Registration approved Mixed Development project

Sri Devidayal La Grace

By Devidayal Shetty

RG-KA-13931 · RERA PRM/KA/RERA/1257/334/PR/210804/004236 · Last updated on RERA Karnataka portal: 7 Jul 2021

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 2 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jun 2023Possession promisedmoved 2 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 82 documents Report an error

Sri Devidayal La Grace is a Mixed Development project by Devidayal Shetty in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/210804/004236 on 4 Aug 2021. Possession is promised by 30 Jun 2023. The completion date has moved by 2 months from the original filing.

At a glance

Project

  • NameSri Devidayal La Grace
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/210804/004236
  • ReraGenie IDRG-KA-13931

Builder

  • NameDevidayal Shetty
  • Entity typeProprietorship Firm
  • Authorized SignatoryDevidayal Shetty
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2021First promiseApr 2023Revised toJun 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Aug 2021
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 30 Apr 2023)
  • Buildings1 building record
  • Documents filed82 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sri Devidayal La Grace-----20

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 7 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
Basement Floor for car park-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 7 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area607 sq m
Named landowners1
LandownerVillageDistrict
Lawrence Dsouza--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.72 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSubramanya
EngineerK Anil Hegde

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1257/334/PR/230802/004236Apr 2023 → Jun 2023

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed82

As listed on the registration, under the names the promoter filed them with; the newest 80 of 82 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/210804/004236 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
self declaration cum affidavit regarding no ITR filled during the financial year 17-18File: self declaration affidavit.pdf7 Jul 2021
GST Registration CertificateFile: REGISTRATION CERTIFICATE - GST.pdf29 Jun 2021
Development details filled on the site screenshotFile: development details.jpg29 Jun 2021
Firm Registration CertificateFile: REGISTRATION CERTIFICATE - GST.pdf14 Jun 2021
Form BFile: Form B.pdf14 Jun 2021
EC from 01/04/2004 to 11/01/2021File: EC 2.pdf14 Jun 2021
EC from 12/01/2021 to 10/06/2021File: EC 3.pdf14 Jun 2021
Building approved drawing (Basement Floor and Ground Floor)File: Approved plan Sheet 1.pdf14 Jun 2021
Building approved drawing ( Sanctioned site, Typical floor plans, Elevation, Section plan)File: Approved plan Sheet 2.pdf14 Jun 2021
Building License LetterFile: Building Approved License.pdf14 Jun 2021
CertificateFile: REGISTRATION CERTIFICATE - GST.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Status of work.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Status of work.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate - Fund Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Pending Work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Pending work.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Certificate - Funds Required .pdf-
AffidavitFile: Form Ex7.pdf-
Latest Encumbrance CertificateFile: yeyyadi site EC 15 years.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails 1.xlsx-
Document 1File: Form B.pdf-
Document 2File: EC last one month till 16 april .pdf-
LICENSE-
BUILDING LICENCE & PLAN-
single site approval-
Lawrence Will-
MOU-
RTC-
BUILDING LICENCE & PLAN-
Property card-
La Grace Brochure-
specification La grace-
EC 2-
AFFIDAVIT-
AFFI CUM DECL-
khatha-
JDA-
Probate-
conversion-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
fire noc Lagrace-
Unnamed document-
Unnamed document-
Unnamed document-
PCB NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
single site approval-
BUILDING LICENCE & PLAN-
Unnamed document-
Balance Sheet 2018 - 2019File: Balance Sheet 2020.pdf-
Balance Sheet 2017 - 2018File: Balance Sheet 2019.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Profit and loss 2020.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Profit and loss 2019.pdf-
Cash Flow Statement 2018 - 2019File: CASH FLOW 2020.pdf-
Auditor's Report 2018 - 2019File: auditors report 2020.pdf-
Auditor's Report 2017 - 2018File: Auditors report 2019.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR acknowlegdement 20-21.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR acknowledgement 19-20.pdf-
FORM B-
Prospectus/BrochureFile: La Grace Brochure.pdf-
Advertisement Copy 1File: La Grace hoarding .pdf-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_210804_004236 AREA.xlsx-
Occupancy CertificateFile: occupancy certificate.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect's Form 5 Certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4CC - La Grace.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: affidavit cum decleration for rera completion.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Sri Devidayal ARA-CompletedApr 2023No date filed

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 2 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep Sri Devidayal La Grace on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmSri Devidayal La GraceOther 58Dot size: filed unitsN

Filed coordinates, straight-line distance. 58 registered projects within 2 km.

Builder: Devidayal Shetty

Devidayal Shetty has 1 registration on RERA Karnataka, including Sri Devidayal La Grace. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if Sri Devidayal La Grace is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sri Devidayal La Grace?

The registered promoter entity is Devidayal Shetty, a proprietorship firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sri Devidayal La Grace?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Sri Devidayal La Grace?

The professionals named in the filing: Architect: Subramanya; Engineer: K Anil Hegde. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sri Devidayal La Grace?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sri Devidayal La Grace. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sri Devidayal La Grace to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.