Home / Browse projects / Palghar, Maharashtra / STAR HEIGHT

Registration lapsed No litigation declared Others project

STAR HEIGHT

By ERIC INFRASTRUCTURE

RG-MH-27198 · RERA P99000008026 · Last updated on MahaRERA portal: 26 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date
  • Completion date moved by 69 months
  • 6 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

STAR HEIGHT is a Others project by ERIC INFRASTRUCTURE in Palghar, Maharashtra, registered with MahaRERA as P99000008026 on 18 Aug 2017. Possession was promised by 5 Mar 2025 and is now 19 months past that date. The completion date has moved by 69 months from the original filing.

At a glance

Project

  • NameSTAR HEIGHT
  • TypeOthers
  • Location
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000008026
  • ReraGenie IDRG-MH-27198

Builder

  • NameERIC INFRASTRUCTURE
  • Entity typePartnership
  • PartnerKIRAN MANISH MEHTA
  • Declared earlier projects1 →

Key dates

19 months past promisethis monthRegisteredAug 2017First promiseJun 2019Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion5 Mar 2025
  • Revised completionRevised to 5 Mar 2025 (originally 30 Jun 2019)
  • Buildings1 building record
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
STAR HEIGHTNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

STAR HEIGHT: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 26 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area621 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2864.18
Proposed, not sanctioned2,864 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch111 SANJAY BUILDING JAWAHAR NAGAR GOREGAON WEST MUMBAI 400062

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJAY WADE & ASSOCIATES
EngineerAPTE ASSOCIATES
Chartered AccountantM SABOO & CO
PartnerRole in project
ERIC INFRASTRUCTURE-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000002004Jun 2019 → Jun 2020

Reason as filed by the promoterTHE BUILDING IS FULLY COMPLETED. ALL FORMALITIES IN RESPECT OF ISSUE OF O.C. IS ALSO COMPLETED. HOWEVER PROCEDURAL DELAYS ARE THERE FOR ISSUE OF O.C. HENCE IT IS REQUESTED FOR EXTENSION FOR SIX MONTHS

EXT99000006124Jun 2019 → Jun 2021

Reason as filed by the promoterDue to Covid-19

EXT99000012265Jun 2019 → Jul 2023

Reason as filed by the promoterBUILDING COMPLETED, OC FORMALITIES COMPLETED PERMISSION FOR OC AWAITED.

EXT99000010102Jun 2019 → Jun 2022

Reason as filed by the promoterDUE TO COVID-19

EXT99000017895Jun 2019 → Sep 2024

Reason as filed by the promoterTECHNICAL DELAY IN ISSUE OF O.C

EXT99000027286Jun 2019 → Mar 2025

Reason as filed by the promoterPost facto extension now proposed date is 30/09/2024 my o.c received on 03/05/2025 please grand me extension up to 03/05/2025

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Apr 2025

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf26 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE.pdf26 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf26 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf26 Apr 2025
Declaration in FORM BFile: Form B.pdf13 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory.pdf13 Mar 2025
Other - TechnicalFile: Technical Balance Pending Work.pdf13 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Form 2A.pdf13 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf13 Mar 2025
Certificates of CA (Form 3)File: FORM 3.pdf23 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf23 Jan 2025
Other - TechnicalFile: MPCB Certificate.pdf20 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf8 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.pdf17 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Form 2A.pdf17 Feb 2024
Certificates of CA (Form 3)File: Form 3.pdf17 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf17 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf21 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Form 2A.pdf21 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf21 Dec 2023
Disclosure of sold/ booked inventoryFile: Discolsure of Sold and Unsold Inventory.pdf1 Nov 2023
Certificates of CA (Form 3)File: FORM 3.pdf13 May 2023
Other - FinanceFile: Self Declaration on Letter Head.pdf13 May 2023
Other - FinanceFile: Self Declaration on Letter Head.pdf13 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf20 Apr 2023
Other - LegalFile: Paper Cutting.pdf20 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Rera Account Statement.pdf13 Apr 2023
Certificates of CA (Form 3)File: Form 3.pdf3 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf2 Dec 2022
Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory.pdf1 Aug 2022
Disclosure of sold/ booked inventoryFile: Sold and Unsold Flat.pdf15 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Vasai Virar CC cum IOD.pdf16 Feb 2022
Certificates of CA (Form 3)File: FORM 3.pdf16 Feb 2022
Certificates of CA (Form 5)File: FORM 5.pdf16 Feb 2022
Declaration about Commencement CertificateFile: Declaration of CC.pdf7 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Form 2A.pdf7 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Form 2A.pdf7 Jul 2021
Disclosure of sold/ booked inventoryFile: Sold And Unsold Units.pdf7 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Fomr 5 2019.pdf7 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2020.pdf7 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2021.pdf7 Jul 2021
Certificates of CA (Form 5)File: Form 5.pdf3 Dec 2018
Layout approvalFile: Layour Plan.pdf29 Jul 2017
Building plan approvalFile: Vasai Virar CC cum IOD.pdf29 Jul 2017
PAN CardFile: Eric Mehta PAN Card.pdf29 Jul 2017
PAN CardFile: Kiran Mehta PAN Card.pdf29 Jul 2017
PAN CardFile: Company PAN CARD.pdf29 Jul 2017
Copy of the legal title reportFile: Legal Title Report.pdf29 Jul 2017
Details of encumbrancesFile: Encumbrence.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layour Plan.pdf29 Jul 2017
Building Plan Approval (IOD)File: Vasai Virar CC cum IOD.pdf29 Jul 2017
Declaration in FORM BFile: Form B Eric.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ajay Wade Architect Certificate.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apte Associates Certificate Engineers.pdf29 Jul 2017
Certificates of CA (Form 3)File: FORM 3.pdf29 Jul 2017
Proforma of Allotment letterFile: Proforma of Allotment Letter.pdf29 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
STAR ENCLAVESTAR ENCLAVE BUILDING NO 1 WING B PUSHPA PARK RESIDENCY VIRAR WEST THANE 4013031CompletedMar 2013Mar 2013

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 69 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep STAR HEIGHT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

2 kmSTAR HEIGHTCompleted 37Lapsed / revoked 20Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: ERIC INFRASTRUCTURE

ERIC INFRASTRUCTURE has 1 registration on MahaRERA, including STAR HEIGHT. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that STAR HEIGHT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if STAR HEIGHT is delayed beyond 5 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of STAR HEIGHT?

The registered promoter entity is ERIC INFRASTRUCTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in STAR HEIGHT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for STAR HEIGHT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at STAR HEIGHT?

The professionals named in the filing: Architect: AJAY WADE & ASSOCIATES; Engineer: APTE ASSOCIATES; Chartered Accountant: M SABOO & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in STAR HEIGHT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About STAR HEIGHT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save STAR HEIGHT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.