Home / Browse projects / Pune, Maharashtra / Square One
Square One
By Kokane - Waghere Associates
RG-MH-04782 · RERA P52100020339 · Last updated on MahaRERA portal: 24 Oct 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 52 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Square One is a Others project by Kokane - Waghere Associates in Pune, Maharashtra, registered with MahaRERA as P52100020339 on 5 Apr 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 52 months from the original filing. 39 of the 53 units on this registration are recorded sold or booked, and 11 of 22 construction stages are filed complete.
At a glance
Project
- NameSquare One
- TypeOthers
- Location
- S No 48 Hissa no 2b/2
- Rahatani
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 411017
- Pincode411017
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100020339
- ReraGenie IDRG-MH-04782
Builder
- NameKokane - Waghere Associates
- Entity typePartnership
- PartnerVaishali Mahadrang Waghere
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Apr 2019
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 28 Aug 2022)
- Buildings2 building records
- Documents filed160 files
Current status
Figures as on 24 Oct 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 9 | 8 | 31 | 2 | 33 |
| Building B | NA | 6 | 5 | 20 | 0 | 20 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 90%.
Building A73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Building B73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 24 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed89
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building A | 13 | 68 | 81 |
| Building B | 8 | 0 | 8 |
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Rajendra Eknath Kawade | Pimpri Chinchawad (M Corp.) | Pune |
| Abbas Gulam Mulla | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building A | NA | Rs 4.70 cr | Rs 4.70 cr |
| Building B | NA | Rs 4.70 cr | Rs 4.70 cr |
| - | NA | Rs 1.66 cr | Rs 1.06 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Architect Vipul Vilaskumar Pagariya |
| Engineer | Mayur Gaikwad |
| Engineer | Akash Gaikwad |
| Chartered Accountant | P H Pandhare and Associates |
| Chartered Accountant | Rohit Mane |
| Partner | Role in project |
|---|---|
| Kokane - Waghere Associates | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) Due to global pandemic labour shortage was there and material was not getting available 2) Due to global pandemic sales of units was slow due to which funds for construction affected construction work. 3) Due to lockdown 2 in year 2021 construction completion got delayed and due to that we were unable to get PCMC completion certificate
Reason as filed by the promoterWe have taken one year extention earlier this year but we received revised sanctioned plan amd commencement certificate 31032023 with reference to this , we required additional time to complete with construction work and sale of remaining flats , We are attaching existing customers consents for the same
Reason as filed by the promoterThe Project is already completed and delayed marginally as can be verified from the PERT chart and attached Photoes. The delay in completion of the project “Square One” (MAHARERA Registration No. P52100020339) is due to multiple unavoidable factors. Prolonged and heavy monsoon rains disrupted construction activities, causing frequent work stoppages and site access issues. The project also faced acute shortage of skilled labour due to large-scale migration during and after the pandemic, affecting construction progress. Further, steep escalation in construction material costs, especially cement
Reason as filed by the promoterDelay for the project reason Shortage of Labour ,Temporary Financial Constraints and Requirement and Purchase of TDR
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Feb 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Oct 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Aug 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Aug 2026
Documents filed160
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 160 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form No 1 24-25 Q4.pdf | 24 Oct 2026 |
| Form 2File: Form No 2 24-25 Q4.pdf | 24 Oct 2026 |
| Form 3File: Form No 3 24-25 Q4.pdf | 24 Oct 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf | 24 Oct 2026 |
| Form 5 (FY 2024-2025)File: Form no 5 fy 2024-25.pdf | 23 Oct 2026 |
| Withdrawal Update Form 1File: Form No 1 FY 26-27 Q1.pdf | 8 Oct 2026 |
| Withdrawal Update Form 1File: Form No 1 FY 26-27 Q1.pdf | 8 Oct 2026 |
| Withdrawal Update Form 2File: Form No 2 FY 26-27 Q1.pdf | 8 Oct 2026 |
| Withdrawal Update Form 2File: Form No 2 FY 26-27 Q1.pdf | 8 Oct 2026 |
| Withdrawal Update Form 3File: Form No 3 FY 26-27 Q1.pdf | 8 Oct 2026 |
| Withdrawal Update Form 3File: Form No 3 FY 26-27 Q1.pdf | 8 Oct 2026 |
| Form 2A (FY 2024-2025)File: Form 2A_25-26.pdf | 8 Oct 2026 |
| Commencement certificateFile: A Wing Part completion Certificate.pdf | 18 Aug 2026 |
| Withdrawal Update Form 1File: Form No 1 FY 26-27 Q1.pdf | 18 Aug 2026 |
| Withdrawal Update Form 2File: Form No 2 FY 26-27 Q1.pdf | 18 Aug 2026 |
| Withdrawal Update Form 3File: Form No 3 FY 26-27 Q1.pdf | 18 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A fy 25-26.pdf | 18 Aug 2026 |
