Home / Browse projects / Mysore, Karnataka / Srishti Anmol

Registration approved Residential/Group Housing project

Srishti Anmol

By RAKER INFRASTRUCTURE LLP

RG-KA-44253 · RERA PRM/KA/RERA/1268/378/PR/171118/001858 · Last updated on RERA Karnataka portal: 15 Mar 2021

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2020Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 103 documents Report an error

Srishti Anmol is a Residential/Group Housing project by RAKER INFRASTRUCTURE LLP in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/171118/001858 on 18 Nov 2017. Possession is promised by 31 Dec 2020. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSrishti Anmol
  • TypeResidential/Group Housing
  • Location
    • MYSORE
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1268/378/PR/171118/001858
  • ReraGenie IDRG-KA-44253

Builder

  • NameRAKER INFRASTRUCTURE LLP
  • Entity typeOther
  • Authorized SignatoryVISHWANATH N P

Key dates

this monthRegisteredNov 2017First promiseDec 2019Revised toDec 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Nov 2017
  • Promised completion31 Dec 2020
  • Revised completionRevised to 31 Dec 2020 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed103 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Srishti Anmol---35035

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Mar 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 15 Mar 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,132 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 9.80 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHarshavardhana H N
EngineerVinay P Gurkar

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2019 → Jun 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1268/378/PR/210409/001858Jun 2021 → Dec 2020

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed103

As listed on the registration, under the names the promoter filed them with; the newest 80 of 103 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/171118/001858 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Modification Order copyFile: Modification order.pdf15 Mar 2021
Consent LetterFile: New Consent Letter.pdf6 Nov 2020
Full format Consent letterFile: CONSENT LETTER.pdf24 Oct 2020
Modified Plan sanction letterFile: Modified plan license.jpeg24 Oct 2020
Project Extension screenshotFile: Screenshot- Application for extension.png24 Oct 2020
Project Extension screenshotFile: Screenshot- Status of Project applied for extension.png24 Oct 2020
Reply LetterFile: Reply to Notice dt, 14.10.2020.pdf24 Oct 2020
Old Site PlanFile: Site Plan & Elevation.jpg20 Oct 2020
Building PlanFile: Basement, Ground floor, 1st Floor & 2nd floor plan.jpg20 Oct 2020
Undertaking LetterFile: Reply to notice dt 14.10.2020.pdf20 Oct 2020
CertificateFile: Raker Infrastructure LLP.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Modified Plans.pdf-
List Of AllotteesFile: List of allotees.pdf-
Consent LetterFile: Consent Letter.pdf-
Chartered Accountant CertificateFile: charted account.pdf-
Notarized AffidavitFile: Affidavit cum declaration.pdf-
Engineer CertificateFile: eng certificate.pdf-
Architect CertificateFile: Architect certificate.pdf-
Structural Engineer Certificate for stability of structureFile: Stability Certificate.pdf-
Modification of Plan DetailsFile: Srishti Anmol.jpg-
Modification of Plan DetailsFile: Modification Sanction Plan.pdf-
Modification of Plan DetailsFile: Commencement certificate.pdf-
Modification of Plan DetailsFile: Commencement certificate.pdf-
Modification of Plan DetailsFile: List of sold and unsold apartments.pdf-
Modification of Plan DetailsFile: List of sold and unsold apartments.pdf-
Bank StatementFile: Bank Statement .pdf-
Modified Building PlanFile: Modified Building Plan.pdf-
Modified Site PlanFile: Modified Site Plan.pdf-
Clarification LetterFile: Clarification Letter.pdf-
Extension ACK & Fees ReceiptFile: Extension Applied ACK Number and Fees Receipt.pdf-
Architect Certificate for Work Completion Schedule till DateFile: ARC Completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: ENG Status of Work.pdf-
CA Certificate for Funds UtilizationFile: CA fund utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: ARC Pending work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: ENG Pending Work.pdf-
CA Certificate for Funds required for Project CompletionFile: CA funds required.pdf-
AffidavitFile: Affidavit (English).pdf-
Latest Encumbrance CertificateFile: EC.pdf-
Consent letter from 2/3rd of AllotteesFile: Concern Letter.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Bank statement 01-07-17 to 05-02-20.pdf-
Document 2File: Compensation Affidavit.pdf-
Document 3File: Commencement certificate.pdf-
Document 4File: Under taking letter for modified Plan and Extension.pdf-
Document 5File: Undertaking Letter for 21 units.pdf-
Document 6File: Under Taking letter for modification.pdf-
Document 7File: Clarification regarding 35 units.pdf-
Document 8File: Modified Sanction Plan.pdf-
Document 9File: Commencement Certificate Undertaking Letter.pdf-
Document 10File: Under taking letter for modified Plan and Extension.pdf-
Document 11File: Commencement certificate.pdf-
Document 12File: Plans.jpg-
Document 13File: Raker Infrastructure.jpeg-
Srishti Anmol-
Srishti Anmol-
Agreement to sale-
Agreement to sale-
Srishti Anmol-
Srishti Anmol-
land doc-
Srishti Anmol-
Srishti Anmol-
Agreement to sale-
front-
plan-
back-
EC 2004-2017-
Katha-2015-
JDA Agreement-
Balance Sheet 2015 - 2016File: BS.pdf-
Balance Sheet 2014 - 2015File: BS.pdf-
Balance Sheet 2013 - 2014File: BS.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P & L.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P & L.pdf-
Audited Profit and Loss Statement 2013 - 2014File: P & L.pdf-
Director's Report 2015 - 2016File: DR.pdf-
Director's Report 2014 - 2015File: DR.pdf-
Director's Report 2013 - 2014File: DR.pdf-
Cash Flow Statement 2015 - 2016File: C F.pdf-
Cash Flow Statement 2014 - 2015File: C F.pdf-

How this compares with Mysore

28%of Mysore projects moved their completion datethis one moved by 12 months
0%of Mysore registrations are shown as withdrawn or revokedthis one is not

Computed across the 700+ Mysore projects on ReraGenie, from their own filings.

Keep Srishti Anmol on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mysore700+ in Mysore

2 kmSrishti AnmolOther 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: RAKER INFRASTRUCTURE LLP

RAKER INFRASTRUCTURE LLP has 1 registration on RERA Karnataka, including Srishti Anmol. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.

Frequently asked questions

What are my rights if Srishti Anmol is delayed beyond 31 Dec 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Srishti Anmol?

The registered promoter entity is RAKER INFRASTRUCTURE LLP. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Srishti Anmol?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Srishti Anmol?

The professionals named in the filing: Architect: Harshavardhana H N; Engineer: Vinay P Gurkar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Srishti Anmol?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Srishti Anmol. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Srishti Anmol to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.