
| CC005000000064370 | Mr. Raghvendra Singh and Mrs. Shanti Singh | M/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 04/07/2020 |
| CC005000000064369 | Mr. Shishir Dash and Mrs. Sibani Mohapatro | M/s. S S G Realty & Infra LLP Through its Partner Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 04/07/2020 |
| CC005000000064375 | Mr. Rohit Pandita | M/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 07/07/2020 |
| CC005000000064376 | Mr. Rahul Pandita | M/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 07/07/2020 |
| CC005000000064389 | Mr. Dhanraj Premraj Wanve & Mrs. Vaishali Dhanraj Wanve | M/s S.S.G Realty & infra LLP through its partners Abhijeet Shende, Pranay Shingi & Saurabh Ghule | 11/07/2020 |
| CC005000000064397 | Mr. Rishikesh Shrikrishna Kabara and Mrs. Bharati Shrikrishna Kabara | M/s. S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 13/07/2020 |
| CC005000000064454 | Mr. Manish Amin and Mrs. Mital Manish Amin | M/s S S G Realty and Infra LLP through its Partners Abhijeet Shende, Pranay shingi & Saurabh Ghule | 30/07/2020 |
| CC005000000064457 | Mrs. Renuka Bajpai and Mr. Anant Kumar Mishra | M/s. S S G Realty & Infra LLP Through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 29/07/2020 |
| CC005000000064451 | Mr. Niwruttee Pandurang Hage and Mrs. Snehal Niwruttee Hage | M/s. S S G Realty and Infra LLP through its Partners Abhijeet Shende, Pranay Shingi & Saurabh Ghule | 28/07/2020 |
| CC005000000064493 | Mr. Niteen Keshri and Mrs. Shweta Keshri | M/s S S G Realty and Infra LLP through its Partners Abhijeet Shende, Pranay Shingi and Saurabh Ghule | 13/08/2020 |
| CC005000000064518 | Mrs. Sapna Nandkishor Daga and Mr. Nandkishor Chaturbhuj Daga | M/s S.S.G.Realty & Infra LLP through its partners Abhijeet Shende, Pranay Shingi & Saurabh Ghule | 18/08/2020 |
| CC005000000064801 | Mrs. Rekha Sachin Supekar and Mr. Sachin Vijay Supekar | M/s S S G Realty & Infra LLP through its Partners Abhijeet Shende, Pranay Shingi & Saurabh Ghule | 04/11/2020 |
| CC005000000064831 | Balasaheb Kisan Raskar | SSG REALITY AND INFRA LLP | 18/11/2020 |
| CC005000000085612 | SSG REALTY AND INFRA LLP | SHAKILA KAZI | 29/06/2021 |
| CC005000000085613 | SSG REALTY AND INFRA LLP | RAJENDRA PARHAD | 29/06/2021 |
| CC005000000085614 | SSG REALTY AND INFRA LLP | UTTANKA HAZARIKA | 29/06/2021 |
| CC005000000085616 | SSG REALTY AND INFRA LLP | VIKAS SRIVASTAVA | 29/06/2021 |
| CC005000000085617 | SSG REALTY AND INFRA LLP | SUMAN GUPTA | 29/06/2021 |
| CC005000000085618 | SSG REALTY AND INFRA LLP | RAVIRAJ MANGALAM | 29/06/2021 |
| CC005000000096022 | SSG Realty and Infra LLP | MR. PRAKASH BHIKAJI JOHARE | 19/09/2021 |
| CC005000000096023 | SSG Realty and Infra LLP | AMIT SRIVASTAV | 19/09/2021 |
| CC005000000096024 | SSG Realty and Infra LLP | VIJAY MANGESHKAR | 19/09/2021 |
| CC005000000096025 | SSG Realty and Infra LLP | VARTIKA GOKHALE BHATIA | 19/09/2021 |
| CC005000000096026 | SSG Realty and Infra LLP | RAJENDRA BALKRISHNA PARHAD | 19/09/2021 |
| CC005000000096027 | SSG Realty and Infra LLP | NITESH KUMAR | 19/09/2021 |
| CC005000000085621 | Rakesh Narendra Dhopte | PRANAY SHINGI | 15/01/2022 |
| CC005000000106619 | TABASSUM SHAIKH | ABISKY-RITKRITI PROJECTS | 20/02/2022 |
| CC005000000095894 | Rahul Sumant Bhadra | Directors of Abisky Ritkriti Projects, Suburbia, Lonikand, MahaRera Registration No. P52100002391 | 06/05/2022 |
| CC005000000095906 | Mrs. Akshada Shrivastav | M/s. S.S.G. Realty and Infra LLP Through its Partners Abhijeet Shende, Pranay Shingi, Saurabh Ghule | 19/08/2021 |
| CC005000000095911 | Mr. Uttanka Hazarika | M/s. S. S. G. Realty and Infra LLP through its partner Pranay Shingi, Sushil Ghule, Saurabh Ghule | 21/08/2021 |
| CC005000000095963 | Gagan Pandey and Munni Priya Pandey | PRANAY PRAKASH SHINGI AND SAURABH EKNATH GHULE | 16/09/2021 |
| CC005000000096006 | Mr. Pinkesh Vasantlal (alias Vasantbhai) Achhodwala | S S G Realty and Infra LLP thro its Partner Pranay Shingi,Sushil Ghule, Saurabh Ghule, Vinay Shingi | 16/09/2021 |