| Form 5 (FY 2025-2026)File: Form 5 fy 25-26.pdf | 18 Aug 2026 |
| Withdrawal Update Form 1File: Form No 1 25-26 Q4.pdf | 1 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 25-26 Q4.pdf | 1 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 25-26 Q4.pdf | 1 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 25-26 Q4.pdf | 26 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 25-26 Q4.pdf | 26 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 25-26 Q4.pdf | 26 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 29 Jan 2026 |
| Withdrawal Update Form 1File: form 1 30-09-2025.pdf | 25 Dec 2025 |
| Withdrawal Update Form 2File: form 2 30-09-2025.pdf | 25 Dec 2025 |
| Withdrawal Update Form 3File: form 3 30-09-2025.pdf | 25 Dec 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 16 Dec 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 16 Dec 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 16 Dec 2025 |
| Declaration about Commencement CertificateFile: Declaration of Commencement.pdf | 22 Mar 2025 |
| Layout approvalFile: LAYOUT REVISED 2024.pdf | 28 Feb 2025 |
| Copy of Layout Approval (in case of layout)File: LAYOUT REVISED 2024.pdf | 28 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 24-25 Q2.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 24-25 Q1.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 23-24 Q4.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 22-23 Q2.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 23-24 Q3.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 23-24 Q2.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 23-24 Q1.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 22-23 Q4.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 22-23 Q3.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 22-23 Q1.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 21-22 Q4.pdf | 24 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FY 22-23.pdf | 24 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FY 23-24.pdf | 24 Feb 2025 |
| Certificates of CA (Form 3)File: FY 24-25 Q3.pdf | 21 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: FY 24-25 Q3.pdf | 21 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2023.pdf | 21 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2024.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 20-21.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 19-20.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 24-25 Q3.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 24-25 Q2.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 24-25 Q1.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 23-24 Q4.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 23-24 Q3.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 23-24 Q2.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 23-24 Q1.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 22-23 Q4.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 22-23 Q3.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 22-23 Q2.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 22-23 Q1.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 21-22 Q4.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FY 21-22 Q3.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 22-23 Q1.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 24-25 Q2.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 24-25 Q1.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 23-24 Q4.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 23-24 Q3.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 23-24 Q2.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 23-24 Q1.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 22-23 Q4.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 22-23 Q3.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 22-23 Q2.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 21-22 Q4.pdf | 20 Feb 2025 |
| Certificates of CA (Form 3)File: FY 21-22 Q3.pdf | 20 Feb 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 160 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Square One on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Rahatani14,000+ in Pune
Filed coordinates, straight-line distance. 192 registered projects within 2 km.
THE ARENA
RION BUILDTECH PRIVATE LIMITED
VARDHAMAN SKYTOWN
VARDHAMAN ASSOCIATES
Tamara
Goldfinger Kataria Urban Developments
Sindhu Skies
G K Wonders
Legacy Kairos A and B Building
Legacy Lifespaces LLP
Amberwood Phase 1
SMP NAMRATA ASSOCIATES
Builder: Kokane - Waghere Associates
Kokane - Waghere Associates has 1 registration on MahaRERA, including Square One. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Square One is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Square One?
The registered promoter entity is Kokane - Waghere Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Square One?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Square One?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Square One?
The professionals named in the filing: Architect: Architect Vipul Vilaskumar Pagariya; Engineer: Mayur Gaikwad; Engineer: Akash Gaikwad; Chartered Accountant: P H Pandhare and Associates; Chartered Accountant: Rohit Mane. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Square One?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback