Home / Browse projects / Pune, Maharashtra / Square One

Registration lapsed No litigation declared Others project

Square One

By Kokane - Waghere Associates

RG-MH-04782 · RERA P52100020339 · Last updated on MahaRERA portal: 29 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 46 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
9 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 90%
15 of 53Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 136 documents Report an error

Square One is a Others project by Kokane - Waghere Associates in Pune, Maharashtra, registered with MahaRERA as P52100020339 on 5 Apr 2019. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 46 months from the original filing. 38 of the 53 units on this registration are recorded sold or booked, and 9 of 22 construction stages are filed complete.

At a glance

Project

  • NameSquare One
  • TypeOthers
  • Location
    • S No 48 Hissa no 2b/2
    • Rahatani
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411017
  • Pincode411017
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100020339
  • ReraGenie IDRG-MH-04782

Builder

  • NameKokane - Waghere Associates
  • Entity typePartnership
  • PartnerVaishali Mahadrang Waghere

Key dates

4 months past promisethis monthRegisteredApr 2019First promiseAug 2022Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Apr 2019
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 28 Aug 2022)
  • Buildings2 building records
  • Documents filed136 files

Current status

72%38 of 53 units booked
82.0%Work done, per cost certificate

Figures as on 29 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA9831233
Building BNA6520020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

Building A64%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Building B55%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed89

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots89
Closed/Covered21
Open Space68
BuildingClosed/CoveredOpen SpaceTotal
Building A136881
Building B808

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,672 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Dec 2025
LandownerVillageDistrict
Rajendra Eknath KawadePimpri Chinchawad (M Corp.)Pune
Abbas Gulam MullaPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI3892.37
Proposed, not sanctioned3,892 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchS No 153, Opp Pk international school Pimple Saudagar
Estimated costRs 11.05 cr
Cost incurredRs 9.06 cr
Work done81.98%
BuildingWingEstimatedIncurred
Building ANARs 4.70 crRs 4.11 cr
Building BNARs 4.70 crRs 4.11 cr
-NARs 1.66 crRs 84.69 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchitect Vipul Vilaskumar Pagariya
EngineerMayur Gaikwad
EngineerAkash Gaikwad
Chartered AccountantP H Pandhare and Associates
Chartered AccountantRohit Mane
PartnerRole in project
Kokane - Waghere Associates-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013376Aug 2022 → Aug 2023

Reason as filed by the promoter1) Due to global pandemic labour shortage was there and material was not getting available 2) Due to global pandemic sales of units was slow due to which funds for construction affected construction work. 3) Due to lockdown 2 in year 2021 construction completion got delayed and due to that we were unable to get PCMC completion certificate

EXT52100017412Aug 2022 → Dec 2025

Reason as filed by the promoterWe have taken one year extention earlier this year but we received revised sanctioned plan amd commencement certificate 31032023 with reference to this , we required additional time to complete with construction work and sale of remaining flats , We are attaching existing customers consents for the same

EA25122518991Aug 2022 → Jun 2026

Reason as filed by the promoterThe Project is already completed and delayed marginally as can be verified from the PERT chart and attached Photoes. The delay in completion of the project “Square One” (MAHARERA Registration No. P52100020339) is due to multiple unavoidable factors. Prolonged and heavy monsoon rains disrupted construction activities, causing frequent work stoppages and site access issues. The project also faced acute shortage of skilled labour due to large-scale migration during and after the pandemic, affecting construction progress. Further, steep escalation in construction material costs, especially cement

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed136

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 136 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf29 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf29 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf29 Jan 2026
Withdrawal Update Form 1File: form 1 30-09-2025.pdf25 Dec 2025
Withdrawal Update Form 2File: form 2 30-09-2025.pdf25 Dec 2025
Withdrawal Update Form 3File: form 3 30-09-2025.pdf25 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf16 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf16 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf16 Dec 2025
Declaration about Commencement CertificateFile: Declaration of Commencement.pdf22 Mar 2025
Layout approvalFile: LAYOUT REVISED 2024.pdf28 Feb 2025
Copy of Layout Approval (in case of layout)File: LAYOUT REVISED 2024.pdf28 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 24-25 Q2.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 24-25 Q1.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 23-24 Q4.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 22-23 Q2.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 23-24 Q3.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 23-24 Q2.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 23-24 Q1.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 22-23 Q4.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 22-23 Q3.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 22-23 Q1.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 21-22 Q4.pdf24 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FY 22-23.pdf24 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FY 23-24.pdf24 Feb 2025
Certificates of CA (Form 3)File: FY 24-25 Q3.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: FY 24-25 Q3.pdf21 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2023.pdf21 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2024.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 20-21.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 19-20.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 24-25 Q3.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 24-25 Q2.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 24-25 Q1.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 23-24 Q4.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 23-24 Q3.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 23-24 Q2.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 23-24 Q1.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 22-23 Q4.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 22-23 Q3.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 22-23 Q2.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 22-23 Q1.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 21-22 Q4.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 21-22 Q3.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 22-23 Q1.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 24-25 Q2.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 24-25 Q1.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 23-24 Q4.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 23-24 Q3.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 23-24 Q2.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 23-24 Q1.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 22-23 Q4.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 22-23 Q3.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 22-23 Q2.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 21-22 Q4.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 21-22 Q3.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 20-21.pdf20 Feb 2025
Certificates of CA (Form 3)File: FY 19-20.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 21-22 Q4.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 24-25 Q3.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 24-25 Q2.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 24-25 Q1.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 23-24 Q4.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 23-24 Q3.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 23-24 Q2.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 23-24 Q1.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 22-23 Q3.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 22-23 Q2.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 22-23 Q1.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 21-22 Q3.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 20-21.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 19-20.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 22-23 Q4.pdf20 Feb 2025
Building plan approvalFile: HPSC3022 (1).pdf18 Oct 2024
Building plan approvalFile: HPSC3024 (1).pdf18 Oct 2024
Building plan approvalFile: HPSC3023 (2).pdf18 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: 20241015084106 (2)-compressed.pdf18 Oct 2024
Building Plan Approval (IOD)File: HPSC3022 (1).pdf18 Oct 2024
Building Plan Approval (IOD)File: HPSC3023 (2).pdf18 Oct 2024
Building Plan Approval (IOD)File: HPSC3024 (1).pdf18 Oct 2024

How this compares with Pune

72%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 46 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Square One on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Rahatani13,700+ in Pune

2 kmSquare OneCompleted 89Lapsed / revoked 43Other 56Dot size: filed unitsN

Filed coordinates, straight-line distance. 188 registered projects within 2 km.

Builder: Kokane - Waghere Associates

Kokane - Waghere Associates has 1 registration on MahaRERA, including Square One. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Square One shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Square One is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Square One?

The registered promoter entity is Kokane - Waghere Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Square One?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Square One?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Square One?

The professionals named in the filing: Architect: Architect Vipul Vilaskumar Pagariya; Engineer: Mayur Gaikwad; Engineer: Akash Gaikwad; Chartered Accountant: P H Pandhare and Associates; Chartered Accountant: Rohit Mane. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Square One?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Square One. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Square One to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.