| CC005000000096067 | Vivek Vidhyasagar | Pranay Shingi | 09/11/2021 |
| CC005000000096070 | Shweta Saran | Pranay Shingvi | 11/11/2021 |
| CC005000000096243 | Raviraj Mangalam | Pranay Shingi | 20/11/2021 |
| CC005000000096236 | Nikhil Naidu | Pranay Shingi | 23/11/2021 |
| CC005000000106455 | SHUVASHANKAR DUTTA | PRANAY SHINGI | 06/01/2022 |
| CC005000000106458 | MANISHA JAIN | MANISHA JAIN | 06/01/2022 |
| CC005000000106486 | Mr. Vikas Shrivastava | S.S.G. Realty & Infra LLP Thr Part. a.Pranay Shingi b.Sushil Ghule c.Saurabh Ghule d.Vinay Shingi | 13/01/2022 |
| CC005000000106545 | Mr. Umesh Dayaram Yadav | S S G Realty and Infra LLP thro its Partner Pranay Shingi,Sushil Ghule, Saurabh Ghule, Vinay Shingi | 25/01/2022 |
| CC005000000106541 | Mr. Omkar Bhalchandra Ambulkar | S.S.G.Realty&Infra LLP Thr.its Partner a.Pranay Shingi b.Sushil Ghule c.Saurabh Ghule d.Vinay Shingi | 25/01/2022 |
| CC005000000106789 | Purushottam M. Jogi | M/s. S.S.G. REALTY AND INFRA LLP | 20/03/2022 |
| CC005000000053917 | Niranjan Ghatpande | SSG Realty and Infra | 12/01/2020 |
| CC005000000106831 | Salahuddin Choudhari | M/s. S. S. G. Realty and Infra LLP a. Pranay Shingi b. Sushil Ghule c. Saurabh Ghule d. Vinay Shingi | 16/04/2022 |
| CC005000000054033 | Vijay Mangeshkar | M/s s s g Realty | 12/02/2020 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 22 Feb 2027
Documents filed151
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 151 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: ARCHITECT CERTIFICATE_0001 (2).pdf | 9 Apr 2026 |
| Form 2File: 01-01-2025 Engineer Certificate_0001.pdf | 9 Apr 2026 |
| Form 3File: CA CERTIFICATE_000.pdf | 9 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0002_.pdf | 9 Apr 2026 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE_0001_.pdf | 9 Apr 2026 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE_0001 (2).pdf | 9 Apr 2026 |
| Withdrawal Update Form 2File: 01-07-2025 Engineer Certificate_0001.pdf | 9 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 - Engineer Certificate _0001.pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: CA_06-2025 (2).pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: CA_09-2025_.pdf | 9 Apr 2026 |
| Form 1File: ARCHITECT CERTIFICATE.pdf | 8 Apr 2026 |
| Form 2File: 01-07-2023 Engineer Certificate_0001.pdf | 8 Apr 2026 |
| Form 3File: CA_06-2023.pdf | 8 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf | 8 Apr 2026 |
| Form 1File: ARCHITECT CERTIFICATE.pdf | 8 Apr 2026 |
| Form 2File: 01-10-2023 Engineer Certificate_0001.pdf | 8 Apr 2026 |
| Form 3File: CA_09-2023 (2).pdf | 8 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf | 8 Apr 2026 |
| Form 1File: ARCHITECT CERTIFICATE.pdf | 8 Apr 2026 |
| Form 2File: 01-01-2024 Engineer Certificate_0001.pdf | 8 Apr 2026 |
| Form 3File: CA_12-2023 (2).pdf | 8 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf | 8 Apr 2026 |
| Form 1File: ARCHITECT CERTIFICATE.pdf | 8 Apr 2026 |
| Form 2File: 01-04-2024 Engineer Certificate_0001.pdf | 8 Apr 2026 |
| Form 3File: CA CERTIFICATE_0001 (2).pdf | 8 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf | 8 Apr 2026 |
| Form 1File: ARCHITECT CERTIFICATE_0001 (2).pdf | 8 Apr 2026 |
| Form 2File: 01-07-2024 Engineer Certificate_0001.pdf | 8 Apr 2026 |
| Form 3File: CA CERTIFICATE_0001 (2).pdf | 8 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf | 8 Apr 2026 |
| Form 1File: ARCHITECT CERTIFICATE_0001 (2).pdf | 8 Apr 2026 |
| Form 2File: 01-10-2024 Engineer Certificate_0001.pdf | 8 Apr 2026 |
| Form 3File: CA CERTIFICATE_0001 (2).pdf | 8 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf | 8 Apr 2026 |
| Form 1File: ARCHITECT CERTIFICATE.pdf | 26 Mar 2026 |
| Form 2File: ENGINEER CERTIFICATE 01-07-2021.pdf | 26 Mar 2026 |
| Form 3File: CA CERTIFICATE 30-06-2021.pdf | 26 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf | 26 Mar 2026 |
| Form 1File: ARCHITECT CERTIFICATE_0001.pdf | 26 Mar 2026 |
