Home / Browse projects / Raigarh, Maharashtra / Sparsh Phase-III

Registration lapsed No litigation declared Others project

Sparsh Phase-III

By Shree Enterprises

RG-MH-28963 · RERA P52000027334 · Last updated on MahaRERA portal: 10 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 80%
126 of 126Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

Sparsh Phase-III is a Others project by Shree Enterprises in Raigarh, Maharashtra, registered with MahaRERA as P52000027334 on 2 Dec 2020. Possession was promised by 30 Jun 2025 and is now 16 months past that date. 0 of the 126 units on this registration are recorded sold or booked, and 0 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSparsh Phase-III
  • TypeOthers
  • Location
    • Street
    • Shedung
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000027334
  • ReraGenie IDRG-MH-28963

Builder

  • NameShree Enterprises
  • Entity typePartnership
  • GSTIN27ACAFS4593E1Z0
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerAjay P Patil
  • Other registrations23 more →
  • Completed7 of 24
  • No longer live10 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

16 months past promisethis monthRegisteredDec 2020PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Dec 2020
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings2 building records
  • Documents filed61 files

Current status

0%0 of 126 units booked
1.4%Work done, per cost certificate

Figures as on 10 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No 1NA5524933
Building No 2NA75722193

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 10 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 80%.

Building No 10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 27%
ActivityProgress
Excavation80%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 10 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Club HouseYes0%

Parking filed91

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots91
Closed/Covered91
BuildingClosed/CoveredTotal
Building No 12121
Building No 27070

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area913 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Oct 2025
LandownerVillageDistrict
Dinesh Mangalchand JainBorivaliMumbai Suburban
Jawanmal Chimanlal ShahAndheriMumbai Suburban
Pandurang Raoji PatilNavi Mumbai (M Corp.)Thane

Approvals and building plan

Sanctioning authorityMaharashtra State Road Development Corporation Limited
Permissible FSI4882.95
Proposed, not sanctioned3,779 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSector 1, Vashi Navi Mumbai
Estimated costRs 10.92 cr
Cost incurredRs 15.60 lakh
Work done1.43%
BuildingWingEstimatedIncurred
Building No 2NARs 7.25 crRs 11.85 lakh
Building No 1NARs 3.00 crRs 3.75 lakh
-NARs 67.10 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA N Arch Architect & Planner
EngineerSabu Scaria
EngineerAmol R Dhumal
Chartered AccountantBRB Associates
Chartered AccountantM G Suthar & Associates
Chartered AccountantBrajesh
PartnerRole in project
Shree Enterprises-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12501224Madhukar Baburao DholeShree Enterprises13/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Nov 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2022-2023)File: 2022-23_Form-5.pdf10 Jan 2026
Form 1File: FORM 1.pdf8 Jul 2025
Form 2File: FORM 2.pdf8 Jul 2025
Form 3File: Form 3.pdf8 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf8 Jul 2025
Form 2A (FY 2023-2024)File: FORM 2A 2023-24.pdf8 Jul 2025
Form 5 (FY 2023-2024)File: From 5.pdf8 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30062024 Phase III.pdf10 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE SPARSH PHASE III 30062024.pdf10 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH III Engineer Certificate 30092024.pdf10 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: From 5 Sparsh PH III.pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202212_Ar.pdf25 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202303_Ar.pdf25 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202306_Ar.pdf25 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202309_Ar.pdf25 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202312_Ar.pdf25 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202212_Er.pdf25 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202303_Er.pdf25 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202306_Er.pdf25 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202309_Er.pdf25 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202312_Er.pdf25 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2023-24_Form-2A.pdf25 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202112_CA.pdf25 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202103_CA.pdf25 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202209_CA.pdf25 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202212_CA.pdf25 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202303_CA.pdf25 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-21_Form-5.pdf25 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202206_Ar.pdf7 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202209_Ar.pdf7 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202206_Er.pdf7 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202209_Er.pdf7 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202103_Ar.pdf27 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202112_Ar.pdf27 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202203_Ar.pdf27 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202103_Er.pdf27 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202112_Er.pdf27 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202203_Er.pdf27 May 2022
OtherFile: Proposed_02.pdf28 Nov 2020
Layout approvalFile: Plan_Part1.pdf27 Nov 2020
Building plan approvalFile: Plan_Part2-1.pdf27 Nov 2020
Building plan approvalFile: Plan_Part3-1.pdf27 Nov 2020
Building plan approvalFile: Plan_Part4-1.pdf27 Nov 2020
Building plan approvalFile: Plan_Part5.pdf27 Nov 2020
Building plan approvalFile: Plan_Part6.pdf27 Nov 2020
PAN CardFile: Shree PAN.pdf27 Nov 2020
Copy of the legal title reportFile: Title Report.pdf27 Nov 2020
Copy of the legal title reportFile: Search Report.pdf27 Nov 2020
Details of encumbrancesFile: No Encumbrance.pdf27 Nov 2020
Copy of Layout Approval (in case of layout)File: Plan_Part1.pdf27 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan_Part2-1.pdf27 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan_Part3-1.pdf27 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan_Part4-1.pdf27 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan_Part5.pdf27 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan_Part6.pdf27 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf27 Nov 2020
Declaration in FORM BFile: Form-B.pdf27 Nov 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar.PDF27 Nov 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er.pdf27 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf27 Nov 2020
Proforma of Allotment letterFile: Binder1.pdf27 Nov 2020

How this compares with Raigarh

0%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sparsh Phase-III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shedung5,900+ in Raigarh

2 kmSparsh Phase-IIICompleted 5Lapsed / revoked 3Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: Shree Enterprises

SHREE ENTERPRISES has 24 registrations on MahaRERA, including SHREE TULSI KUNJ and SILVER DREAMS. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Sparsh Phase-III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sparsh Phase-III is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sparsh Phase-III?

The registered promoter entity is Shree Enterprises, a partnership as per the filing. Its GSTIN 27ACAFS4593E1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sparsh Phase-III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sparsh Phase-III?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sparsh Phase-III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sparsh Phase-III?

The professionals named in the filing: Architect: A N Arch Architect & Planner; Engineer: Sabu Scaria; Engineer: Amol R Dhumal; Chartered Accountant: BRB Associates; Chartered Accountant: M G Suthar & Associates; Chartered Accountant: Brajesh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sparsh Phase-III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sparsh Phase-III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sparsh Phase-III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.