| Form 2File: ENGINEER CERTIFICATE 01-10-2021.pdf | 26 Mar 2026 |
| Form 3File: CA CERTIFICATE 30-09-2021.pdf | 26 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001.pdf | 26 Mar 2026 |
| Form 1File: ARCHITECT CERTIFICATE_0001.pdf | 26 Mar 2026 |
| Form 2File: ENGINEER CERTIFICATE 01-01-2022_0001.pdf | 26 Mar 2026 |
| Form 3File: CA CERTIFICATE 30-12-2021.pdf | 26 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf | 26 Mar 2026 |
| Form 1File: ARCHITECT CERTIFICATE.pdf | 26 Mar 2026 |
| Form 2File: EG_12-2022.pdf | 26 Mar 2026 |
| Form 3File: CA_12-2022.pdf | 26 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf | 26 Mar 2026 |
| Form 5 (FY 2019-2020)File: 2019-20.pdf | 21 Mar 2026 |
| Form 5 (FY 2020-2021)File: 2020-21.pdf | 21 Mar 2026 |
| Form 5 (FY 2021-2022)File: 2021-22.pdf | 21 Mar 2026 |
| Form 5 (FY 2022-2023)File: 2022-23.pdf | 21 Mar 2026 |
| Form 5 (FY 2023-2024)File: 2023-24.pdf | 21 Mar 2026 |
| Form 1File: ARCHITECT CERTIFICATE.pdf | 20 Mar 2026 |
| Form 2File: 01-01-2023 Engineer Certificate_0001.pdf | 20 Mar 2026 |
| Form 3File: CA_03-2023.pdf | 20 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001 (2).pdf | 20 Mar 2026 |
| Form 1File: ARCHITECT CERTIFICATE_0001.pdf | 20 Mar 2026 |
| Form 2File: 01-04-2019 Engineer Certificate_0001.pdf | 20 Mar 2026 |
| Form 3File: CA-CERTIFICATE-31-03-2019.pdf | 20 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001.pdf | 20 Mar 2026 |
| Form 1File: ARCHITECT CERTIFICATE_0001.pdf | 20 Mar 2026 |
| Form 2File: 01-04-2020 Engineer Certificate_0001.pdf | 20 Mar 2026 |
| Form 3File: CA-CERTIFICATE-31-03-2020.pdf | 20 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001.pdf | 20 Mar 2026 |
| Form 1File: ARCHITECT CERTIFICATE_0001.pdf | 20 Mar 2026 |
| Form 2File: 01-04-2021 Engineer Certificate_0001.pdf | 20 Mar 2026 |
| Form 3File: CA CERTIFICATE 31-03-2021.pdf | 20 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY_0001.pdf | 20 Mar 2026 |
| Form 1File: ARCHITECT CERTIFICATE18-03-2026.pdf | 18 Mar 2026 |
| Form 2File: 01-04-2022 Engineer Certificate_0001.pdf | 18 Mar 2026 |
| Form 3File: CA_03-2022.pdf | 18 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf | 18 Mar 2026 |
| Form 1File: AR_06-2022.pdf | 18 Mar 2026 |
| Form 2File: 01-07-2022 Engineer Certificate.pdf | 18 Mar 2026 |
| Form 3File: CA_06-2022.pdf | 18 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf | 18 Mar 2026 |
| Form 1File: ARCHITECT CERTIFICATE.pdf | 18 Mar 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 151 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SUBURBIA ESTATE PHASE 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near -13,700+ in Pune
Filed coordinates, straight-line distance. 10 registered projects within 2 km.
GURUVISTA PHASE 3
Arham Realty
AUM AANGAN
KAMDHENU SPACES LLP
Skyline Square Phase 1- Wing A
Mulik Associates
OXY FLORA PHASE 3
YOGESH DEVELOPERS
Aura Sai Krishnangan-Building A
Bhagvati Infra
SPARKLE RESIDENCE
Kale Developer
Builder: SSG REALTY AND INFRA LLP
SSG REALTY AND INFRA LLP has 2 registrations on MahaRERA, including SUBURBIA ESTATE PHASE 1 and SUBURBIA ESTATE PHASE 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SUBURBIA ESTATE PHASE 1 is delayed beyond 22 Feb 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SUBURBIA ESTATE PHASE 1?
The registered promoter entity is SSG REALTY AND INFRA LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SUBURBIA ESTATE PHASE 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SUBURBIA ESTATE PHASE 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SUBURBIA ESTATE PHASE 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SUBURBIA ESTATE PHASE 1?
The professionals named in the filing: Architect: GOHAD ARCHITECTS; Engineer: HANSAL PARIKH & ASSOCIATES; Engineer: VISHWANATH BALASAHEB PANDHARE; Engineer: INFINITY CONSULTANTS; Engineer: RAJKUMAR SITARAM JAGTAP; Chartered Accountant: ZAMBAD AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUBURBIA ESTATE PHASE 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.